Delhi High Court
Banking and Finance LawArbitration and Mediation

Invocation of an unconditional bank guarantee cannot be restrained absent egregious fraud or special equities.

National Highways Of India vs Gr Infraprojects Limited

Delhi High CourtJUDGMENT: September 17, 20262 MIN READSOURCE JUDGMENT
Invocation of an unconditional bank guarantee cannot be restrained absent egregious fraud or special equities.. National Highways Of India vs Gr Infraprojects Limited. Delhi High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The parties entered into an EPC Agreement dated 21 August 2018 for construction and maintenance of a highway bypass. After provisional and completion certificates were issued, pavement deterioration was reported. NHAI attributed it to deficient construction and maintenance; GR Infraprojects disputed liability, attributing the deterioration principally to overloading and allegedly inadequate contractual specifications. NHAI sought approximately ₹102.49 crore for rehabilitation and consequential damages, and the disputes were referred to arbitration.

Source reference: pp. 2–3

During the arbitration, NHAI sought to encash the Performance Bank Guarantee (PBG). On GR Infraprojects’ application under Section 17 of the Arbitration and Conciliation Act, 1996, the Arbitral Tribunal restrained invocation and directed that the PBG remain alive during the proceedings. NHAI appealed under Section 37 of the Act.

Source reference: pp. 1, 3
02

Issues

Whether the Arbitral Tribunal was justified in restraining NHAI from encashing an unconditional and irrevocable PBG

Source reference: p. 6, para. 27
03

Law Applied

Under the settled law governing unconditional bank guarantees, courts may restrain encashment only in exceptional circumstances, including egregious fraud of which the bank has notice and which vitiates the guarantee’s foundation, or special equities where encashment would cause irretrievable harm or injustice. The Court relied on the Division Bench decision in Black Gold Resources Private Limitada v. International Coal Ventures Pvt. Ltd., FAO(OS)(COMM) 211/2025.

Source reference: p. 6, para. 29

An unconditional PBG is an independent obligation; disputes concerning the underlying contract do not, without an applicable exception, justify restraining its invocation.

Source reference: pp. 7–8, paras. 31–36
04

Reasoning

The Court treated the competing explanations for pavement deterioration and the parties’ dispute over contractual responsibility as matters for the pending arbitration, not as grounds to restrain an unconditional PBG.

Source reference: p. 7, paras. 30–33

It held that financial burden on the contractor, or the possibility that it might ultimately succeed in arbitration, did not amount to irreparable harm; that consequence is inherent in performance security.

Source reference: p. 7–8, paras. 35–36

NHAI’s continuing rehabilitation expenditure and highway-maintenance obligations likewise did not prevent invocation in accordance with the PBG’s terms.

Source reference: p. 8, paras. 37–38
05

Holding

The Court held that the restraint on invocation of the PBG was unjustified and set aside the impugned order insofar as it restrained NHAI from invoking the guarantee.

The appeal was allowed, with all merits of the parties’ claims and counterclaims left open for determination by the Arbitral Tribunal.

Source reference: pp. 8–9, paras. 40–42
06

Acts & Sections Cited

2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19962

Delhi High Court

Original Court PDF

National Highways Of IndiavsGr Infraprojects Limited

Delhi High Court · September 17, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment