Facts
The Union of India awarded the respondent a contract on 22 November 2010 to reconstruct a sea dyke.
Source reference: para. 1–15Although the respondent furnished the earnest money deposit (EMD) and performance guarantee, the work did not commence because the site had not been handed over.
Source reference: para. 1–15The Union invoked Clause 3A of the General Conditions of Contract (GCC) to foreclose the contract on 23 March 2015, several years after the stipulated commencement date.
Source reference: para. 1–15The arbitrator found that the site was unavailable, awarded amounts on certain claims—including ₹12,85,982 for loss of profit, calculated at 3.75% of the net contract amount—and rejected the respondent’s claim for idling of machinery, tools, plant and site overheads.
Source reference: para. 17–20The Section 34 challenge was dismissed by the Additional District Judge. The Union appealed under Section 37, principally challenging the award for loss of profit.
Source reference: para. 21–28Issues
Whether the award of loss of profit under Claim No. 4 was unsustainable because the arbitrator rejected the separate claim for idling of machinery, tools, plant and site overheads under Claim No. 5.
Source reference: para. 23–28, 36, 43–44Whether the arbitrator’s quantification of loss of profit was unsupported or perverse, warranting interference under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996.
Source reference: para. 29–30, 35, 40–48Law Applied
Section 37 of the Arbitration and Conciliation Act, 1996 provides limited appellate review of an arbitral award, while Section 34 confines judicial interference to the grounds specified there; the court does not reappraise the merits as an appellate court.
Source reference: para. 29–35Section 73 of the Indian Contract Act, 1872 permits compensation for loss or damage naturally arising from a breach, but excludes remote and indirect loss.
Source reference: para. 29–35In Batliboi Environmental Engineers Ltd. v. Hindustan Petroleum Corporation Ltd., (2024) 2 SCC 375, the Supreme Court held that an award may be set aside where, among other things, it lacks reasoning or a rational basis for quantification, or results in disproportionate or overlapping compensation.
Source reference: para. 29–35A.T. Brij Paul Singh v. State of Gujarat, AIR 1984 SC 1703, supports the availability of damages for loss of expected profit following a breach, subject to the circumstances and evidence.
Source reference: para. 45–48The tribunal’s construction of the contract and assessment of evidence are not to be displaced merely because another view is possible.
Source reference: para. 45–48Reasoning
The court upheld the finding that the Union was responsible for the failure to proceed: the NIT stated that the site was available, but the correspondence showed that it had not been demarcated or handed over.
Source reference: para. 7–14, 37–39Clause 3A contemplated early foreclosure where work could not start for reasons beyond the contractor’s control, yet the Union invoked it more than four years after commencement was due.
Source reference: para. 7–14, 37–39The court treated the loss-of-profit claim as distinct from Claim No. 5, which concerned unsubstantiated expenditure on idle resources and manpower.
Source reference: para. 36, 40For Claim No. 4, the arbitrator had before it the respondent’s income-tax returns showing declining gross income and the contract’s 15% margin for overheads and profit.
Source reference: para. 42–47The award allowed only 3.75% of the net contract amount, which the court considered a reasoned and reasonable quantification, unlike the unsupported and disproportionate calculation in Batliboi.
Source reference: para. 40, 42–47The court therefore found no basis for interference under Sections 34 or 37.
Source reference: para. 43–55Holding
The court held that rejecting the claim for idling costs did not preclude a separate award for loss of profit, and that the 3.75% award was not shown to be arbitrary, unsupported or otherwise liable to be set aside.
The appeal was dismissed, the arbitral award and the order dismissing the Section 34 challenge were left undisturbed, and any pending application was disposed of.
Source reference: para. 43–55Acts & Sections Cited
6 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19965
Indian Contract Act, 18721
Original Court PDF
THE UNION OF INDIAvsM/S K.P. TRADING AND COMPANY
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
