Facts
The Appellant (PTCUL), a State Transmission Utility, challenged a CERC order dated 31.03.2021.
Source reference: p. 4In 2008, the Standing Committee on Transmission Planning (SCM) agreed to standard norms for 400/220 kV substations, which included six 220 kV line bays at the Dehradun substation.
Source reference: p. 15, para 31-32While PTCUL utilized two bays for the Jhajra-Sherpur line in 2017, four bays remained unutilized as downstream networks were not commissioned.
Source reference: p. 6, para 7PGCIL (Respondent No. 1) sought approval for the Commercial Operation Date (COD) of these four bays (Asset-III) as 04.02.2017.
Source reference: p. 6, para 7The CERC approved the COD and held PTCUL liable to pay yearly transmission charges from that date until the completion of downstream assets, based on the "defaulter pays" principle derived from previous meeting minutes and correspondence.
Source reference: p. 7, para 13PTCUL appealed, denying any binding contractual obligation to build the remaining lines or pay the charges.
Source reference: p. 8, para 17Issues
1. Whether the minutes of meetings and planning correspondence, in the absence of a contract, created a binding obligation on PTCUL to construct downstream assets.
Source reference: p. 9, para 182. Whether PTCUL can be held liable for bilateral transmission charges under the PoC-based regime (2014-2019) for unutilized bays.
Source reference: p. 9, para 183. Whether the COD of the subject bays could be declared under the 2014 Tariff Regulations without actual utilization.
Source reference: p. 9, para 18Law Applied
The Court applied the National Electricity Policy (2005) and the Indian Electricity Grid Code (IEGC) 2006/2010, which mandate coordinated transmission planning through Regional Standing Committees.
Source reference: p. 12-13, para 26-28It relied on the principle from Kollipara Sriramulu v. T. Aswathanarayana that an informal agreement is binding only if all material terms (like timelines and specific responsibilities) are finalized.
Source reference: p. 12, para 25The Court interpreted Regulation 4(3), Proviso (ii) of the CERC Tariff Regulations, 2014, which allows for the declaration of "deemed COD" when an asset is ready but unutilized due to delays in upstream/downstream systems.
Source reference: p. 31, para 71Finally, it considered the "defaulter pays" principle established in Nuclear Power Corporation of India Ltd. v. CERC to determine liability during a mismatch period.
Source reference: p. 33, para 73Reasoning
The Tribunal analyzed the 23rd SCM minutes and subsequent meetings, concluding that the six bays were created based on generic planning norms for demand growth, not an exclusive request or commitment by PTCUL to build six specific lines.
Source reference: p. 15, para 32; p. 23, para 51The Court found that for Minutes of Meetings (MOM) to constitute a binding contract in the regulated electricity sector, they must specify the implementing agency and clear timelines, which were absent here.
Source reference: p. 14, para 29; p. 21, para 47While the Tribunal upheld the CERC's declaration of COD under Proviso (ii) of Regulation 4(3) because PGCIL’s bays were physically ready, it held that the "defaulter pays" principle could not be applied to PTCUL.
Source reference: p. 32, para 72; p. 26, para 61This was because no underlying contractual or legal obligation was established forcing PTCUL to utilize all six bays by a specific date.
Source reference: p. 26, para 61The Tribunal further noted that PGCIL, acting as the CTU, failed in its statutory duty under Section 38 of the Electricity Act to ensure an "economical" and "coordinated" system by failing to execute a formal Implementation Agreement (IA) which would have clarified these obligations.
Source reference: p. 28, para 64Holding
The Tribunal allowed the appeal and set aside the Impugned Order to the extent it held PTCUL solely liable for transmission charges.
The Tribunal held that while the COD of 04.02.2017 was validly declared, PTCUL cannot be saddled with bilateral charges as no binding commitment for the downstream network existed.
Source reference: p. 37, para 85; p. 40, para 93The matter was remanded to the CERC for fresh adjudication to determine who should bear the transmission charges (e.g., whether they should be socialized via the PoC pool) after considering PGCIL’s coordination failures as the CTU and the lack of a formal Implementation Agreement.
Source reference: p. 45, para 106Original Court PDF
Power Transmission Corporation of Uttarakhand Limited,vsPower Grid Corporation of India Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in