Bombay High Court

No additional lease premium is leviable for construction delays caused by pending litigation involving the planning authority.

RAJKUMAR CHANDRASEN CHAVAN vs MANAGING DIRECTOR CIDCO LIMITED

Bombay High CourtJUDGMENT: March 27, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

CIDCO allotted a plot in Kharghar to one Mr. Mapara in 2005, executing a lease agreement in October 2010

Source reference: para 2, 5

In December 2010, the Petitioner entered into an agreement with Mr. Mapara to acquire the leasehold rights

Source reference: para 3

Due to Mr. Mapara’s subsequent refusal to perform the contract, the Petitioner filed a suit for specific performance in 2011, impleading CIDCO as a defendant

Source reference: para 6

The Trial Court granted an interim injunction restraining the defendants from transferring or disposing of the property

Source reference: para 7

The suit was decreed in favor of the Petitioner in 2018, and execution proceedings followed

Source reference: para 8, 9

In June 2024, CIDCO issued demand notices for Additional Lease Premium (ALP) totaling ₹80,72,507/- for the period 2014–2024, citing the failure to complete construction within the four-year period prescribed in the lease

Source reference: para 13, 17

The Petitioner challenged these notices, arguing that the delay was due to pending litigation and judicial restraint

Source reference: para 11, 12
02

Issues

1. Whether the Petitioner, as a transferee under a decree for specific performance, is liable to pay Additional Lease Premium (ALP) for a period where construction was delayed due to active litigation and judicial orders

Source reference: para 29, 34

2. Whether the benefit of CIDCO’s Board Resolution providing for 0% ALP during litigation periods applies to the Petitioner

Source reference: para 31, 39
03

Law Applied

The court examined the Navi Mumbai Disposal of Lands (Amendment) Regulations, 2008, specifically Regulation 7, which mandates construction completion within four years

Source reference: para 30

Regulation 8, which allows for time extensions upon payment of ALP

Source reference: para 30

Regulation 10, which requires a transferee to observe all conditions of the original lease

Source reference: para 30

The court further applied the CIDCO Board Resolutions (BR 11885 and 12209), which establish a policy that ALP shall be levied at 0% for periods where a licensee is restrained from commencing or continuing construction due to court cases or judicial orders, provided CIDCO is a party to the litigation

Source reference: para 31
04

Reasoning

The court rejected CIDCO’s contention that construction could have proceeded because the interim injunction only restrained "transfer" and not "construction."

Source reference: para 36, 37

The court reasoned that it was "impossible" for the Petitioner to commence construction or apply for building permissions while his title was still being disputed by Mr. Mapara in a pending suit

Source reference: para 36, 37

It noted that the Petitioner only obtained legal possession and the right to execute the tripartite agreement after the decree was passed and executed

Source reference: para 37, 40

The court found that since CIDCO was a party to the suit, the conditions of the Board Resolution for 0% ALP were met

Source reference: para 39

The court held that holding the Petitioner liable for the breach committed by the original allottee (Mr. Mapara) during the litigation period was "harsh," "unfair," and "arbitrary"

Source reference: para 38, 40

It clarified that while Regulation 10 requires a transferee to step into the shoes of the lessee, such compliance is only feasible once the decree is executed

Source reference: para 40
05

Holding

The High Court allowed the Writ Petition and quashed the demand notices dated 25/06/2024 and 27/06/2024

The court held that ALP must be levied at 0% for the period the Petitioner was restrained by the circumstances of the litigation and judicial orders

Source reference: para 39

It further observed that CIDCO remains at liberty to pursue claims against the original allottee, Mr. Mapara, if permissible under law, but cannot penalize the Petitioner

Source reference: para 40, 42
Bombay High Court

Original Court PDF

RAJKUMAR CHANDRASEN CHAVANvsMANAGING DIRECTOR CIDCO LIMITED

Bombay High Court · March 27, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment