Madras High CourtAdministrative and Public LawConstitutional Law

Madras HC Extends Velan Infra’s Commissioning Deadline By 180 Days Without Additional Commitment Charges

M/S.VELAN INFRA PROJECTS PRIVATE LIMITED,v.The Tamilnadu power Distribution corporation limit

Madras HC Extends Velan Infra’s Commissioning Deadline By 180 Days Without Additional Commitment Charges. M/S.VELAN INFRA PROJECTS PRIVATE LIMITED, vs The Tamilnadu power Distribution corporation limit. Madras High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the directions issued in W.P. No. 21524 of 2026 (Batch) should also govern the petitioner’s request for an extended commissioning period without additional commitment charges.

The court held

The Court disposed of the writ petition in the terms of W.P. No. 21524 of 2026 (Batch).

It also directed

Accordingly, 180 days are to be added to the petitioner’s final commissioning deadline without additional commitment charges; the earlier directions concerning the impugned communication and processing of pending requests and certificates also apply.

The Court made no order as to costs and closed the connected miscellaneous petitions.

01Facts

The petitioner sought to quash the fifth respondent’s circular memo dated 27 May 2026 and obtain an additional 180 days beyond the commissioning deadline in its award letter dated 8 January 2025, without commitment charges for that extended period.

pp. 1–2

At the hearing, both sides submitted that the facts were identical to those in W.P. No. 21524 of 2026 (Batch), decided on 19 August 2026, and requested that the same directions be applied.

p. 3

02Issues

i.1. Whether the directions issued in W.P. No. 21524 of 2026 (Batch) should also govern the petitioner’s request for an extended commissioning period without additional commitment charges.

p. 3, 5

ii.2. Whether the writ petition and connected miscellaneous petitions should be disposed of on those terms.

p. 5

03Law Applied

The petition was brought under Article 226 of the Constitution of India.

p. 2

The Court applied its prior order in W.P. No. 21524 of 2026 (Batch), which provided that, where the relevant circumstances were established, 180 days would be added to each petitioner’s final commissioning deadline without additional commitment charges; it also recorded that the impugned communication keeping the NFR in abeyance was no longer in force and directed authorities to process pending requests and certificates.

pp. 3–5

04Reasoning

The Court accepted the parties’ submission that the material facts were identical to those in the earlier batch decision.

p. 5

On that basis, rather than separately reconsidering the circular or the petitioner’s entitlement, it followed the earlier order and applied its directions to this petition.

p. 3, 5

05Holding

The Court disposed of the writ petition in the terms of W.P. No. 21524 of 2026 (Batch).

p. 5

Accordingly, 180 days are to be added to the petitioner’s final commissioning deadline without additional commitment charges; the earlier directions concerning the impugned communication and processing of pending requests and certificates also apply.

pp. 4–5

The Court made no order as to costs and closed the connected miscellaneous petitions.

p. 5
Madras High Court

Original Court PDF

M/S.VELAN INFRA PROJECTS PRIVATE LIMITED,vsThe Tamilnadu power Distribution corporation limit

Madras High Court · October 27, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment