Facts
The Petitioner, a confectionery and beverages manufacturer, obtained formal sanctions from the Maharashtra State Electricity Distribution Company Ltd (MSEDCL) for an additional power supply of 4689 KV at its manufacturing plant in Induri, Pune
Source reference: para. 3.2, 3.4Upon securing permissions and no-objection certificates from MSEDCL, MIDC, Zilla Parishad, and the Village Panchayat, the Petitioner initiated the laying of an underground High Tension (HT) cable across a 14 km stretch between the Ambi sub-station and its factory
Source reference: para. 3.5, 3.6The Petitioner successfully executed 13.8 km of the project but was obstructed by Respondents Nos. 1 to 8 from completing the final 200 meters abutting Gat No. 391
Source reference: para. 3.7, 3.8The Petitioner filed a Regular Civil Suit for a permanent injunction and sought a temporary injunction (Exhibit 5)
Source reference: para. 3.8, 3.9The Respondents resisted, claiming the Petitioner was laying cables through their private properties rather than the public road margin
Source reference: para. 3.11The Civil Judge rejected the temporary injunction application on the grounds that the Petitioner failed to establish a prima facie case, that the balance of convenience favored the Respondents, and that an alternate remedy existed under Rule 3 of the Works of Licensees Rules, 2006
Source reference: para. 3.13The District Judge dismissed the subsequent appeal
Source reference: para. 3.15Aggrieved, the Petitioner invoked the supervisory jurisdiction of the High Court under Article 227 of the Constitution of India
Source reference: para. 2, 3.16Issues
1. Whether the High Court is justified in interfering with concurrent discretionary findings of the sub-ordinate courts under Article 227 of the Constitution of India
Source reference: para. 21, 232. Whether the Petitioner established the requisite legal triad—prima facie case, balance of convenience, and irreparable injury—to justify a temporary injunction restraining the Respondents from obstructing infrastructure works
Source reference: para. 40, 413. Whether the statutory mechanism under Rule 3 of the Works of Licensees Rules, 2006 operates as an alternative efficacious remedy that bars civil court jurisdiction to grant injunctive relief
Source reference: para. 39, 40Law Applied
The Court applied the principles governing Article 227 of the Constitution of India, observing that while supervisory jurisdiction must be used sparingly, interference is warranted in instances of patent error of law, perversity, or grave miscarriage of justice (Rajendra Diwan v. Pradeep Kumar Ranibala)
Source reference: para. 21, 22Sections 10 and 16 of the Indian Telegraph Act, 1885 govern the execution of telegraph/electricity lines across immovable property, stipulating that unobstructed access is imperative for public infrastructure, and the remedy for aggrieved landowners lies strictly in financial compensation, not obstruction (Power Grid Corporation of India Limited v. Century Textiles And Industries Limited and Century Rayon Limited v. IVP Limited)
Source reference: para. 33, 35, 36Rule 3 of the Works of Licensees Rules, 2006 provides an administrative mechanism to handle obstructions only where the objector's proprietary status over the disputed land parcel is undisputed or indisputable
Source reference: para. 39, 40Regarding injunctions, the Court applied the standard test of prima facie case, balance of convenience, and irreparable loss (Hubbard v. Vosper and Ramakant Ambalal Choksi v. Harish Ambalal Choksi)
Source reference: para. 42, 43Interim relief partaking the character of final relief may be granted in rare, exceptional cases where its refusal would result in immediate, extreme hardship (Deoraj v. State of Maharashtra)
Source reference: para. 50, 51Reasoning
The High Court observed that both lower courts committed a gross and perverse error of law by failing to properly appreciate the evidentiary weight of the Court Commissioner's local inspection report
Source reference: para. 30The report by the Executive Engineer explicitly verified the physical existence of an established public road (Other District Road No. 61) on the disputed stretch, fracturing the Respondents' claim of exclusive private ownership
Source reference: para. 24, 25, 31The High Court rejected the argument that dedications to a single consumer strip the distribution infrastructure of its statutory status under the Electricity Act, reinforcing that infrastructure development remains a protected activity in the larger public interest
Source reference: para. 37, 38Because the Respondents failed to offer prima facie proof of title over the road parcel, the lower courts erred in applying the statutory bar under Rule 3 of the Works of Licensees Rules, 2006, which comes into play only when title is clear
Source reference: para. 39, 40Assessing the parameters of injunction, the Court observed that the Petitioner had completed 13.8 km of the 14 km stretch, meaning a refusal to grant relief would render massive capital expenditure entirely nugatory, tilting the balance of convenience heavily in the Petitioner's favor
Source reference: para. 44, 47Conversely, the deployment of Horizontal Directional Drilling (HDD)—a specialized trenchless technology—ensured minimal surface damage
Source reference: para. 45, 46Any minor damage is financially compensable under the Indian Telegraph Act, meaning the Respondents faced no risk of irretrievable loss
Source reference: para. 33, 47Finally, although the temporary injunction resembled final relief, the high threshold of a "strong prima facie case" was met, justifying immediate protection from immediate and pressing injury
Source reference: para. 50-52Holding
The High Court allowed the Writ Petition, quashing and setting aside the orders dated 12th July 2024 and 30th August 2025 passed by the Civil Judge and District Judge respectively
The Petitioner’s application for a temporary injunction was allowed, restraining the Respondents from obstructing the project
Source reference: para. 54(iii)The holding was conditioned upon the Petitioner: (a) strictly adhering to administrative permissions and utilizing the HDD boring method to cause minimum land damage, and (b) executing a security deposit of Rs. 20,00,000 before the trial court to secure potential future compensation claims by the Respondents
Source reference: para. 54(iii)(a), (b)No order was made as to costs
Source reference: para. 54(e)Original Court PDF
Mondelez India Foods Private LimitedvsVishal Pansare And Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in