APTEL

LTA transmission charges are payable on the entire sanctioned capacity regardless of actual usage or power flow.

PTC India Limited vs Secretary Central Electricity Regulatory Commission & Ors

APTELJUDGMENT: April 07, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant (PTC), an inter-state trading licensee, entered into a Power Purchase Agreement (PPA) with Respondent No. 2 (KPL) in 2005 for 300 MW of power, subsequently secured through a Power Sale Agreement (PSA) with Haryana Power (HPPC)

Source reference: p. 4-5

PTC obtained Long-Term Open Access (LTA) for 300 MW from the Central Transmission Utility (CTUIL)

Source reference: p. 5

In 2011, KPL terminated the PPA, leading to prolonged litigation currently pending before the Supreme Court (SC)

Source reference: p. 6-7

On 18.09.2015, the SC passed an interim order for the resumption of power supply, during which KPL voluntarily opened a Letter of Credit (LC) for the full 300 MW LTA charges on behalf of PTC to restart the plant

Source reference: p. 8

While 95% of the power was supplied to HPPC via LTA, 5% was supplied to Chhattisgarh (CSPDCL) via Short-Term Open Access (STOA)

Source reference: p. 9

CTUIL invoiced PTC for 100% LTA charges; however, PTC deducted the 5% corresponding to the STOA supply from KPL’s energy bills

Source reference: p. 9-10

KPL petitioned the CERC (Petition No. 227/MP/2017), which directed PTC to pay 100% of the LTA charges to CTUIL and refund the 5% deducted from KPL

Source reference: p. 3

PTC appealed, challenging CERC’s jurisdiction and the relief granted without a specific prayer

Source reference: p. 10-11
02

Issues

1. Whether Petition No. 227/MP/2017 was maintainable before the CERC given that the primary dispute between the parties was pending before the Hon’ble Supreme Court.

Source reference: para. 13 / para. 21

2. Whether the CERC correctly determined the liability for 100% LTA transmission charges and correctly directed PTC to refund the 5% deducted from KPL’s payments.

Source reference: para. 13 / para. 30
03

Law Applied

The Tribunal applied Section 79(1)(c) and (f) of the Electricity Act, 2003, which empowers the CERC to regulate inter-state transmission and adjudicate related disputes

Source reference: para. 22

It relied on Regulation 8 of the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010, which mandates that LTA charges are based on the quantum of LTA granted rather than actual power flow

Source reference: para. 12.2

The Tribunal further applied the principle of "moulding of relief" as established in Srinivas Ram Kumar Firm v. Mahabir Prasad and Hindalco Industries Ltd. v. Union of India, allowing a court to grant relief based on admitted facts and substance of pleadings even if not specifically prayed for

Source reference: para. 10.16

Additionally, it invoked the legal maxim that a party cannot take advantage of its own wrong

Source reference: para. 39
04

Reasoning

On the first issue, the Tribunal held that the SC’s interim order dated 18.09.2015 was an arrangement to resume supply and did not supersede the CERC’s statutory jurisdiction to resolve transmission charge disputes arising under the Bulk Power Transmission Agreement (BPTA)

Source reference: para. 26-27

On the second issue, the Tribunal observed that under the 2010 Sharing Regulations, PTC (as the LTA grantee) was unconditionally liable for 100% of the transmission charges for the 300 MW capacity, regardless of the actual 95% usage for HPPC

Source reference: para. 38

The Tribunal found that PTC failed to relinquish the 5% LTA capacity for nearly four years, choosing instead to pass the financial burden onto KPL while retaining the capacity

Source reference: para. 39

It rejected PTC's procedural objection regarding the lack of a specific prayer in KPL's petition, ruling that since PTC admitted to making the deductions in its pleadings, the CERC was justified in directing a refund to prevent PTC from benefiting from its failure to relinquish the unused LTA portion

Source reference: para. 39
05

Holding

The Tribunal dismissed the appeal and affirmed the CERC's order

(i) the CERC had valid jurisdiction as the dispute was distinct from the issues before the Supreme Court

Source reference: para. 27

(ii) PTC is liable for 100% LTA charges to CTUIL until the date of formal relinquishment

Source reference: para. 40.2

(iii) PTC's deduction of 5% charges from KPL was illegal

Source reference: para. 39

PTC was directed to refund the deducted amounts to KPL with 9% interest within four weeks

Source reference: para. 40.4
APTEL

Original Court PDF

PTC India LimitedvsSecretary Central Electricity Regulatory Commission & Ors

APTEL · April 07, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment