Facts
The Appellant developed a 16 MW Hydro Electric Project in Himachal Pradesh
Source reference: para. 2It entered into a Power Purchase Agreement (PPA) with the Respondent Board (HPSEB) on 05.07.2004 at a tariff of Rs. 2.25/kWh, based on an initial Design Energy of 78.81 MU (revised to 78.02 MU)
Source reference: paras. 11, 13, 69In a previous round of litigation (Patikari-1), this Tribunal granted the Appellant liberty to approach the State Commission (HPERC) if actual river discharge was significantly lower than the DPR data, provided such change "endangered the existence" of the project
Source reference: paras. 19, 67The Appellant filed Petition No. 74 of 2017 seeking a downward revision of Design Energy to 56.98 MU and a tariff increase to Rs. 3.11/kWh due to lower water inflows
Source reference: paras. 20, 21HPERC dismissed the petition via orders dated 21.11.2018 and 15.05.2020, holding that lower generation alone does not justify reopening a PPA or revising design energy
Source reference: paras. 23, 24Issues
1. Whether the HPERC is empowered to reopen or modify a concluded PPA to revise tariff based on changed hydrological circumstances.
Source reference: paras. 22, 49, 782. Whether the reduction in river discharge was of such magnitude as to "endanger the existence" of the project, thereby warranting a tariff hike.
Source reference: paras. 67, 68Law Applied
Electricity Act, 2003, specifically Sections 61 and 62 regarding tariff determination
Source reference: para. 21Regulation 6(1) of the HPERC (Power Procurement from Renewable Sources...) Regulations, 2007, which permits modification of PPAs under specific conditions
Source reference: paras. 15, 47The "litmus test" for relief was derived from the Tribunal’s own binding precedent in Patikari-1 (Appeal 179/2010), which held that a project’s tariff can only be reconsidered if natural factors beyond the developer’s control endanger its very "existence"
Source reference: paras. 64, 68GUVNL v. Solar Semiconductor (2017), which limits the power of Commissions to override PPAs unless specifically authorized by subsequent legislation
Source reference: para. 51Return on Equity (RoE) is a business risk and lower returns do not constitute a ground for reopening a voluntary contract
Source reference: para. 76Reasoning
The Tribunal focused on whether the lower hydrology posed an "existential threat" to the project, defining "existence" as the ability to meet Operation Maintenance (OM) expenses and stay operational
Source reference: para. 68On a technical review, the Tribunal found that while Design Energy was 78.02 MU, the average theoretical generation based on measured data was 74.53 MU
Source reference: para. 69Financial analysis revealed that the rational expectation of annual revenue at the DPR stage was approximately Rs. 1660 Lakh, while the actual average revenue was approximately Rs. 1635 Lakh—a negligible reduction of only 1.5%
Source reference: paras. 69, 70Furthermore, normative OM expenses for a 16 MW plant were estimated at Rs. 360 Lakh, which consumed only about 22% of the average annual revenue, leaving a substantial margin for debt servicing
Source reference: para. 72The Tribunal noted the project was operated efficiently with 99.38% machine availability
Source reference: para. 73It rejected the Appellant's claims of financial distress, noting that the Appellant failed to provide a detailed account of revenue application or prove that occasional debt-servicing difficulties amounted to systemic unviability
Source reference: paras. 75, 77Holding
The Tribunal dismissed both appeals
It held that the Appellant failed to establish that the change in hydrology was of such magnitude as to endanger the project's existence or render it unviable
Source reference: para. 77The Tribunal further held that since the claim failed on merits, the legal question of whether the Commission could modify a PPA retrospectively remained theoretical and unnecessary to decide
Source reference: para. 78All pending applications were disposed of
Source reference: p. 32Original Court PDF
M/s Patikari Power Pvt. Ltd.vsHimachal Pradesh State Electricity Regulatory Commission & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in