01Facts
The Appellant (NHAI) and Respondent (Unitech-NCC JV) entered into a contract on 25.05.2001 for the upgrade of NH-5 in Andhra Pradesh
p. 2The project was delayed by 13 months, completing on 20.03.2005 instead of February 2004
p. 3Disputes arose regarding financial consequences of the delay, leading to horizontal arbitration. A three-member Tribunal rendered an Award on 16.05.2011, granting the Respondent compensation for additional mobilization (Claim 3), idling costs (Claim 4), and loss of opportunity to earn a bonus (Claim 7)
pp. 3-4NHAI challenged the Award under Section 34 of the Arbitration and Conciliation Act, 1996 ("A&C Act"), which the learned Single Judge dismissed on 30.05.2025
p. 502Issues
i.1. Whether the Arbitral Tribunal’s award for additional mobilization and idling of machinery (Claims 3 and 4) was based on sufficient evidence or was patently illegal
p. 18, 25ii.2. Whether the award of compensation for "loss of opportunity to earn bonus" (Claim 7) was contrary to express contractual prohibitions (Clause 47.3)
pp. 30-31iii.3. Whether the delay of eight months in the pronouncement of the Section 34 judgment vitiated the decision
p. 1703Law Applied
The Court applied the restrictive standards for judicial interference under Sections 34 and 37 of the A&C Act, relying on NHAI v. M. Hakeem and UHL Power Co. Ltd. v. State of Himachal Pradesh to establish that Section 37 jurisdiction is narrower than Section 34 and prohibits merit-based reassessment
p. 14, 16It relied on McDermott International Inc. v. Burn Standard Co. Ltd. regarding the arbitrator's prerogative to interpret contracts
p. 15Section 73 of the Indian Contract Act, 1872, was applied to award damages for breach of contract (failure to provide a clear site)
p. 26, 31Regarding delay in judgment, it followed the principle from Anil Rai v. State of Bihar that delay is not ipso facto fatal unless prejudice is shown
p. 17Provisions in the judgment · 3 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 34Section 37
Indian Contract Act, 1872 Section 73
04Reasoning
The Court observed that the Tribunal's findings on Claim 3 were rooted in contemporaneous records like Monthly Progress Reports (MPRs) and the Engineer's letter confirming that the site was handed over in 36 fragmented pieces, necessitating additional machinery deployment
pp. 18-19The Court rejected NHAI's argument that the award was speculative, noting the Tribunal actually used NHAI's own data to reduce the claim significantly
p. 20For Claim 4, the Court found that the Tribunal properly distinguished between "additional mobilization" and "idling costs of minimum resources" during the extension period
pp. 25-27Regarding Claim 7, the Court reasoned that while Clause 47.3 prohibited contractual bonus during extensions, the Tribunal awarded it as damages under Section 73 for the loss of opportunity to earn that bonus caused by NHAI’s breaches
pp. 30-31The Court emphasized that interpreting these clauses and assessing evidence falls within the sole domain of the arbitrator; as long as the view is "plausible," the Court cannot substitute it with its own
p. 3305Holding
The Court answered all issues in the negative and dismissed the Appeal
p. 34It held that the Tribunal’s findings were based on a plausible interpretation of the contract and evidenced by contemporaneous project records. The effective relief under Claim 7 was neutralized by adjustments against Claim 3 to prevent double recovery. The Court affirmed the Single Judge's decision, ruling that NHAI failed to demonstrate patent illegality or perversity warranting interference under Section 37
p. 29, 34Original Court PDF
National Highways Authority Of IndiavsM/S Unitech-Ncc Jv
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
