APTEL

Liquidated damages are not awardable under Section 74 without proof of actual loss or legal injury.

Raasi Green Earth Energy Pvt. Ltd. vs Tamil Nadu Electricity Regulatory Commission & Ors

APTELJUDGMENT: July 29, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant entered into a Power Purchase Agreement (PPA) with Respondent No. 2 (TANGEDCO) on September 26, 2017, for a solar power project, with a commissioning deadline of 24 months.

Source reference: p. 3-4

Due to the imposition of "Safeguard Duty" on solar modules, the Appellant failed to commission the project within the maximum allowable 34-month window.

Source reference: p. 4, 10-11

Consequently, TANGEDCO encashed Performance Bank Guarantees (PBGs) worth ₹15 crores.

Source reference: p. 6-7

The Appellant approached the Tamil Nadu Electricity Regulatory Commission (TNERC) seeking a project-specific extension, which was rejected via order dated February 2, 2021.

Source reference: p. 2

The Commission held that the PPA stood automatically terminated and the Appellant was liable for liquidated damages (LD) under Article 14.

Source reference: p. 2, 6
02

Issues

1. Whether TANGEDCO was entitled to encash the Performance Bank Guarantees despite the Appellant's claims of Force Majeure and lack of proven loss.

Source reference: p. 7 / para. 13; p. 12 / para. 20

2. Whether the Commission erred in awarding liquidated damages to TANGEDCO without proof of actual loss suffered due to the non-commissioning of the project.

Source reference: p. 14 / para. 23
03

Law Applied

Section 74 of the Indian Contract Act, 1872, which stipulates that while parties can pre-estimate damages, the court will only award "reasonable compensation" not exceeding the named amount, regardless of whether actual loss is proved.

Source reference: p. 18, 20

Section 73 of the Indian Contract Act, 1872 regarding compensation for loss caused by breach.

Source reference: p. 16

The Tribunal relied on the Supreme Court precedents in Kailash Nath Associates v. DDA, which held that loss is a sine qua non for damages and proof of loss is only dispensed with if it is difficult or impossible to prove.

Source reference: p. 21-24

Maula Bux v. Union of India, which clarified that where loss is determinable in money, the claimant must prove it.

Source reference: p. 25-27
04

Reasoning

Regarding the PBGs, the Tribunal found that under Article 14 of the PPA, encashment was a contractually triggered consequence of missing the 24-to-29-month timeline, independent of proven loss.

Source reference: p. 10, 13

The Appellant failed to properly amend its pleadings to challenge the encashment before the Commission.

Source reference: p. 12

Regarding Liquidated Damages, the Tribunal noted that the Commission failed to ascertain if TANGEDCO suffered any actual legal injury or loss.

Source reference: p. 31

While TANGEDCO argued that quantifying loss in power distribution is complex, the Tribunal held that the Commission acted in an "arbitrary and cavalier manner" by awarding LD without first determining if the case was one where proving loss was truly impossible or if TANGEDCO could demonstrate proximity of damage.

Source reference: p. 31-32
05

Holding

The Tribunal rejected the prayer for refund of the Bank Guarantee amount, upholding the encashment based on contractual timelines.

The Tribunal set aside the Commission’s order regarding the Appellant's liability for liquidated damages and remanded the case for a fresh determination on whether TANGEDCO suffered any actual loss.

Source reference: p. 32-33
APTEL

Original Court PDF

Raasi Green Earth Energy Pvt. Ltd.vsTamil Nadu Electricity Regulatory Commission & Ors

APTEL · July 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment