Chhattisgarh High Court

Interest is payable on admitted contractual sums withheld by the State from the date of completion.

GILCON PROJECT SERVICE LTD. vs CHIEF EXECUTIVE OFFICER

Chhattisgarh High CourtJUDGMENT: March 25, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

Two contract agreements (Nos. 24/RC-4/CGRRDA and 25-RC/4/CGRRDA) were executed between the State of Chhattisgarh and Gilcon Project Service Ltd. on October 23, 2007

Source reference: para 3

Disputes regarding payments and escalations led to the appointment of a sole Arbitrator, who passed a common arbitral award on August 31, 2018

Source reference: para 3

Both parties challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, before the Commercial Court

Source reference: para 3

On February 29, 2020, the Commercial Court dismissed the State’s applications but partially allowed Gilcon’s applications, setting aside the Arbitrator’s rejection of "Claim No. 1" concerning admitted amounts withheld by the State (Rs. 44.06 lakhs, Rs. 64,99,051, and Rs. 4,08,441)

Source reference: para 7, 19, 20

The State appealed the Commercial Court's order, alleging perversity and violation of contract Clause 6.5

Source reference: para 4

Gilcon appealed seeking interest on the awarded sums, which the Commercial Court had omitted

Source reference: para 5
02

Issues

1. Whether the Arbitral Award and the Commercial Court’s order were patently illegal or contrary to the public policy of India under Section 34/37 of the Act

Source reference: para 4, 12

2. Whether Gilcon Project Service Ltd. is entitled to interest (ante-lite, pendente-lite, and post-lite) on the admitted claims allowed by the Commercial Court

Source reference: para 5, 21
03

Law Applied

The court primarily applied Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, which restrict judicial interference to specific grounds such as patent illegality or conflict with public policy

Source reference: para 11, 13

It relied on Haryana Tourism Limited v. Kandhari Beverages Limited, establishing that courts cannot decide Section 37 appeals as regular first appeals on merits

Source reference: para 12

The court also cited Delhi Airport Metro Express Private Limited v. Delhi Metro Rail Corporation Limited, which defined "patent illegality" as an error that goes to the root of the matter, excluding mere erroneous applications of law

Source reference: para 14

Finally, it applied Gayatri Balasamy v. ISG Novasoft Technologies Limited, confirming the court's limited power to modify awards, specifically regarding post-award interest

Source reference: para 16, 18.3
04

Reasoning

The High Court observed that the Arbitrator had conducted an elaborate factual and documentary analysis, including the interpretation of contract clauses and limitation issues

Source reference: para 9

The State failed to establish any specific grounds for interference under Section 37, as the lower court’s refusal to set aside the findings was based on a reasonable appreciation of the Arbitrator’s logic

Source reference: para 17

Regarding Gilcon’s appeal, the Court noted that the Commercial Court had correctly identified that the Arbitrator erred in rejecting Claim No. 1, which comprised admitted amounts illegally withheld by the State

Source reference: para 17, 19

However, because the Commercial Court’s order was silent on the component of interest for these withheld sums, the High Court determined that granting interest was essential for justice

Source reference: para 21

The Court found no reason to disturb the findings of fact or the interpretation of the contract, adhering to the principle of minimal judicial interference

Source reference: para 10, 14
05

Holding

The High Court dismissed the State’s appeals (ARBA Nos. 36, 37, 39, and 40 of 2020)

It allowed Gilcon’s appeals (ARBA Nos. 41 and 42 of 2020) specifically regarding the claim for interest

Source reference: para 22

The Court held that Gilcon is entitled to interest at the rate of 6% per annum on the admitted sums (Rs. 44.06 lakhs, Rs. 64,99,051, and Rs. 4,08,441), payable from the date of completion of the contract until actual realization

Source reference: para 21, 22
Chhattisgarh High Court

Original Court PDF

GILCON PROJECT SERVICE LTD.vsCHIEF EXECUTIVE OFFICER

Chhattisgarh High Court · March 25, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment