Facts
The State acquired land situated in the revenue estates of Shergarh, Dhakola, Jawahargarh and Bihta, District Ambala, for construction of an effluent channel and establishment of Growth Centre, Phase-II, of HSIIDC. Notifications under Sections 4 and 6 of the Land Acquisition Act, 1894, were issued on 28 October 2013 and 27 October 2014, respectively.
Source reference: para. 4; pp. 4–6The Land Acquisition Collector passed the award on 21 October 2016, determining different market values for the acquired land depending on its location and depth.
Source reference: paras. 5–6; pp. 6–7The landowners sought references under Section 18 of the 1894 Act, contending that the compensation was inadequate. The Land Acquisition, Rehabilitation and Resettlement Authority, by a common award dated 28 February 2025, enhanced the applicable multiplying factor from 1 to 1.25 for land in Dhakola and Jawahargarh, and to 1.5 for land in Bihta and Shergarh.
Source reference: paras. 6–7; pp. 7–8HSIIDC challenged the enhancement, while certain landowners filed appeals and cross-objections seeking further relief.
Source reference: para. 7; p. 8HSIIDC argued that several reference applications were barred by limitation and that the 2018 notification prescribing the multiplier could not apply because the Section 4 notification and Collector’s award predated it. The landowners contended that their applications were filed within limitation from the date of actual knowledge of the award and that any delay resulted from the Collector’s failure to promptly forward the applications.
Source reference: paras. 8–9; pp. 8–9Issues
1. Whether the reference applications under Section 18 of the Land Acquisition Act, 1894, were barred by limitation where notice of the Collector’s award under Section 12(2) had not been served and actual or constructive knowledge was disputed?
Source reference: paras. 8–18; pp. 8–132. Whether the notification prescribing the enhanced multiplying factor issued in 2018 could be applied despite the Section 4 notification and the Collector’s award having been issued before that notification?
Source reference: paras. 8–9, 22; pp. 8–9, 143. Whether the Authority had erred in enhancing the multiplying factor for the acquired land in the four villages?
Source reference: paras. 3, 7, 22–24; pp. 5–8, 14–154. Whether the parties were entitled to lead additional evidence at the appellate stage?
Source reference: paras. 25–26; p. 15Law Applied
The Court applied Section 74 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, governing appeals, along with Sections 4, 6, 11, 12(2), 18 and 28A of the Land Acquisition Act, 1894.
Source reference: no citationUnder Section 18, limitation begins only when the person interested has actual or constructive knowledge of the award; mere making or filing of the award is insufficient where statutory notice under Section 12(2) has not been served. Relying on Harish Chandra Raj Singh v. Land Acquisition Officer, 1961 SCC OnLine SC 140, the Court held that communication or knowledge of the award is an essential requirement before limitation can commence.
Source reference: para. 14; pp. 9–11Relying on Bhagwan Das v. State of U.P., (2010) 3 SCC 545, it held that the Collector bears the burden of proving actual or constructive knowledge once the claimant asserts absence of notice and knowledge; such knowledge may be established through receipt of compensation, participation in possession proceedings, challenge to the award, or acknowledgment of the award.
Source reference: para. 15; pp. 11–12Section 28A reflects the principle that similarly situated landowners should receive re-determined compensation on the basis of a Court’s enhanced award.
Source reference: paras. 19–20; pp. 13–15The Court also followed its earlier decision in Financial Commissioner & Principal Secretary to Government of Haryana v. Jamila, which had held that the 2018 notification prescribing the multiplier applied even where the Section 4 notification or award predated the notification.
Source reference: paras. 9, 22; pp. 9, 14Reasoning
The Court examined the original record and found that many applications under Section 18 had admittedly been filed within the prescribed period, while the Collector had failed to establish timely service of notice under Section 12(2) or actual or constructive knowledge of the award in the disputed cases.
Source reference: paras. 13, 16–18; pp. 9, 12–13Applying Harish Chandra Raj Singh and Bhagwan Das, the Court held that limitation could not mechanically be computed from the date of the award in the absence of proof that the landowners knew of its contents.
Source reference: no citationThe Court further observed that applications filed during the pendency of valid references could, in substance, be considered consistently with the object of Section 28A, namely, securing equal and just compensation for similarly situated landowners.
Source reference: paras. 19–21; pp. 13–15On the multiplier, HSIIDC conceded that the issue had already been settled in Jamila. Accordingly, the Court upheld the Authority’s application of the 2018 notification and the enhanced factors of 1.25 for Dhakola and Jawahargarh and 1.5 for Bihta and Shergarh.
Source reference: para. 22; p. 14The landowners were unable to demonstrate any error in the basic market values determined by the Collector and upheld by the Authority. Consequently, neither the HSIIDC appeals nor the landowners’ appeals and cross-objections disclosed grounds for interference.
Source reference: paras. 23–24; p. 14–15Holding
The Court held that the disputed reference applications were not shown to be barred by limitation because the Collector had not established service of notice or actual/constructive knowledge of the awards.
It further held that the 2018 notification prescribing the enhanced multiplier was applicable, and that the Authority correctly applied multiplying factors of 1.25 and 1.5 to the specified villages.
Source reference: paras. 21–24; pp. 14–15All HSIIDC appeals, landowners’ appeals and cross-objections were dismissed.
Source reference: paras. 21–24; pp. 14–15Any delay in filing the appeals was condoned by consent, but the appellants were denied interest for the delayed period.
Source reference: para. 12; p. 9Applications seeking permission to lead additional evidence were also dismissed, and all pending applications stood disposed of.
Source reference: paras. 25–26; p. 15Acts & Sections Cited
3 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 20133
Original Court PDF
Haryana State Industrial And Infrastructural Development Corporation LtdvsRaj Pal Singh And Others
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
