Facts
The appellant, a solar power developer, established a 20 MW solar project at Kudligi, Karnataka, pursuant to a Letter of Award issued by Karnataka Renewable Energy Development Limited and a Power Purchase Agreement (“PPA”) with Bangalore Electricity Supply Company Limited (“BESCOM”).
Source reference: paras. 2, 5–6The PPA was approved by the Karnataka Electricity Regulatory Commission (“KERC”) on 04.05.2018, making 03.11.2019 the Scheduled Commercial Operation Date (“SCOD”).
Source reference: para. 8Although the appellant completed the project and obtained CEIG and PTCC approvals by 23.10.2019, the 220/66 kV Kudligi sub-station and associated upstream transmission facilities of Karnataka Power Transmission Corporation Limited (“KPTCL”) were not ready by the SCOD.
Source reference: paras. 15, 20–22, 40–42The appellant issued force majeure notices to BESCOM, including on 23.10.2019, and repeatedly sought information and action from KPTCL regarding the evacuation facilities.
Source reference: paras. 46–51The sub-station was ultimately test-charged on 30.05.2020, and the project achieved commercial operation on that date.
Source reference: paras. 21–22The appellant sought extension of the SCOD to 30.05.2020 and exemption from liquidated damages, reduced tariff and other contractual penalties.
Source reference: paras. 23, 25–32KERC rejected the petition, holding that the delay was not covered by the PPA’s force majeure clause and that the appellant was liable for the contractual consequences of delayed commissioning.
Source reference: paras. 23, 25–32Issues
Whether the appellant’s solar project was completed and ready for commissioning by the SCOD of 03.11.2019.
Source reference: paras. 25–26, 40–42Whether the non-availability and delayed commissioning of KPTCL’s Kudligi sub-station and associated transmission facilities constituted a force majeure event under Article 14.3.1 of the PPA.
Source reference: paras. 25, 43–53Whether the appellant was precluded from invoking force majeure because it had accepted the tentative and regular evacuation scheme approvals, or was required to pursue an alternative evacuation arrangement.
Source reference: paras. 25, 27–29, 43–49Whether the appellant complied with the PPA’s procedural requirements for invoking force majeure, including timely notice under Article 14.5.1.
Source reference: paras. 36, 39, 59Whether the appellant was liable for liquidated damages, reduced tariff or other contractual penalties for commissioning after the original SCOD.
Source reference: paras. 25, 30–31, 36–38Law Applied
The Tribunal applied Articles 5.7, 5.8 and 14 of the PPA.
Source reference: paras. 36–39Article 5.7.1 permitted the developer, after commissioning, to approach KERC for condonation of delay caused by a BESCOM default or a force majeure event affecting BESCOM or the developer; Article 5.7.3 provided that, if condoned, the SCOD would be extended for the period of delay.
Source reference: paras. 36–38Article 5.8 imposed liquidated damages for delayed commencement of supply only where the delay was not attributable to the circumstances specified in Article 5.7.1.
Source reference: paras. 36–38Article 14.3.1 defined force majeure as an event beyond the affected party’s reasonable control that prevented or unavoidably delayed performance, including the unlawful, unauthorized or unjustified refusal or delay in granting a required permit, authorization, consent or approval.
Source reference: paras. 36, 39, 52Article 14.4 excluded events within the parties’ reasonable control and specified contractual or negligent defaults.
Source reference: paras. 36, 39, 52Article 14.5.1 required timely notice of the force majeure event, ordinarily within seven days of knowledge of its commencement.
Source reference: paras. 36, 39The Tribunal also applied the contractual interpretation principles in Nabha Power Ltd. v. Punjab State Power Corporation Ltd., (2018) 11 SCC 508, including the “business efficacy” test for implying a term where necessary, obvious, reasonable, capable of clear expression and consistent with the express contract.
Source reference: paras. 54–58Chamundeshwari Electricity Supply Co. Ltd. v. Saisudhir Energy (Chitradurga) Pvt. Ltd., (2026) 1 SCC 799, was distinguished on the ground that it concerned the absence of a properly obtained contractual extension, whereas the appellant here had invoked the relevant contractual procedure.
Source reference: para. 60Reasoning
The Tribunal accepted KERC’s finding that the project itself was ready for commissioning before the SCOD, relying on the CEIG and PTCC approvals dated 23.10.2019; the respondents had not effectively challenged that finding.
Source reference: paras. 40–42The appellant had initially been informed by KPTCL that the sub-station and incoming transmission line would be commissioned by 30.04.2019 and 30.06.2019, both dates preceding the SCOD.
Source reference: paras. 45–49The appellant nevertheless followed up with KPTCL in July and August 2019 and approached the Commission when no confirmation was received.
Source reference: paras. 45–49Accordingly, its acceptance of the evacuation scheme could not be treated as negligence or an intentional assumption of the risk of delay.
Source reference: paras. 43–49Since the project could not be commissioned or supply power without KPTCL’s evacuation authorization and facilities, the delayed commissioning of the sub-station and associated lines fell within Article 14.3.1(e), and none of the exclusions in Article 14.4 applied.
Source reference: paras. 52–53The Tribunal further held that treating a KPTCL-caused delay as outside the PPA’s extension mechanism would unfairly penalize the appellant for an event beyond its control; reading the PPA to include such a transmission-licensee default was necessary to give the contract business efficacy and avoid an inequitable result.
Source reference: paras. 54–58The appellant also substantially complied with the notice requirement by issuing an initial force majeure notice in February 2019 and a fresh notice immediately after learning in October 2019 that the evacuation facilities would not be available by the SCOD.
Source reference: para. 59Consequently, the delay was attributable to the non-availability of the evacuation system, not to any default by the appellant.
Source reference: para. 61Holding
The Tribunal set aside KERC’s order dated 11.06.2021 and held that the delayed commissioning of the Kudligi sub-station, including its incoming lines and terminal bays, constituted a force majeure event under Article 14.3.1 of the PPA and was not attributable to the appellant.
The SCOD was extended from 03.11.2019 to the actual commissioning and synchronization date of 30.05.2020.
Source reference: para. 61The appellant was consequently held not liable for liquidated damages, reduction in tariff or any other contractual penalty arising from failure to commission by the original SCOD.
Source reference: para. 62The appeal was allowed and pending applications, if any, were disposed of.
Source reference: para. 63Acts & Sections Cited
1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Electricity Act, 20031
Original Court PDF
M/s ACME Kudligi Solar Energy Private LimitedvsKarnataka Electricity Regulatory Commission & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
