Facts
The Appellant entered into a Power Purchase Agreement (PPA) with Respondent No. 2 (TANGEDCO) on September 26, 2017, for a solar power project, with a commissioning deadline of 24 months.
Source reference: p. 3-4Due to the imposition of "Safeguard Duty" on solar modules, the Appellant failed to commission the project within the maximum allowable 34-month window.
Source reference: p. 4, 10-11Consequently, TANGEDCO encashed Performance Bank Guarantees (PBGs) worth ₹15 crores.
Source reference: p. 6-7The Appellant approached the Tamil Nadu Electricity Regulatory Commission (TNERC) seeking a project-specific extension, which was rejected via order dated February 2, 2021.
Source reference: p. 2The Commission held that the PPA stood automatically terminated and the Appellant was liable for liquidated damages (LD) under Article 14.
Source reference: p. 2, 6Issues
1. Whether TANGEDCO was entitled to encash the Performance Bank Guarantees despite the Appellant's claims of Force Majeure and lack of proven loss.
Source reference: p. 7 / para. 13; p. 12 / para. 202. Whether the Commission erred in awarding liquidated damages to TANGEDCO without proof of actual loss suffered due to the non-commissioning of the project.
Source reference: p. 14 / para. 23Law Applied
Section 74 of the Indian Contract Act, 1872, which stipulates that while parties can pre-estimate damages, the court will only award "reasonable compensation" not exceeding the named amount, regardless of whether actual loss is proved.
Source reference: p. 18, 20Section 73 of the Indian Contract Act, 1872 regarding compensation for loss caused by breach.
Source reference: p. 16The Tribunal relied on the Supreme Court precedents in Kailash Nath Associates v. DDA, which held that loss is a sine qua non for damages and proof of loss is only dispensed with if it is difficult or impossible to prove.
Source reference: p. 21-24Maula Bux v. Union of India, which clarified that where loss is determinable in money, the claimant must prove it.
Source reference: p. 25-27Reasoning
Regarding the PBGs, the Tribunal found that under Article 14 of the PPA, encashment was a contractually triggered consequence of missing the 24-to-29-month timeline, independent of proven loss.
Source reference: p. 10, 13The Appellant failed to properly amend its pleadings to challenge the encashment before the Commission.
Source reference: p. 12Regarding Liquidated Damages, the Tribunal noted that the Commission failed to ascertain if TANGEDCO suffered any actual legal injury or loss.
Source reference: p. 31While TANGEDCO argued that quantifying loss in power distribution is complex, the Tribunal held that the Commission acted in an "arbitrary and cavalier manner" by awarding LD without first determining if the case was one where proving loss was truly impossible or if TANGEDCO could demonstrate proximity of damage.
Source reference: p. 31-32Holding
The Tribunal rejected the prayer for refund of the Bank Guarantee amount, upholding the encashment based on contractual timelines.
The Tribunal set aside the Commission’s order regarding the Appellant's liability for liquidated damages and remanded the case for a fresh determination on whether TANGEDCO suffered any actual loss.
Source reference: p. 32-33Original Court PDF
Raasi Green Earth Energy Pvt. Ltd.vsTamil Nadu Electricity Regulatory Commission & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in