Facts
The Petitioner and Respondent entered into a Concession Agreement (CA) on January 30, 2006, for the development and maintenance of a section of NH-7 on a Build-Operate-Transfer (BOT) Toll basis
Source reference: para 4.1In May 2024, disputes arose regarding Force Majeure and Change in Law, leading to arbitration
Source reference: para 4.4During the proceedings, NHAI issued a Cure Period Notice dated October 7, 2025, alleging defaults including failure to perform bituminous overlay, non-payment of damages, and failure to comply with Article 34.11 regarding the retention of funds in an Escrow Account
Source reference: para 4.7The Arbitral Tribunal, vide an interim order under Section 17, stayed the notice regarding overlay obligations and damages as they were sub-judice, but permitted NHAI to proceed regarding the Article 34.11 default (retention of Rs. 46.54 Crores)
Source reference: para 2, 12The Petitioner challenged this limited portion of the order
Source reference: para 3Issues
1. Whether the obligation to retain funds or provide a Bank Guarantee under Article 34.11 of the Concession Agreement is an independent obligation or contingent upon the adjudication of disputed bituminous overlay works.
Source reference: para 5, 122. Whether the Arbitral Tribunal’s refusal to stay the Cure Period Notice in respect of Article 34.11 warrants interference under Section 37(2)(b) of the Arbitration Act.
Source reference: para 19-21Law Applied
Section 17 of the Arbitration and Conciliation Act, 1996 regarding interim measures by an arbitral tribunal
Source reference: para 1Section 37(2)(b) regarding the limited scope of appellate interference, which is restricted to cases of patent illegality or perversity
Source reference: para 20The principle from Dinesh Gupta v. Anand Gupta that a court should not substitute its discretion for that of the arbitrator if the arbitrator's view is plausible
Source reference: para 20"non-obstante" mandate of Article 34.11 of the Concession Agreement, which creates a substantive divestment-stage safeguard independent of other contractual disputes
Source reference: para 13, 14Reasoning
The court reasoned that Article 34.11 contains a non-obstante clause ("notwithstanding anything to the contrary"), making the retention of funds a mandatory, independent obligation triggered two years prior to the expiry of the concession period
Source reference: para 13, 14This obligation ensures a reserve for renewal works across all project assets, not just the disputed bituminous overlay
Source reference: para 18The Court found that the Independent Engineer (IE) had properly calculated the required amount as Rs. 46.54 Crores based on traffic volume, a calculation the Petitioner never challenged
Source reference: para 15-17Furthermore, the court noted that the issues framed in the ongoing arbitration did not overlap with the Article 34.11 mandate
Source reference: para 18Since the Petitioner failed to demonstrate any patent illegality, and the Tribunal’s view was deemed plausible, the court held that judicial interference under Section 37 was not justified
Source reference: para 21Holding
The Court dismissed the appeal and upheld the Arbitral Tribunal's order
The Court held that the obligation under Article 34.11 is independent and non-derogable, and the Petitioner's failure to furnish the Bank Guarantee or retain funds justified the Respondent's pursuit of the Cure Period Notice
Source reference: para 17, 18The Court further held that pleas of balance of convenience or irreparable injury cannot be used to bypass mandatory contractual obligations
Source reference: para 22Original Court PDF
M/S Nk Toll Road LtdvsNational Highways Authority Of India
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in