Facts
The petitioner sought an agricultural electricity connection for his land at Mouza Gogi, Araria.
Source reference: no citationAlthough poles, wires and a meter had been installed, he alleged that the last pole was about one kilometre from his land, leaving him unable to irrigate while electricity bills were issued
Source reference: pp. 2–3The Electricity Department stated that the connection had been provided and restored following verification, and that an erroneous bill had been corrected and the excess adjusted
Source reference: p. 4The petitioner maintained that the connection remained more than one and a half kilometres from his land and boring, and was therefore unusable for irrigation
Source reference: pp. 5–6The petitioner filed the writ petition seeking a usable connection at his agricultural land
Source reference: pp. 1–3Issues
Whether the petitioner was entitled to a direction requiring the respondents to provide a usable agricultural electricity connection at his land
Source reference: pp. 1–3, 8–9Whether any further direction was warranted in light of the Department’s statement that the connection had been provided and restored and the billing error corrected
Source reference: pp. 8–9Law Applied
The judgment does not identify or apply any specific statute, regulation, precedent, or articulated legal doctrine.
Source reference: no citationThe Court considered the Department’s statements that the agricultural connection had been provided and restored after departmental verification and that the erroneous bill had been corrected and the excess amount adjusted
Source reference: pp. 8–9It permitted the petitioner to approach the concerned authority if he continued to face a specific technical difficulty
Source reference: p. 9Reasoning
The Court relied on the Department’s account of the connection, restoration, and bill correction in concluding that no further direction was required in the writ petition
Source reference: pp. 8–9Although the petitioner disputed that the connection was located at or usable for his land, the Court did not resolve that factual disagreement; instead, it left the petitioner at liberty to seek redress from the concerned authority if a specific technical difficulty persisted
Source reference: pp. 6, 9Holding
The Court held that no further direction was required and dismissed the writ petition.
It left the petitioner at liberty to approach the concerned authority for redress of any continuing specific technical difficulty with the connection
Source reference: p. 9Any interlocutory applications were also disposed of
Source reference: p. 10Original Court PDF
Rashid Imam @ Md. Rashid ImamvsThe State of Bihar
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in