Delhi High Court

Interim Protection Against Termination and Liquidated Damages Subject to Exhausting Mandated Dispute Adjudication Board Mechanism

M/S Vishal Infrastructure Ltd. And M/S Ojsc Euro - Asian Construction Corporation Evrascon (Jv) vs Chief Engineer (Const)-I, North Western Railway, Jaipur

Delhi High CourtJUDGMENT: May 26, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner entered into an EPC Agreement dated 14.07.2023 with the Respondent for the "Major Upgradation of Jodhpur Railway Station"

Source reference: p. 1-2

On 13.05.2026, the Respondent issued a Notice of intention to terminate the Agreement and sought to impose liquidated damages of ₹47.75 Crores (10% of contract value) via communications dated 12.05.2026 and 13.05.2026

Source reference: p. 2

The Petitioner filed this petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking an interim stay on the termination and the recovery of liquidated damages, citing fears of bank guarantee invocation and irreparable financial loss

Source reference: p. 2

The Respondent argued that the Petitioner failed to meet contractual timelines and that the petition was premature as the mandatory Dispute Resolution Mechanism (Conciliation and Dispute Adjudication Board) had not been exhausted

Source reference: p. 3
02

Issues

1. Whether the Petitioner is entitled to interim protection against the termination of the EPC Agreement and the imposition of liquidated damages pending the resolution of disputes

Source reference: p. 1-2

2. Whether the Section 9 petition is maintainable before exhausting the multi-tier contractual dispute resolution mechanism, including the Dispute Adjudication Board (DAB)

Source reference: p. 3
03

Law Applied

The Court's order was guided by Section 9 of the Arbitration and Conciliation Act, 1996, which empowers the Court to grant interim measures of protection

Source reference: p. 1

The Court further emphasized the sanctity of the contractual Dispute Resolution Mechanism (Article 34 of the Agreement), which mandated a tiered process: first conciliation, then reference to a Dispute Adjudication Board (DAB) with a 90-day decision period, prior to the commencement of formal arbitral proceedings

Source reference: p. 3
04

Reasoning

The Respondent challenged the maintainability of the petition, asserting that the Petitioner bypassed the mandatory DAB process stipulated in Article 34

Source reference: p. 3

The Petitioner argued that extreme urgency and the threat of coercive financial measures justified judicial intervention

Source reference: p. 2

Ultimately, the court did not choose between these positions but recorded a consensus (ad idem) between the parties. The parties agreed to revert to the contractual mechanism, specifically the DAB, to resolve the underlying disputes

Source reference: p. 3

To balance the interests during this period, the court recognized the agreement that the Respondent would refrain from acting upon the liquidated damages notices until the DAB rendered its decision, thereby addressing the Petitioner's immediate concern regarding financial prejudice while upholding the contract's procedural requirements

Source reference: p. 3-4
05

Holding

The Court disposed of the petition based on the mutual agreement of the parties.

The Court directed that the Respondent shall not act upon the communications dated 12.05.2026 and 13.05.2026 regarding the imposition of ₹47.75 Crores in liquidated damages until the DAB renders its decision

Source reference: p. 4

Parties were granted liberty to pursue further legal remedies following the DAB's decision

Source reference: p. 3
Delhi High Court

Original Court PDF

M/S Vishal Infrastructure Ltd. And M/S Ojsc Euro - Asian Construction Corporation Evrascon (Jv)vsChief Engineer (Const)-I, North Western Railway, Jaipur

Delhi High Court · May 26, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment