Delhi High Court

Interim protection against bank guarantee encashment granted pending adjudication of disputes before the Dispute Resolution Committee

M/S Nkg Infrastructure Ltd. vs Airport Authority Of India (Aai) Through Djm/Jt. Gm Engg. (C) Jabalpur Airport

Delhi High CourtJUDGMENT: April 28, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner, having entered into an agreement dated June 4, 2019, for the upgradation of Jabalpur Airport, moved the court under Section 9 of the Arbitration and Conciliation Act, 1996

Source reference: p. 2

The Petitioner challenged letters dated April 24, 2026, issued by the Respondent (AAI) to various banks for the encashment of six bank guarantees totaling Rs. 3,17,00,000/-

Source reference: p. 2

The Petitioner contended that the invocation was arbitrary as dispute resolution proceedings under Clause 25 of the Agreement were already pending before the Dispute Resolution Committee (DRC)

Source reference: p. 2

The Respondent countered that the bank guarantees were unconditional contracts, and four had already been encashed while two were processed for payment

Source reference: p. 4, 8
02

Issues

1. Whether the Court should interdict the encashment of bank guarantees when dispute resolution proceedings under the contract are currently pending

Source reference: p. 2, 8

2. Whether the Petitioner is entitled to interim protection against further coercive actions pending the decision of the DRC

Source reference: p. 10
03

Law Applied

Section 9 of the Arbitration and Conciliation Act, 1996, which provides for interim measures by the Court

Source reference: p. 2

A bank guarantee is a separate, unconditional contract, and courts generally do not interfere with its invocation except in cases of fraud, irreparable loss, or invocation not in terms of the guarantee

Source reference: p. 6

Contractual mechanism under Clause 25 of the parties’ agreement, which mandates a reference of disputes to a Dispute Resolution Committee (DRC) prior to arbitration

Source reference: p. 2, 8
04

Reasoning

The Court acknowledged the Respondent's argument that bank guarantees are independent contracts requiring payment without demur

Source reference: p. 5, 6

It was noted that a DRC had been constituted and was actively hearing the matter, with the last hearing occurring on April 23, 2026

Source reference: p. 8

Relying on a precedent between the same parties (O.M.P.(I)(COMM.) 118/2026), where protection was granted until the mediation panel considered the disputes, the Court reasoned that further coercive steps should be stayed to ensure the efficacy of the DRC process

Source reference: p. 2, 3

The Court distinguished between the four guarantees already encashed and the remaining two that were already "processed" for payment, excluding the latter from the stay to respect the completed stages of banking transactions

Source reference: p. 10
05

Holding

The Court disposed of the petition by directing the Respondent to take no further "precipitative action" against the Petitioner until the DRC proceedings are finally adjudicated

The Court further ordered that no coercive action be taken for a period of 10 days following the DRC's decision. Crucially, this stay does not apply to the two bank guarantees that have already been processed for encashment

Source reference: p. 10
Delhi High Court

Original Court PDF

M/S Nkg Infrastructure Ltd.vsAirport Authority Of India (Aai) Through Djm/Jt. Gm Engg. (C) Jabalpur Airport

Delhi High Court · April 28, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment