Facts
The Appellant obtained a term loan of ₹5,27,000 from the Respondent Bank in 2015 to purchase a radio taxi
Source reference: para. 2The Appellant entered into a bilateral agreement with M/s Magic Sewa Pvt. Ltd., according to which the Appellant was to pay the first 24 EMIs and the company was to pay the remaining 36 EMIs
Source reference: para. 3Following a default, a settlement was reached in Lok Adalat in 2018 where the Appellant acknowledged a liability of ₹5,03,874, but subsequently failed to pay
Source reference: paras. 5-6The Trial Court decreed the suit for recovery in favor of the Bank on 18.04.2023, holding that the Bank was not a party to the agreement with Magic Sewa
Source reference: para. 1The Appellant’s subsequent suit for declaration and his objections in execution proceedings were both dismissed
Source reference: paras. 9-10The Appellant now challenges the 2023 decree with a delay of 1035 days
Source reference: para. 29Issues
1. Whether a bilateral agreement between a borrower and a third party regarding EMI payments can absolve the borrower of his liability toward the lending Bank
Source reference: para. 112. Whether the Appellant demonstrated "sufficient cause" under Section 5 of the Limitation Act to condone a delay of 1035 days in filing the appeal
Source reference: para. 29Law Applied
The Court applied the principle of privity of contract, noting that a lender is not bound by a bilateral arrangement between a borrower and a third party unless it is a tripartite agreement
Source reference: para. 14, 8.3It relied on Section 47 of the CPC as interpreted in MMFC Limited v. Anglo American Metallurgical Coal Pvt. Limited and Electrosteel Steel Ltd. v. Ispat Carrier (P) Ltd., which establishes that an executing court cannot go behind the decree except in cases of jurisdictional infirmity or voidness
Source reference: para. 25, 8-10Furthermore, it applied Section 5 of the Limitation Act, emphasizing that the Commercial Courts Act, 2015 mandates a higher degree of diligence and expedition, narrowing the discretion to condone inordinate delays
Source reference: para. 29Reasoning
The Court reasoned that the loan documents (Ex. PW1/1 to PW1/10) established a clear contractual relationship solely between the Appellant and the Bank
Source reference: paras. 15-16The Court found that while the Appellant may have a claim against M/s Magic Sewa Pvt. Ltd. under their 2015 agreement, the Bank was neither a signatory nor a party to that contract; thus, it remained a res inter alios acta (a matter between others) that could not extinguish the Appellant's absolute liability to the Bank
Source reference: para. 20Regarding the procedural delay, the Court observed that the Appellant's attempt to litigate the same issue through a separate suit and execution objections—all of which were dismissed—did not constitute a valid legal excuse for a 1035-day delay
Source reference: para. 27, 29The Court held that the Appellant's acknowledgment of debt during the 2018 Lok Adalat further solidified his status as the primary debtor
Source reference: para. 17Holding
The High Court dismissed the appeal both on merits and on the ground of limitation
The Court held that the Appellant's liability is absolute and unconditional regardless of his inter-se arrangement with a third party
Source reference: para. 28The application for condonation of delay was rejected as no "sufficient cause" was shown
Source reference: para. 29However, the Court clarified that under principles akin to Section 140 of the Indian Contract Act, the Appellant, upon satisfying the decree, remains at liberty to sue M/s Magic Sewa Pvt. Ltd. for recovery of the amounts paid
Source reference: para. 31Original Court PDF
Yogesh Kumar SharmavsCanara Bank (Erstwhile Syndicate Bank)
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in