01Facts
The Petitioner and Respondent entered into a Concession Agreement (CA) on January 30, 2006, for the development and maintenance of a section of NH-7 on a Build-Operate-Transfer (BOT) Toll basis
¶ 4.1In May 2024, disputes arose regarding Force Majeure and Change in Law, leading to arbitration
¶ 4.4During the proceedings, NHAI issued a Cure Period Notice dated October 7, 2025, alleging defaults including failure to perform bituminous overlay, non-payment of damages, and failure to comply with Article 34.11 regarding the retention of funds in an Escrow Account
¶ 4.7The Arbitral Tribunal, vide an interim order under Section 17, stayed the notice regarding overlay obligations and damages as they were sub-judice, but permitted NHAI to proceed regarding the Article 34.11 default (retention of Rs. 46.54 Crores)
¶ 2, 12The Petitioner challenged this limited portion of the order
¶ 302Issues
i.1. Whether the obligation to retain funds or provide a Bank Guarantee under Article 34.11 of the Concession Agreement is an independent obligation or contingent upon the adjudication of disputed bituminous overlay works.
¶ 5, 12ii.2. Whether the Arbitral Tribunal’s refusal to stay the Cure Period Notice in respect of Article 34.11 warrants interference under Section 37(2)(b) of the Arbitration Act.
¶ 19-2103Law Applied
Section 17 of the Arbitration and Conciliation Act, 1996 regarding interim measures by an arbitral tribunal
¶ 1Section 37(2)(b) regarding the limited scope of appellate interference, which is restricted to cases of patent illegality or perversity
¶ 20The principle from Dinesh Gupta v. Anand Gupta that a court should not substitute its discretion for that of the arbitrator if the arbitrator's view is plausible
¶ 20"non-obstante" mandate of Article 34.11 of the Concession Agreement, which creates a substantive divestment-stage safeguard independent of other contractual disputes
¶ 13, 14Provisions in the judgment · 3 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 17Section 32Section 37
04Reasoning
The court reasoned that Article 34.11 contains a non-obstante clause ("notwithstanding anything to the contrary"), making the retention of funds a mandatory, independent obligation triggered two years prior to the expiry of the concession period
¶ 13, 14This obligation ensures a reserve for renewal works across all project assets, not just the disputed bituminous overlay
¶ 18The Court found that the Independent Engineer (IE) had properly calculated the required amount as Rs. 46.54 Crores based on traffic volume, a calculation the Petitioner never challenged
¶ 15-17Furthermore, the court noted that the issues framed in the ongoing arbitration did not overlap with the Article 34.11 mandate
¶ 18Since the Petitioner failed to demonstrate any patent illegality, and the Tribunal’s view was deemed plausible, the court held that judicial interference under Section 37 was not justified
¶ 2105Holding
The Court dismissed the appeal and upheld the Arbitral Tribunal's order
¶ 23The Court held that the obligation under Article 34.11 is independent and non-derogable, and the Petitioner's failure to furnish the Bank Guarantee or retain funds justified the Respondent's pursuit of the Cure Period Notice
¶ 17, 18The Court further held that pleas of balance of convenience or irreparable injury cannot be used to bypass mandatory contractual obligations
¶ 22Original Court PDF
M/S Nk Toll Road LtdvsNational Highways Authority Of India
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
