Facts
The Appellant, a state-owned distribution licensee, challenged the Bihar Electricity Regulatory Commission’s (BERC) orders dated 21.03.2018 and 19.12.2018, which determined the truing up of the Aggregate Revenue Requirement (ARR) for FY 2016-17 and tariff determination for FY 2018-19
Source reference: p. 2, 3The Appellant was formed following the restructuring of the Bihar State Electricity Board under Section 131 of the Electricity Act, 2003
Source reference: para. 3The core dispute arose from BERC’s disallowance of several claims, including fixed costs for power purchase from Adani Enterprises Limited (AEL), prior period expenses, and the imposition of a 1% "deemed rebate" on power purchases
Source reference: para. 5Issues
1. Whether the State Commission was justified in disallowing fixed capacity charges paid to AEL for April–June 2016 on the grounds of imprudent demand forecasting
Source reference: para. 62. Whether a 1% normative "deemed rebate" on power purchase can be treated as non-tariff income in the absence of actual realization
Source reference: para. 193. Whether prior period expenses can be disallowed for lack of item-wise details despite being reflected in audited accounts
Source reference: para. 244. Whether the apportionment of fixed and variable costs in tariff design for FY 2018-19 was erroneous regarding PPA capacity charges
Source reference: para. 275. Whether the Interest on Working Capital (IoWC) for FY 2016-18 was correctly computed, specifically concerning the retrospective application of regulatory amendments
Source reference: para. 31, 326. Whether Late Payment Surcharge (LPSC) paid to generators is a pass-through expense
Source reference: para. 39Law Applied
The Tribunal applied the Bihar Electricity Regulatory Commission (Multi-Year Distribution Tariff) Regulations, 2015 ("MYDT Regulations 2015"), specifically Regulation 9.1(d) regarding uncontrollable factors, Regulation 20.2(5) regarding operational inefficiency, and Regulation 26 regarding Working Capital.
Source reference: p. 5, 9, 17, 19It also considered Regulation 44 of the CERC Tariff Regulations, 2014, regarding the rebate structure.
Source reference: p. 12The court relied on the principle of "least-cost procurement" and Section 61 of the Electricity Act, 2003, which mandates safeguarding consumer interests through a "prudence check".
Source reference: p. 9, 13The precedent NDPL v. DERC (Appeal No. 153 of 2009) was distinguished regarding the treatment of rebates.
Source reference: p. 11Reasoning
Regarding AEL costs, the Tribunal found that substituting AEL power with cheaper exchange power resulted in tangible consumer savings (approx. Rs. 47.42 Crore) despite the fixed cost liability; thus, the disallowance was unjustified.
Source reference: para. 12-14On the "deemed rebate," the Tribunal held that BERC cannot assume a normative 1% income if it was not actually earned, as regulations do not mandate DISCOMs to structure finances solely to avail rebates.
Source reference: para. 22, 23For prior period expenses, while audited accounts are credible, the Commission’s right to a "prudence check" under Section 61 allows it to demand year-wise details.
Source reference: para. 26Regarding IoWC, the Tribunal ruled that the 30.06.2017 amendment to Regulation 26 could not be applied retrospectively to the period before its notification (11.07.2017).
Source reference: para. 34Furthermore, it held that disallowed power purchase costs should not be deducted when calculating the working capital requirement, as it creates an artificial reduction in the ARR.
Source reference: para. 36Finally, the LPSC was disallowed because the DISCOM already received financing costs on its receivables (Delayed Payment Surcharge), and allowing LPSC on payables would constitute a double benefit.
Source reference: para. 41Holding
The Tribunal partly allowed the appeal.
It set aside the disallowance of AEL fixed costs for April–June 2016 and reversed the 1% deemed rebate, directing that only actual rebates be considered.
Source reference: para. 17, 23The disallowance of prior period expenses and LPSC was upheld, though the Appellant was granted liberty to provide better details for the former.
Source reference: para. 26, 41The IoWC issue was remanded to BERC for re-computation on a prorated basis for FY 2017-18 and to exclude disallowed power purchase costs from the deduction.
Source reference: para. 35, 36, 42BERC was directed to pass consequential orders within four months.
Source reference: p. 22Original Court PDF
NORTH BIHAR POWER DISTRIBUTION COMPANY LIMITEDvsBIHAR ELECTRICITY REGULATORY COMMISSION & Anr
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in