01Facts
The Decree Holder (DH) filed a petition under Section 17(2) of the Arbitration and Conciliation Act, 1996, seeking enforcement of an Interim Order dated 06.11.2025 passed by a Sole Arbitrator
pp. 1-2The interim order directed the Judgment Debtor (JD) to deposit 81.25% of monthly mesne profits (approx. Rs. 2.97 Crores) for the period of 01.11.2024 to 31.10.2025
p. 2During the pendency of these enforcement proceedings, the Arbitral Tribunal pronounced its Final Award on 02.03.2026
p. 2 · ¶ 3The Final Award allowed Claim No. 2, directing the JD to pay the same 81.25% share of mesne profits starting from 01.11.2024 until the handing over of possession
p. 3 · ¶ 602Issues
i.1. Whether a petition under Section 17(2) for enforcement of an interim order remains maintainable after the pronouncement of the Final Award, especially when the interim directions are incorporated into the said Award
p. 2 · ¶ 303Law Applied
The court primarily applied Section 17 of the Arbitration and Conciliation Act, 1996 (as amended in 2015 and 2019), which empowers an Arbitral Tribunal to grant interim measures during proceedings
pp. 6-8Section 17(2) creates a legal fiction whereby such orders are deemed orders of a Civil Court and are enforceable under the Code of Civil Procedure, 1908
pp. 7-8The court relied on Alka Chandewar v. Shamshul Ishrar Khan (2017) 16 SCC 119, which established that Section 17(2) provides a "complete solution" for the enforcement of interim orders
pp. 5, 8-9The court further considered Section 36, which stipulates that a final award can only be enforced as a decree after the expiry of the three-month challenge period under Section 34(3)
p. 4, 12Provisions in the judgment · 5 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 17Section 27Section 34Section 36Section 37
04Reasoning
The Court reasoned that while Section 17(2) provides an independent right to enforce interim orders, the power of a Tribunal to grant such measures is temporally restricted to the pendency of arbitral proceedings
p. 11 · ¶ 25In this case, the substantive directions of the Interim Order dated 06.11.2025 were "subsumed and merged" into the Final Award dated 02.03.2026
p. 12 · ¶ 26The Court observed that allowing enforcement of the interim order at this stage would bypass the statutory safeguards of Section 36, which mandates a waiting period before a final award becomes enforceable as a decree
p. 12 · ¶ 27To maintain hormonal operation between Section 17 and Section 36, the Court held that once interim directions are incorporated into the Final Award, the enforcement must follow the regime applicable to Awards rather than parallel proceedings under Section 17(2)
p. 13 · ¶ 29-3005Holding
The Court held that the petition under Section 17(2) is not maintainable at this stage because the Interim Order has merged into the Final Award
pp. 13-14The Court dismissed the petition but granted the Decree Holder liberty to avail legal remedies for the enforcement of the Final Award in accordance with the law
p. 14 · ¶ 33-34Original Court PDF
Sh. Sunder Lal GuptavsM/S Sahyog Hospitality And Others Through Its Partners
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
