01Facts
Swelect Energy Systems Limited sought a seven-month extension, without commitment charges, to complete and commission its 110/33 kV pooling substation at Velalaviduthi.
pp. 1–3It also sought expeditious processing of pending commissioning approvals, including registration and issuance of a Noted for Record (NFR) for its solar plant.
pp. 1–3At the hearing, both sides submitted that the case was factually similar to W.P. No. 21524 of 2026 (Batch), decided on 19 August 2026, and that the same directions could be applied.
p. 302Issues
i.Whether Swelect was entitled to an extension of its commissioning deadline without additional commitment charges, in line with the directions in W.P. No. 21524 of 2026 (Batch).
p. 3, 6ii.Whether the respondents should proceed with pending approvals necessary for commissioning, consistently with the directions in the earlier batch order.
pp. 3–503Law Applied
No statute or distinct legal doctrine was identified as the basis for the decision.
pp. 4–5The Court applied its earlier order in W.P. No. 21524 of 2026 (Batch), which directed that authorities process pending requests and certificates so projects could proceed towards commissioning, and that 180 days be added to each petitioner’s final commissioning deadline without additional commitment charges.
pp. 4–5The present Court treated that order as applicable because the facts were identical.
p. 604Reasoning
The Court accepted the parties’ joint submission that the circumstances matched those in the earlier batch, including the delay associated with the NFR issue.
p. 6Finding no material distinction warranting different treatment, it disposed of the petition on the terms of that order and granted a 180-day extension without additional commitment charges.
p. 6The earlier order’s directions concerning the processing of pending requests and certificates were incorporated by reference.
pp. 4–605Holding
The petition was disposed of in terms of W.P. No. 21524 of 2026 (Batch).
p. 6The respondents were directed to grant a 180-day extension, starting from 29 October 2026, without additional commitment charges.
p. 6No costs were ordered, and the connected miscellaneous petitions were closed.
p. 6Original Court PDF
Swelect Energy Systems Limited,vsThe Tamil Nadu Power Distribution Corporation Limi
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
