Facts
The Appellants, distribution licensees (DISCOMs) in Delhi, entered into Power Purchase Agreements (PPAs) with Indraprastha Power Generation Company Ltd. (Respondent No. 2) on 16.07.2012 for the Rajghat Power House (RPH)
Source reference: p. 3-4Clause 13.1 stipulated a 25-year validity from the date of commercial operation
Source reference: p. 4These PPAs expired in May and July 2015 respectively. Despite the Appellants expressing no intent to renew and requesting the State Load Despatch Center (SLDC) to stop scheduling power, Respondent No. 2 continued billing until the plant’s closure on 31.12.2015 per pollution control orders
Source reference: p. 4The Delhi Electricity Regulatory Commission (DERC) issued an order on 10.12.2019 holding the Appellants liable for bills until 31.12.2015, citing a government meeting where it was decided to continue allocation for grid stability
Source reference: p. 5-7Issues
1. Whether a distribution licensee is liable to pay capacity charges and energy bills to a generator after the expiry of a PPA by efflux of time, in the absence of a mutual renewal
Source reference: p. 3 / para. 22. Whether the scheduling of power by SLDC under Section 32 of the Electricity Act occupies a higher priority than the existence of a valid underlying contract
Source reference: p. 22 / para. 27-28Law Applied
The Tribunal applied basic principles of contract law, noting that once a PPA—governed by Section 86(1)(b) of the Electricity Act, 2003—expires, the mutual obligations of the parties cease
Source reference: p. 9 / para. 12Regarding Respondent 2's right to challenge findings without a cross-appeal, the Tribunal relied on Banarsi Ors. v. Ram Phal (2003) 9 SCC 606, which allows a respondent to support a decree by challenging adverse findings without filing a cross-objection
Source reference: p. 11-13Crucially, the Tribunal interpreted Section 32(2)(a) of the Electricity Act, 2003, which mandates that the SLDC must schedule and dispatch electricity "in accordance with the contracts entered into with the licensees"
Source reference: p. 22-23Reasoning
The Tribunal held that a PPA is a commercial contract; once its duration ends by efflux of time, the generator cannot force supply and the licensee is not bound to pay
Source reference: p. 9It rejected Respondent 2’s new plea that the 25-year period should start from a "stabilization date" in December 1990 rather than the May 1990 commissioning, noting this was a fresh factual argument based on conjecture and not raised before the Commission
Source reference: p. 19-20The Tribunal further dismissed the argument that a government meeting on 05.06.2015 superseded the PPA, as the minutes themselves required the parties to "take necessary actions for renewal," which never occurred
Source reference: p. 21Finally, the Tribunal corrected the SLDC’s stance, clarifying that under Section 32(2)(a), the SLDC’s authority to schedule power is derived strictly from existing contracts; it cannot ignore a DISCOM's notice of PPA expiry and continue scheduling power unlawfully
Source reference: p. 23-24Holding
The Tribunal allowed the appeal and set aside the DERC order. It held that the Appellants are not liable to pay any energy or capacity charges beyond the expiry of their respective PPAs in May 2015 (BRPL) and July 2015 (BYPL)
The energy bills raised by Respondent No. 2 for the period between July and December 2015 were declared unlawful and quashed
Source reference: p. 25Original Court PDF
BSES Yamuna Power Ltd. & AnrvsThe Secretary Delhi Electricity Regulatory Commission
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in