Delhi High Court

Judicial Intervention Under Section 11 to Appoint Sole Arbitrator Upon Failure of Party Consensus

Triveni Engineering And Industries Ltd. vs Bharat Heavy Electricals Ltd.

Delhi High CourtJUDGMENT: July 22, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner, a manufacturing company, was awarded a contract by the Respondent (a Government of India undertaking) for the supply, erection, and commissioning of an Effluent Treatment Plant (ETP) and a Sewerage Treatment Plant (STP)

Source reference: paras. 2-3

The work was governed by Letters of Intent dated 30.06.2008, a work order dated 11.08.2008, and the General Conditions of Contract (GCC)

Source reference: para. 1

Disputes arose regarding outstanding payments for running account bills and retention money totaling Rs. 1,28,77,352.95/-

Source reference: para. 5

The Petitioner invoked the arbitration clause (Clause 33 of the GCC) via a Section 21 notice on 16.01.2026

Source reference: para. 6

The parties failed to reach a consensus on the appointment of a Sole Arbitrator, leading the Petitioner to approach the High Court under Section 11(6) of the Arbitration and Conciliation Act, 1996

Source reference: paras. 7-8
02

Issues

1. Whether a Sole Arbitrator should be appointed under Section 11(6) of the Act given the prima facie existence of an arbitration agreement?

Source reference: para. 10

2. Whether the Court can refer the matter to arbitration when the Respondent does not object to the appointment?

Source reference: paras. 9, 13
03

Law Applied

The Court applied Section 11(6) of the Arbitration and Conciliation Act, 1996, which empowers the Court to appoint an arbitrator when parties fail to agree on a procedure

Source reference: para. 1

It relied on the precedent SBI General Insurance Co. Ltd. v. Krish Spinning (2024), which establishes that the scope of inquiry under Section 11 is strictly confined to examining the prima facie existence of a valid arbitration agreement

Source reference: para. 10

The Court also referenced Section 21 regarding the commencement of arbitral proceedings

Source reference: para. 6

Section 12(2) regarding mandatory arbitrator disclosures

Source reference: para. 15
04

Reasoning

The Court observed that the core requirement for exercising jurisdiction under Section 11—the existence of a valid arbitration agreement—was undisputed by both parties

Source reference: para. 11

Since the Petitioner had properly invoked the arbitration clause through a Section 21 notice and the parties had reached a deadlock over the specific individual to be appointed, the statutory conditions for judicial intervention were met

Source reference: paras. 6-8

During the hearing, the Respondent’s counsel expressly stated they had no objection to the relief sought

Source reference: para. 9

Consequently, as the parties were ad idem (in agreement) regarding the reference of disputes to arbitration and there was no legal impediment, the Court determined it was necessary to appoint an independent arbitrator to adjudicate the claims

Source reference: para. 13
05

Holding

The Court allowed the petition and appointed Mr. Alakh Kumar, Advocate, as the Sole Arbitrator to adjudicate the disputes

The Court directed that the arbitration be conducted under the rules and aegis of the Delhi International Arbitration Centre (DIAC) and that the arbitrator must provide disclosures under Section 12(2) of the Act

Source reference: paras. 15-16

All pleas regarding arbitrability, jurisdiction, and limitation were left open for the arbitrator to decide

Source reference: para. 17

The petition and pending applications were disposed of accordingly

Source reference: para. 20
Delhi High Court

Original Court PDF

Triveni Engineering And Industries Ltd.vsBharat Heavy Electricals Ltd.

Delhi High Court · July 22, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment