Facts
The Petitioner, a manufacturing company, was awarded a contract by the Respondent (a Government of India undertaking) for the supply, erection, and commissioning of an Effluent Treatment Plant (ETP) and a Sewerage Treatment Plant (STP)
Source reference: paras. 2-3The work was governed by Letters of Intent dated 30.06.2008, a work order dated 11.08.2008, and the General Conditions of Contract (GCC)
Source reference: para. 1Disputes arose regarding outstanding payments for running account bills and retention money totaling Rs. 1,28,77,352.95/-
Source reference: para. 5The Petitioner invoked the arbitration clause (Clause 33 of the GCC) via a Section 21 notice on 16.01.2026
Source reference: para. 6The parties failed to reach a consensus on the appointment of a Sole Arbitrator, leading the Petitioner to approach the High Court under Section 11(6) of the Arbitration and Conciliation Act, 1996
Source reference: paras. 7-8Issues
1. Whether a Sole Arbitrator should be appointed under Section 11(6) of the Act given the prima facie existence of an arbitration agreement?
Source reference: para. 102. Whether the Court can refer the matter to arbitration when the Respondent does not object to the appointment?
Source reference: paras. 9, 13Law Applied
The Court applied Section 11(6) of the Arbitration and Conciliation Act, 1996, which empowers the Court to appoint an arbitrator when parties fail to agree on a procedure
Source reference: para. 1It relied on the precedent SBI General Insurance Co. Ltd. v. Krish Spinning (2024), which establishes that the scope of inquiry under Section 11 is strictly confined to examining the prima facie existence of a valid arbitration agreement
Source reference: para. 10The Court also referenced Section 21 regarding the commencement of arbitral proceedings
Source reference: para. 6Section 12(2) regarding mandatory arbitrator disclosures
Source reference: para. 15Reasoning
The Court observed that the core requirement for exercising jurisdiction under Section 11—the existence of a valid arbitration agreement—was undisputed by both parties
Source reference: para. 11Since the Petitioner had properly invoked the arbitration clause through a Section 21 notice and the parties had reached a deadlock over the specific individual to be appointed, the statutory conditions for judicial intervention were met
Source reference: paras. 6-8During the hearing, the Respondent’s counsel expressly stated they had no objection to the relief sought
Source reference: para. 9Consequently, as the parties were ad idem (in agreement) regarding the reference of disputes to arbitration and there was no legal impediment, the Court determined it was necessary to appoint an independent arbitrator to adjudicate the claims
Source reference: para. 13Holding
The Court allowed the petition and appointed Mr. Alakh Kumar, Advocate, as the Sole Arbitrator to adjudicate the disputes
The Court directed that the arbitration be conducted under the rules and aegis of the Delhi International Arbitration Centre (DIAC) and that the arbitrator must provide disclosures under Section 12(2) of the Act
Source reference: paras. 15-16All pleas regarding arbitrability, jurisdiction, and limitation were left open for the arbitrator to decide
Source reference: para. 17The petition and pending applications were disposed of accordingly
Source reference: para. 20Original Court PDF
Triveni Engineering And Industries Ltd.vsBharat Heavy Electricals Ltd.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in