Facts
The respondents’ lands in Village Detroj, Ahmedabad, were acquired for the Narmada Canal project. An award under Section 11 of the Land Acquisition Act was passed on 19.03.1996.
Source reference: p.2The Reference Court enhanced compensation on 03.11.1999.
Source reference: p.2Although the State deposited funds on 30.07.2003, there was a shortfall of ₹9,665/- in the principal amount due to a calculation error by the State.
Source reference: p.3, 11The original claimants filed a recovery application for the remaining amount plus interest on the delayed payment. The Reference Court allowed the application, directing the State to pay the remaining principal plus 15% interest for 6728 days (the period between 31.07.2003 and 31.12.2021).
Source reference: p.3, 6Issues
1. Whether the Reference Court erred in awarding 15% interest on the delayed payment of the remaining compensation amount for the period from 2003 to 2021.
Source reference: p.62. Whether the calculation of interest under Section 28 of the Land Acquisition Act was just and proper in view of a shortfall in the initial deposit.
Source reference: p.6Law Applied
Section 28 of the Land Acquisition Act, 1894, which mandates interest on excess compensation at 9% p.a. from the date of possession for the first year, and 15% p.a. thereafter on any unpaid "excess or part thereof".
Source reference: p.8Section 34 regarding interest on unpaid compensation.
Source reference: p.8The Act is a self-contained code and courts cannot award interest on equitable grounds or in a manner contrary to statutory rates as established in Union of India v. Budh Singh [(1995) 6 SCC 233] and State of Himachal Pradesh v. Dharam Das [(1995) 5 SCC 683].
Source reference: p.10-11Reasoning
The State argued that the Reference Court had granted "interest upon interest," which is prohibited by precedent.
Source reference: p.4-5The High Court observed that the State had admitted to a shortfall of ₹9,665/- in the 2003 deposit. Under the proviso to Section 28, if any part of the excess compensation is not paid into court within one year of taking possession, interest at 15% p.a. is legally payable on the unpaid portion.
Source reference: p.3, 8, 11The Court found that the Reference Court did not grant compound interest but rather applied the statutory 15% rate specifically to the "delayed payment of the remaining amount".
Source reference: p.12Since the State failed to deposit the full amount in 2003, the claimants were entitled by law to the higher interest rate on the deficiency until the date of actual payment.
Source reference: p.11-12Holding
The High Court held that there was no error of law as the 15% interest rate was applied to the shortfall in accordance with the mandate of Section 28 of the Act.
The Court concluded that the compensation of ₹21,246/- (representing ₹5,643/- principal plus ₹15,603/- interest) was just and proper; the petitions were dismissed and Rule discharged.
Source reference: p.12, 13Original Court PDF
STATE OF GUJARATvsDILIPBHAI VITHHALBHAI PATEL
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in