Karnataka High CourtArbitration and MediationContract Law

Mutual Breaches and Inordinate Delay Bar Specific Performance of Joint Development Agreement Under Section 34 Limitation

M/S FORTUNA CONSTRUCTIONS INDIA PVT LTDv.SMT. SHAMALAMMA

Mutual Breaches and Inordinate Delay Bar Specific Performance of Joint Development Agreement Under Section 34 Limitation. M/S FORTUNA CONSTRUCTIONS INDIA PVT LTD vs SMT. SHAMALAMMA. Karnataka High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Arbitral Tribunal exceeded its jurisdiction by deciding "ex aequo et bono" (interests of justice and equity) without express authorization, in violation of Section 28(2) of the Act

The court held

The High Court dismissed both appeals, affirming the Commercial Court's refusal to set aside the award

It also directed

It held that the Arbitrator’s decision to cancel the JDA and restore parties to their pre-contract position via a monetary refund was a "plausible view" not vitiated by patent illegality

The cancellation of the GPA was upheld as a natural consequence of the JDA's termination

The Landowners' challenge to the monetary award was also rejected as it was based on factual evidence accepted by the Tribunal

01Facts

The Appellant (FCIPL) and the Respondents (Landowners) entered into a Memorandum of Understanding (MOU) in 2013 and a registered Joint Development Agreement (JDA) in 2014 for an apartment complex

pp. 8-9

Execution was delayed primarily due to an order by the National Green Tribunal (NGT) regarding buffer zones around water bodies, which was subsequently challenged in the Supreme Court

p. 10

The Landowners terminated the JDA in 2018 alleging breach of time-lines, whereas FCIPL claimed the Landowners obstructed the project by withdrawing cooperation after the Supreme Court's 2019 ruling

p. 11, 29

A Sole Arbitrator passed an award dated 12.06.2023 cancelling the JDA and GPA, while directing the Landowners to refund ₹65,00,000/- to FCIPL

p. 13

Both parties challenged the award under Section 34 of the Arbitration and Conciliation Act, which the Commercial Court dismissed on 30.01.2024

pp. 17-18

02Issues

i.1. Whether the Arbitral Tribunal exceeded its jurisdiction by deciding "ex aequo et bono" (interests of justice and equity) without express authorization, in violation of Section 28(2) of the Act

p. 18 / para. 28

ii.2. Whether the award was patently illegal due to contradictory findings regarding mutual breach and the resulting cancellation of the JDA

p. 19 / para. 29

iii.3. Whether the court could interfere with the Arbitrator’s factual determination of the refund amount

p. 17 / para. 25

03Law Applied

Section 28(2) of the Arbitration and Conciliation Act, 1996, which prohibits an arbitrator from deciding ex aequo et bono unless expressly authorized

p. 36

Section 34 regarding the limited grounds for setting aside an award, specifically focusing on "patent illegality" and "public policy"

p. 14, 41

Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd., which mandates that an award must have intelligible and adequate reasoning, but the court should not set aside awards for mere "gaps in reasoning" if the conclusion is plausible

pp. 38-39

Provisions in the judgment · 9 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 11Section 26Section 28Section 31Section 33Section 34Section 37

Commercial Courts Act, 2015 Section 13

Code of Civil Procedure, 1908 Section 26

04Reasoning

The Court examined the Arbitrator’s reasoning that both parties were responsible for the project's failure

¶ 56

While the Arbitrator used the phrase "interest of justice and equity," the Court analyzed this not as a departure from the law, but as a practical consequence of the finding of mutual breach

¶ 62-64

The Court noted that FCIPL's failure to take "effective steps" to resubmit plans after the NGT stay was lifted constituted a breach, rendering the denial of specific performance a legal and plausible outcome

p. 35, 37

Regarding the refund of ₹65,00,000/-, the Court held that the Arbitrator meticulously analyzed the evidence and receipts produced by FCIPL, and a Section 34 court cannot re-evaluate such factual findings or supplant its own opinion

p. 38, 40

05Holding

The High Court dismissed both appeals, affirming the Commercial Court's refusal to set aside the award

p. 41

It held that the Arbitrator’s decision to cancel the JDA and restore parties to their pre-contract position via a monetary refund was a "plausible view" not vitiated by patent illegality

pp. 40-41

The cancellation of the GPA was upheld as a natural consequence of the JDA's termination

p. 16

The Landowners' challenge to the monetary award was also rejected as it was based on factual evidence accepted by the Tribunal

p. 17
Karnataka High Court

Original Court PDF

M/S FORTUNA CONSTRUCTIONS INDIA PVT LTDvsSMT. SHAMALAMMA

Karnataka High Court · July 20, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment

Related judgments

Recent judgments that share this one’s subject or court. Hover a card to read what was held.

All Arbitration and Mediation judgments →