Facts
The petitioner, a Draughtsman Grade-I, retired from service on 31 August 2014.
Source reference: p.2, para.3A disciplinary proceeding initiated against him on 1 August 2012 resulted in withholding of his retiral benefits; the proceeding was ultimately quashed by the Central Administrative Tribunal (CAT) on 17 January 2023.
Source reference: p.2, para.3; p.5, para.7By order dated 8 January 2025 in OA No. 776 of 2023, the CAT directed payment of gratuity and other benefits, while observing that no interest would be granted because no such prayer had been made; it further provided for 8% interest from 18 February 2024 if the dues were not paid within the stipulated period.
Source reference: p.2–3, para.3The petitioner’s dues, including gratuity, were eventually paid on 15 March 2025, but without interest for the delayed payment of gratuity.
Source reference: p.3–4, para.4In OA No. 50 of 2025, the CAT refused interest on the grounds that the petitioner had not claimed it earlier and that the delay resulted from litigation pursued by him. The petitioner challenged that order before the High Court.
Source reference: p.3–4, paras.4–6Issues
1. Whether the petitioner was entitled to statutory interest on gratuity delayed from 31 August 2014 until its payment on 15 March 2025 under Section 7(3-A) of the Payment of Gratuity Act, 1972?
Source reference: p.5–6, paras.8–9; p.10–11, para.122. Whether the petitioner’s pursuit of legal proceedings, and his failure to claim interest in an earlier proceeding, constituted “fault” disentitling him to interest under the proviso to Section 7(3-A) of the Act?
Source reference: p.9–10, paras.10–11; p.11, para.133. Whether the principles of constructive res judicata or Order II Rule 2 of the Code of Civil Procedure barred the subsequent claim for interest?
Source reference: p.11, para.13Law Applied
Section 7(2) and (3) of the Payment of Gratuity Act, 1972 require the employer to determine and pay gratuity within the prescribed period, while Section 7(3-A) mandates payment of simple interest from the date gratuity becomes payable until the date of payment.
Source reference: p.5–6, para.8The proviso excludes interest only where the delay is due to the employee’s fault and the employer has obtained written permission from the controlling authority on that ground.
Source reference: p.5–6, para.8In H. Gangahanume Gowda v. Karnataka Agro Industries Corpn. Ltd., (2003) 3 SCC 40, the Supreme Court held that payment of interest on delayed gratuity is a statutory mandate, not a matter of judicial discretion, unless the requirements of the proviso to Section 7(3-A) are satisfied.
Source reference: p.6–9, para.9The Court further applied the principle that pursuing lawful remedies against an employer cannot, by itself, be treated as employee fault, and held that strict principles of constructive res judicata or Order II Rule 2 CPC should not defeat a statutory claim arising under the beneficial provisions of the Payment of Gratuity Act.
Source reference: p.9–11, paras.10–13Reasoning
The Court held that gratuity became payable when the petitioner retired on 31 August 2014, but was paid only on 15 March 2025, resulting in a delay of more than nine years.
Source reference: p.10–11, para.12Although the respondents attributed the delay to the petitioner’s repeated litigation, the Court found that approaching a competent court to challenge an allegedly illegal disciplinary proceeding and to claim retiral benefits could not constitute “fault” under the proviso to Section 7(3-A).
Source reference: p.9–10, para.10The respondents also had not established that they had obtained written permission from the controlling authority for withholding interest on the ground of employee fault, which was a mandatory condition under the proviso.
Source reference: p.6–9, para.9Applying the statutory mandate and the ratio of H. Gangahanume Gowda, the Court concluded that the CAT had no discretion to deny interest merely because it had not been specifically claimed in an earlier proceeding or because the petitioner had pursued litigation.
Source reference: p.10–11, paras.12–13The beneficial object of the Gratuity Act reinforced the petitioner’s entitlement.
Source reference: p.10–11, paras.12–13Holding
The High Court allowed the writ petition and quashed the CAT’s order dated 18 August 2025 in OA No. 50 of 2025.
It held that the petitioner was entitled to simple interest on the gratuity amount at 8% per annum from 31 August 2014 to 15 March 2025, the date on which gratuity was paid.
Source reference: p.11, para.14The opposite parties were directed to pay the interest within three months from receipt of the certified copy of the judgment.
Source reference: p.11, para.14Acts & Sections Cited
1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Code of Civil Procedure, 19081
Original Court PDF
SATYANANDA NAYAKvsUNION OF INDIA
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
