Facts
The Petitioner, a Multi-System Operator (MSO), entered into an Interconnect Agreement (valid from 25.07.2020 to 31.03.2025) with Respondent No. 1 (R-1), a Local Cable Operator (LCO), for the retransmission of signals
Source reference: p.2-3The Petitioner provided approximately 655 Set Top Boxes (STBs) to R-1
Source reference: p.2In December 2020, R-1 allegedly began swapping these STBs to Respondent No. 2 (R-2), a competing MSO, in violation of Interconnect Regulations and the agreement
Source reference: p.3Despite notices, R-1 failed to clear outstanding invoices or return 232 STBs
Source reference: p.3The Petitioner sought an injunction against the swapping of STBs and a direction for R-1 to return 232 STBs or pay their depreciated cost
Source reference: p.1-2R-1 remained ex-parte, while R-2 denied liability citing a lack of privity of contract
Source reference: p.3-4Issues
1. Whether the instant Petition is maintainable in its present form?
Source reference: para. 8, Issue i2. Whether Respondent No. 1 illegally migrated to Respondent No. 2 in violation of Interconnected Regulations and the terms of the Agreement?
Source reference: para. 8, Issue ii3. Whether the Petitioner is entitled to the recovery of 232 STBs and viewing cards or, in the alternative, the cost of the STBs?
Source reference: para. 8, Issue iii4. To what other relief/reliefs is the Petitioner entitled?
Source reference: para. 8, Issue ivLaw Applied
Section 14A(1) and 14(a)(ii) of the Telecom Regulatory Authority of India (TRAI) Act, 1997, which governs disputes between service providers
Source reference: p.1-2Regarding the burden of proof in civil proceedings, the Tribunal relied on the "preponderance of probabilities"
Source reference: para. 12Anil Rishi v. Gurbaksh Singh (AIR 2006 SC 1971) regarding the initial onus of proof on the party asserting a fact
Source reference: para. 13State of JK v. Hindustan Forest Co. (2006) 12 SCC 198, asserting that a plaintiff must stand on the strength of their own evidence
Source reference: para. 13The Tribunal applied the established legal principle that there is no "Privity of Contract" between competing MSOs; therefore, one MSO cannot be held liable for the contractual breaches or misconduct of an LCO shifting to another MSO
Source reference: para. 14Reasoning
The Tribunal found the petition maintainable against R-1 but noted that no claim could be sustained against R-2 due to the absence of privity of contract
Source reference: para. 14Regarding the illegal migration and non-return of STBs, the Tribunal observed that the Petitioner’s evidence—submitted via affidavit—remained uncontroverted as R-1 failed to appear or file a reply
Source reference: para. 15The Petitioner successfully proved that 232 STBs were not returned and established their depreciated value at Rs. 672 per STB
Source reference: para. 16Since the Petitioner’s claims regarding the violation of Interconnect Regulations and the agreement were made on oath and not rebutted, the Tribunal held that the Petitioner had discharged its burden of proof under the principle of preponderance of probabilities
Source reference: para. 15-16The Tribunal further determined that a 9% per annum simple interest rate was justifiable given the current fiscal scenario
Source reference: para. 17Holding
The Tribunal allowed the Petition against Respondent No. 1 and dismissed claims against Respondent No. 2
R-1 was directed to return 232 STBs along with viewing cards in good working condition within two months. In the event of default, R-1 is ordered to pay Rs. 1,55,904 (calculated at Rs. 672 per STB). Additionally, the Petitioner was awarded simple interest at 9% per annum (pendente lite and future) until the actual date of payment, along with the costs of the petition.
Source reference: p.10; para. 17Original Court PDF
GTPL HATHWAY LTDvsSRI SHIRIDI SAI CABLE NETWORK & ANR
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in