No further direction is warranted where the department reports restoration of the agricultural electricity connection.

Rashid Imam @ Md. Rashid Imam vs The State of Bihar

Patna High CourtJUDGMENT: October 07, 20262 MIN READSOURCE JUDGMENT
No further direction is warranted where the department reports restoration of the agricultural electricity connection.. Rashid Imam @ Md. Rashid Imam vs The State of Bihar. Patna High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner sought an agricultural electricity connection for his land at Mouza Gogi, Araria.

Source reference: no citation

Although poles, wires and a meter had been installed, he alleged that the last pole was about one kilometre from his land, leaving him unable to irrigate while electricity bills were issued

Source reference: pp. 2–3

The Electricity Department stated that the connection had been provided and restored following verification, and that an erroneous bill had been corrected and the excess adjusted

Source reference: p. 4

The petitioner maintained that the connection remained more than one and a half kilometres from his land and boring, and was therefore unusable for irrigation

Source reference: pp. 5–6

The petitioner filed the writ petition seeking a usable connection at his agricultural land

Source reference: pp. 1–3
02

Issues

Whether the petitioner was entitled to a direction requiring the respondents to provide a usable agricultural electricity connection at his land

Source reference: pp. 1–3, 8–9

Whether any further direction was warranted in light of the Department’s statement that the connection had been provided and restored and the billing error corrected

Source reference: pp. 8–9
03

Law Applied

The judgment does not identify or apply any specific statute, regulation, precedent, or articulated legal doctrine.

Source reference: no citation

The Court considered the Department’s statements that the agricultural connection had been provided and restored after departmental verification and that the erroneous bill had been corrected and the excess amount adjusted

Source reference: pp. 8–9

It permitted the petitioner to approach the concerned authority if he continued to face a specific technical difficulty

Source reference: p. 9
04

Reasoning

The Court relied on the Department’s account of the connection, restoration, and bill correction in concluding that no further direction was required in the writ petition

Source reference: pp. 8–9

Although the petitioner disputed that the connection was located at or usable for his land, the Court did not resolve that factual disagreement; instead, it left the petitioner at liberty to seek redress from the concerned authority if a specific technical difficulty persisted

Source reference: pp. 6, 9
05

Holding

The Court held that no further direction was required and dismissed the writ petition.

It left the petitioner at liberty to approach the concerned authority for redress of any continuing specific technical difficulty with the connection

Source reference: p. 9

Any interlocutory applications were also disposed of

Source reference: p. 10
Patna High Court

Original Court PDF

Rashid Imam @ Md. Rashid ImamvsThe State of Bihar

Patna High Court · October 07, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment