Interim restraint on adjoining construction confined to wall-abutting work; finishing permitted, security FDR modified.

Snehdhara Welfare Societyv.Rajesh Yadav And Another

Interim restraint on adjoining construction confined to wall-abutting work; finishing permitted, security FDR modified.. Snehdhara Welfare Society vs Rajesh Yadav And Another. Punjab and Haryana High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the restraint imposed by the First Appellate Court on the petitioner's construction activity, as framed in the impugned order, permits completion of finishing and furnishing work on the already-raised structure.

The court held

The restraint on the petitioner is confined to further excavation or construction adjoining the plaintiff's wall. The petitioner may complete finishing and furnishing work and raise a mumty not abutting or interfering with that wall.

It also directed

The ₹20 lakh security is retained, but the petitioner may deposit an FDR in its own name, subject to the Trial Court's control over its encumbrance, withdrawal, and final disposal.

The Court disposed of the revision petition with clarifications. The observations are confined to the interim controversy and do not bind the trial. All pending miscellaneous applications stand disposed of.

The judgment does not state a reduced FDR amount despite the petitioner's request.

01Facts

Respondent No.1-plaintiff sued for a permanent prohibitory injunction restraining petitioner-defendant No.1 from construction on the adjoining property until the plaintiff's house was repaired and its structural safety restored, and for damages for necessary repairs, with quantum to be determined at trial.

¶ 2

Along with the suit, the plaintiff moved an application under Order XXXIX Rules 1 and 2 CPC seeking interim restraint on construction.

¶ 2.1

The Civil Judge (Junior Division), Gurugram, dismissed the application by order dated 20.04.2026.

¶ 1, 3

In appeal (CMA No. 137 of 2026), the Additional District Judge, Gurugram, by judgment dated 01.09.2026, partly allowed the appeal. It restrained the petitioner from further excavation or construction adjoining the wall of the plaintiff's house and directed the petitioner to deposit ₹20 lakh by FDR before the Trial Court, subject to the final outcome of the suit.

¶ 1, 3

The petitioner challenged this under Article 227 of the Constitution.

¶ 1, 4

The respondent, having lodged a caveat, appeared through counsel. Both sides agreed, on instructions, to dispose of the petition by clarifying the impugned order, since the petitioner had already raised the structure and sought permission only for finishing and furnishing work. The petitioner also sought reduction of the FDR amount.

¶ 5

02Issues

i.1. Whether the restraint imposed by the First Appellate Court on the petitioner's construction activity, as framed in the impugned order, permits completion of finishing and furnishing work on the already-raised structure.

¶ 5, 6

ii.2. Whether the direction to deposit ₹20 lakh by FDR before the Trial Court should be modified, including as to the petitioner's procurement of the FDR and the amount.

¶ 5, 6.1

03Law Applied

The Court exercised supervisory jurisdiction under Article 227 of the Constitution to examine the appellate interim order.

¶ 1

The Court proceeded under Order XXXIX Rules 1 and 2 CPC, which govern interim injunctions pending suit.

¶ 1, 2.1

The judgment refers generally to "settled principles governing the grant of interim injunctions" but cites no specific statute, precedent, or doctrine.

¶ 1

Interim security may be ordered to protect the plaintiff pending suit, but its terms may be modified to limit prejudice to the defendant, and interim orders are confined to the controversy at hand and do not decide the merits.

¶ 6.1, 7

04Reasoning

The Court read the impugned order and found no express bar on finishing or furnishing the existing structure. It held that the restraint was confined to further excavation or new construction immediately adjoining the plaintiff's wall. Applying this reading, the Court held that the petitioner may complete furnishing and may raise a mumty, provided it does not abut or interfere with the plaintiff's wall.

¶ 6

On the FDR, the Court accepted that security was justified to protect the plaintiff during the suit, so the direction was not set aside entirely. It modified only the mechanism: the petitioner may procure the FDR in its own name and deposit it, but the FDR may not be encumbered, withdrawn, or prematurely encashed without the Trial Court's permission, and its final disposal will follow the Trial Court's decree.

¶ 6.1

The Court did not expressly fix a reduced amount, although the petitioner had sought one.

¶ 5, 6.1

The Court expressly stated that its observations do not reflect any opinion on the merits of the suit or on disputed questions of fact or law.

¶ 7

05Holding

The restraint on the petitioner is confined to further excavation or construction adjoining the plaintiff's wall. The petitioner may complete finishing and furnishing work and raise a mumty not abutting or interfering with that wall.

¶ 6, 6.2

The ₹20 lakh security is retained, but the petitioner may deposit an FDR in its own name, subject to the Trial Court's control over its encumbrance, withdrawal, and final disposal.

¶ 6.1, 6.2

The Court disposed of the revision petition with clarifications. The observations are confined to the interim controversy and do not bind the trial. All pending miscellaneous applications stand disposed of.

¶ 6, 7, 8

The judgment does not state a reduced FDR amount despite the petitioner's request.

¶ 5, 6.1
Punjab and Haryana High Court

Original Court PDF

Snehdhara Welfare SocietyvsRajesh Yadav And Another

Punjab and Haryana High Court · November 25, 2026