Delhi High CourtArbitration and MediationContract Law

Mandatory Escrow Retention Under Concession Agreements Is an Independent Obligation Not Contingent on Pending Arbitral Adjudication

M/S Nk Toll Road Ltdv.National Highways Authority Of India

Mandatory Escrow Retention Under Concession Agreements Is an Independent Obligation Not Contingent on Pending Arbitral Adjudication. M/S Nk Toll Road Ltd vs National Highways Authority Of India. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the obligation to retain funds or provide a Bank Guarantee under Article 34.11 of the Concession Agreement is an independent obligation or contingent upon the adjudication of disputed bituminous overlay works.

The court held

The Court dismissed the appeal and upheld the Arbitral Tribunal's order

It also directed

The Court held that the obligation under Article 34.11 is independent and non-derogable, and the Petitioner's failure to furnish the Bank Guarantee or retain funds justified the Respondent's pursuit of the Cure Period Notice

The Court further held that pleas of balance of convenience or irreparable injury cannot be used to bypass mandatory contractual obligations

01Facts

The Petitioner and Respondent entered into a Concession Agreement (CA) on January 30, 2006, for the development and maintenance of a section of NH-7 on a Build-Operate-Transfer (BOT) Toll basis

¶ 4.1

In May 2024, disputes arose regarding Force Majeure and Change in Law, leading to arbitration

¶ 4.4

During the proceedings, NHAI issued a Cure Period Notice dated October 7, 2025, alleging defaults including failure to perform bituminous overlay, non-payment of damages, and failure to comply with Article 34.11 regarding the retention of funds in an Escrow Account

¶ 4.7

The Arbitral Tribunal, vide an interim order under Section 17, stayed the notice regarding overlay obligations and damages as they were sub-judice, but permitted NHAI to proceed regarding the Article 34.11 default (retention of Rs. 46.54 Crores)

¶ 2, 12

The Petitioner challenged this limited portion of the order

¶ 3

02Issues

i.1. Whether the obligation to retain funds or provide a Bank Guarantee under Article 34.11 of the Concession Agreement is an independent obligation or contingent upon the adjudication of disputed bituminous overlay works.

¶ 5, 12

ii.2. Whether the Arbitral Tribunal’s refusal to stay the Cure Period Notice in respect of Article 34.11 warrants interference under Section 37(2)(b) of the Arbitration Act.

¶ 19-21

03Law Applied

Section 17 of the Arbitration and Conciliation Act, 1996 regarding interim measures by an arbitral tribunal

¶ 1

Section 37(2)(b) regarding the limited scope of appellate interference, which is restricted to cases of patent illegality or perversity

¶ 20

The principle from Dinesh Gupta v. Anand Gupta that a court should not substitute its discretion for that of the arbitrator if the arbitrator's view is plausible

¶ 20

"non-obstante" mandate of Article 34.11 of the Concession Agreement, which creates a substantive divestment-stage safeguard independent of other contractual disputes

¶ 13, 14

Provisions in the judgment · 3 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 17Section 32Section 37

04Reasoning

The court reasoned that Article 34.11 contains a non-obstante clause ("notwithstanding anything to the contrary"), making the retention of funds a mandatory, independent obligation triggered two years prior to the expiry of the concession period

¶ 13, 14

This obligation ensures a reserve for renewal works across all project assets, not just the disputed bituminous overlay

¶ 18

The Court found that the Independent Engineer (IE) had properly calculated the required amount as Rs. 46.54 Crores based on traffic volume, a calculation the Petitioner never challenged

¶ 15-17

Furthermore, the court noted that the issues framed in the ongoing arbitration did not overlap with the Article 34.11 mandate

¶ 18

Since the Petitioner failed to demonstrate any patent illegality, and the Tribunal’s view was deemed plausible, the court held that judicial interference under Section 37 was not justified

¶ 21

05Holding

The Court dismissed the appeal and upheld the Arbitral Tribunal's order

¶ 23

The Court held that the obligation under Article 34.11 is independent and non-derogable, and the Petitioner's failure to furnish the Bank Guarantee or retain funds justified the Respondent's pursuit of the Cure Period Notice

¶ 17, 18

The Court further held that pleas of balance of convenience or irreparable injury cannot be used to bypass mandatory contractual obligations

¶ 22
Delhi High Court

Original Court PDF

M/S Nk Toll Road LtdvsNational Highways Authority Of India

Delhi High Court · April 27, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment