01Facts
The Petitioner (IICECL) awarded an EPC contract to the Respondent (L&T) for Phase-I of a large-scale project at Dwarka.
¶ 6(a)-(d)Disputes arose regarding alleged negative variations by L&T, leading to the commencement of arbitration.
¶ 6(g)-(i)During the proceedings, L&T filed an application under Section 17 of the Arbitration and Conciliation Act, 1996 (A&C Act), seeking the release of payments under Stage Payment Certificates SP-68, SP-69, and SP-70.
pp. 3-4The Majority Arbitral Tribunal, via an Impugned Order dated 03.04.2026, directed IICECL to release approximately Rs. 227 Crore relating to SP-69 and SP-70 as an interim measure, while finding no prima facie case for SP-68.
p. 2, para 152IICECL appealed this order under Section 37(2)(b) of the A&C Act, arguing that the Tribunal granted final monetary relief at an interlocutory stage without a clear admission of liability.
¶ 7-1102Issues
i.1. Whether an Arbitral Tribunal can grant substantial monetary relief as an interim measure under Section 17 of the A&C Act when the underlying liability is seriously contested.
¶ 82, 116ii.2. Whether the Majority Arbitral Tribunal correctly applied the triple test of prima facie case, balance of convenience, and irreparable injury in directing the release of certified payments.
¶ 10203Law Applied
Section 17 of the A&C Act, which empowers tribunals to grant interim measures of protection analogous to Section 9 powers of a Court.
¶ 53, 80The principle from Evergreen Land Mark (P) Ltd. v. John Tinson & Co. (P) Ltd., which prohibits directing payment/deposit of disputed monetary amounts under Section 17 when liability is contested and requires adjudication.
¶ 82The triple-test doctrine for injunctions (Order XXXIX CPC), emphasizing that "irreparable injury" must be harm that cannot be adequately compensated by damages or interest.
¶ 53, 112The limits of Section 37(2)(b), where appellate interference is restricted to cases of perversity, arbitrariness, or manifest illegality.
¶ 50Provisions in the judgment · 9 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 17Section 37Section 16Section 31Section 5Section 8Section 9Section 34
Indian Partnership Act, 1932 Section 69
04Reasoning
The High Court found that the Majority Tribunal’s reasoning was internally inconsistent.
¶ 73, 103While the Tribunal acknowledged that the dispute regarding "negative variations" (and the resulting reduction in contract price) required a full trial and evidence—leading it to deny relief for SP-68—it paradoxically treated SP-69 and SP-70 as prima facie payable despite the Engineer's certifications for those stages being subject to the same caveats regarding price reconciliation.
¶ 89-91, 99Regarding the balance of convenience and irreparable injury, the Court noted that since the project was 80% paid for, substantially completed, and already operationalized, there was no urgent "cash flow" necessity that would justify bypassing the final adjudication of claims.
¶ 105, 111The Court held that the Tribunal failed to meet the "heightened threshold" required to grant mandatory monetary relief at an interim stage, as the loss (if any) was purely financial and compensable through interest.
¶ 118, 12505Holding
The Court answered the issues in the negative, holding that the grant of substantive monetary relief under Section 17 was unwarranted in the face of serious contractual disputes.
¶ 119The High Court set aside the Impugned Order dated 03.04.2026 passed by the Majority Arbitral Tribunal, clarified that all observations are tentative, and allowed the Appeal with no order as to costs.
¶ 128, 129, 131Original Court PDF
India International Convention And Exhibition Centre LimitedvsLarsen And Toubro Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
