01Facts
The petitioner, a landlord, inducted K.G. Industries Pvt. Ltd. as a monthly tenant for premises in Burrabazar, Kolkata. From March 2014 to January 2025, the tenant deposited monthly rent (totaling Rs. 11,13,500) with the Rent Controller (Respondent No. 2) under the West Bengal Premises Tenancy Act, 1997
pp. 1-2In a previous writ petition (WPO 461 of 2025), the court directed the Rent Controller to disburse the amount upon the petitioner fulfilling statutory formalities
p. 4Consequently, Rs. 9,43,500 was released, followed by the remaining Rs. 1,70,000 during the pendency of the current writ
p. 2, 5The petitioner filed the present petition seeking 12% interest per annum on the delayed remittance, alleging that the Rent Controller failed in its statutory duty to notify the landlord of the deposits
pp. 2-302Issues
i.1. Whether the claim for interest is barred by the principle of constructive res judicata because it was prayed for but not expressly granted in the earlier writ petition
pp. 5-6ii.2. Whether the petitioner is entitled to interest on the rent amounts deposited with the Rent Controller in the absence of a specific statutory provision for interest
p. 5, 1003Law Applied
The court applied Section 11, Explanation V of the Code of Civil Procedure (CPC), which states that relief claimed but not expressly granted is deemed refused, provided there was an actual adjudication of the issue
pp. 6-7It relied on Saroja vs. Chinnusamy (Dead) regarding the conditions for res judicata
p. 6Regarding the merits, the court interpreted Sections 21 and 23 of the West Bengal Premises Tenancy Act, 1997, and Rules 9 and 11 of the 1999 Rules, which mandate that a landlord must file a specific application for withdrawal of rent and undergo a quasi-judicial verification process
pp. 10-13It distinguished the precedent Poornima Advani vs. Govt. of NCT, which allows interest on the refund of taxes/duties retained without authority, noting such principles do not apply to private rent deposits held in trust
pp. 8-9, 16Provisions in the judgment · 3 · Linked ones open on LawLens
West Bengal Premises Tenancy Act, 1997 Section 21Section 23
Code of Civil Procedure, 1908 Section 11
04Reasoning
On the first issue, the court held that res judicata did not apply because the previous Bench only granted liberty to file a withdrawal application and did not "hear and finally decide" the entitlement to interest; thus, there was no adjudication to trigger Explanation V
pp. 7-8On the second issue, the court found that under Section 23 of the 1997 Act, remittance is not automatic; the landlord must proactively apply for withdrawal
pp. 13-14The court observed that the petitioner knew of the deposits since 2014 but failed to file the prescribed Form 4 applications until 2025
p. 16The Rent Controller, acting in a quasi-judicial capacity, does not "collect" rent as a tax or duty but holds it to the credit of the landlord
pp. 15-16Since the delay was primarily due to the petitioner's lack of diligence in following statutory procedures, the doctrine of "unjust enrichment" or "retention" by the State did not apply
pp. 16-1705Holding
The court answered the first issue in the negative, holding the petition maintainable
p. 8The court held that the petitioner is not entitled to interest because the delay was self-inflicted by failing to file the required withdrawal applications timely
pp. 16-17The court dismissed the writ petition, making no order as to costs
p. 17Original Court PDF
AJAY RAJ AGENCIES PVT, LTD.vsSTATE OF WEST BENGAL AND ORS
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
