Madras High Court

Madras HC Gives Solar Developers In Batch 180 Extra Days To Commission Projects Without Extra Commitment Charges

M/s. Para Enterprises Pvt. Ltd., vs The Tamil Nadu Power Distribution Corporation Lim

Madras High CourtJUDGMENT: October 14, 20262 MIN READSOURCE JUDGMENT
Madras HC Gives Solar Developers In Batch 180 Extra Days To Commission Projects Without Extra Commitment Charges. M/s. Para Enterprises Pvt. Ltd., vs The Tamil Nadu Power  Distribution Corporation Lim. Madras High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The lead petitioner challenged a notice dated 23 May 2026 and sought permission to commission a 150 MVA transformer at its Vagaikulam pooling substation to evacuate 25 MW of solar power, together with processing of related open-access applications

Source reference: p. 2

When the batch came for hearing, counsel for both sides submitted that the petitions arose in circumstances similar to those addressed in W.P. No. 21524 of 2026 (Batch), decided on 19 August 2026, and requested the same directions

Source reference: p. 3

The Court recorded that the relevant facts were identical to those in that earlier batch

Source reference: p. 6
02

Issues

1. Whether the directions issued in W.P. No. 21524 of 2026 (Batch) should also govern these petitions, given the parties’ submission that the circumstances were identical

Source reference: pp. 3, 6

2. Whether the Court should determine the merits of the challenge to the notice dated 23 May 2026, or dispose of the petitions by applying the directions in the earlier batch

Source reference: pp. 2–3, 6
03

Law Applied

The Court followed its order in W.P. No. 21524 of 2026 (Batch), which provided that the communication keeping the NFR (Noted for Record) in abeyance was no longer in force; authorities were to process pending requests and certificates, and projects could proceed towards commissioning, with projects obtaining CEIG certificates to be commissioned expeditiously

Source reference: pp. 4–5

That order also extended each petitioner’s final commissioning deadline by 180 days, without additional commitment charges for the extended period

Source reference: p. 5

Although the lead petitioner’s prayer invoked Section 10(1) of the Electricity Act, 2003, the Court did not analyse or decide that provision

Source reference: p. 2
04

Reasoning

The Court relied on the parties’ joint submission that the present petitions involved facts identical to those in the earlier batch.

Source reference: p. 6

It therefore considered it sufficient to apply the directions already made there, rather than separately examining the merits of each petition or the challenge to the notice.

Source reference: p. 6

The incorporated directions addressed the NFR communication, the processing of pending requests and certificates, project commissioning, and an extension of the commissioning deadline without additional commitment charges.

Source reference: pp. 4–5
05

Holding

The Court disposed of the writ petitions in terms of its order dated 19 August 2026 in W.P. No. 21524 of 2026 (Batch).

Accordingly, the authorities were to proceed with pending requests and certificates and permit the projects to progress towards commissioning; each petitioner received an additional 180 days beyond its original final commissioning deadline, without additional commitment charges for that period.

Source reference: pp. 4–5

No costs were ordered, and the connected miscellaneous petitions were closed.

Source reference: p. 6
06

Acts & Sections Cited

1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Electricity Act, 20031

Madras High Court

Original Court PDF

M/s. Para Enterprises Pvt. Ltd.,vsThe Tamil Nadu Power Distribution Corporation Lim

Madras High Court · October 14, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment