Facts
The Appellant (PTC), an inter-state trading licensee, entered into a Power Purchase Agreement (PPA) with Respondent No. 2 (KPL) in 2005 for 300 MW of power, subsequently secured through a Power Sale Agreement (PSA) with Haryana Power (HPPC)
Source reference: p. 4-5PTC obtained Long-Term Open Access (LTA) for 300 MW from the Central Transmission Utility (CTUIL)
Source reference: p. 5In 2011, KPL terminated the PPA, leading to prolonged litigation currently pending before the Supreme Court (SC)
Source reference: p. 6-7On 18.09.2015, the SC passed an interim order for the resumption of power supply, during which KPL voluntarily opened a Letter of Credit (LC) for the full 300 MW LTA charges on behalf of PTC to restart the plant
Source reference: p. 8While 95% of the power was supplied to HPPC via LTA, 5% was supplied to Chhattisgarh (CSPDCL) via Short-Term Open Access (STOA)
Source reference: p. 9CTUIL invoiced PTC for 100% LTA charges; however, PTC deducted the 5% corresponding to the STOA supply from KPL’s energy bills
Source reference: p. 9-10KPL petitioned the CERC (Petition No. 227/MP/2017), which directed PTC to pay 100% of the LTA charges to CTUIL and refund the 5% deducted from KPL
Source reference: p. 3PTC appealed, challenging CERC’s jurisdiction and the relief granted without a specific prayer
Source reference: p. 10-11Issues
1. Whether Petition No. 227/MP/2017 was maintainable before the CERC given that the primary dispute between the parties was pending before the Hon’ble Supreme Court.
Source reference: para. 13 / para. 212. Whether the CERC correctly determined the liability for 100% LTA transmission charges and correctly directed PTC to refund the 5% deducted from KPL’s payments.
Source reference: para. 13 / para. 30Law Applied
The Tribunal applied Section 79(1)(c) and (f) of the Electricity Act, 2003, which empowers the CERC to regulate inter-state transmission and adjudicate related disputes
Source reference: para. 22It relied on Regulation 8 of the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010, which mandates that LTA charges are based on the quantum of LTA granted rather than actual power flow
Source reference: para. 12.2The Tribunal further applied the principle of "moulding of relief" as established in Srinivas Ram Kumar Firm v. Mahabir Prasad and Hindalco Industries Ltd. v. Union of India, allowing a court to grant relief based on admitted facts and substance of pleadings even if not specifically prayed for
Source reference: para. 10.16Additionally, it invoked the legal maxim that a party cannot take advantage of its own wrong
Source reference: para. 39Reasoning
On the first issue, the Tribunal held that the SC’s interim order dated 18.09.2015 was an arrangement to resume supply and did not supersede the CERC’s statutory jurisdiction to resolve transmission charge disputes arising under the Bulk Power Transmission Agreement (BPTA)
Source reference: para. 26-27On the second issue, the Tribunal observed that under the 2010 Sharing Regulations, PTC (as the LTA grantee) was unconditionally liable for 100% of the transmission charges for the 300 MW capacity, regardless of the actual 95% usage for HPPC
Source reference: para. 38The Tribunal found that PTC failed to relinquish the 5% LTA capacity for nearly four years, choosing instead to pass the financial burden onto KPL while retaining the capacity
Source reference: para. 39It rejected PTC's procedural objection regarding the lack of a specific prayer in KPL's petition, ruling that since PTC admitted to making the deductions in its pleadings, the CERC was justified in directing a refund to prevent PTC from benefiting from its failure to relinquish the unused LTA portion
Source reference: para. 39Holding
The Tribunal dismissed the appeal and affirmed the CERC's order
(i) the CERC had valid jurisdiction as the dispute was distinct from the issues before the Supreme Court
Source reference: para. 27(ii) PTC is liable for 100% LTA charges to CTUIL until the date of formal relinquishment
Source reference: para. 40.2(iii) PTC's deduction of 5% charges from KPL was illegal
Source reference: para. 39PTC was directed to refund the deducted amounts to KPL with 9% interest within four weeks
Source reference: para. 40.4Original Court PDF
PTC India LimitedvsSecretary Central Electricity Regulatory Commission & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in