Delhi High Court

Past performance in unrelated projects may justify technical disqualification if relevant to bidder suitability.

Bhilai Engineering Corporation Limited vs Steel Authority Of India Limited

Delhi High CourtJUDGMENT: May 14, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner (Bhilai Engineering Corp.) challenged a letter dated 18.04.2024 and an internal advisory dated 17.09.2022 issued by the Respondent (SAIL) which led to the Petitioner’s technical disqualification from a global tender for a "Stamp Charged Coke Oven Battery" project at the IISCO Steel Plant.

Source reference: p. 1-2

The disqualification was based on an internal "adverse report" regarding the Petitioner’s unsatisfactory performance as an EPC contractor in a separate Sinter Plant project at Bokaro Steel Limited (BSL).

Source reference: p. 2, 6

Following a previous High Court direction in W.P.(C) 4044/2024, SAIL provided the Petitioner a hearing and issued a detailed speaking order rejecting their representation, noting that the BSL project remained stalled due to factors attributable to the Petitioner.

Source reference: p. 3-4, 6

During the pendency of this writ, the contract was awarded to a third-party consortium, which had already completed 25% of the work.

Source reference: p. 4, 9
02

Issues

1. Whether the Respondent was justified in rejecting the Petitioner’s technical bid based on an inter-departmental advisory regarding poor performance in a different project.

Source reference: p. 2 / para. 3(i)

2. Whether the disqualification and the internal advisory amounted to permanent or illegal blacklisting without following due process.

Source reference: p. 4 / para. 10

3. Whether it is appropriate to set aside the award of the contract after significant work has been completed by a successful bidder who is not a party to the suit.

Source reference: p. 2 / para. 3(ii)
03

Law Applied

Article 226 of the Constitution of India regarding the scope of judicial review in contractual matters, emphasizing that courts should only interfere if there is a gross violation of public interest or arbitrary exercise of power.

Source reference: p. 2, 5

Clause 9.3 of the Purchase Contract Procedure (PCP) and Clause 13 of Section-A of the Tender, which empowers the employer to consider the "capability and past performance" of bidders in other projects during evaluation.

Source reference: p. 5, 10

Principles of natural justice and proportionality, distinguishing between internal performance assessments and external debarment, while noting the standards for "drastic remedies" established in Banshidhar Construction Pvt. Ltd. v. Bharat Coking Coal Ltd. and Blue Dreamz Advertising Pvt. Ltd. v. Kolkata Municipal Corporation.

Source reference: p. 13
04

Reasoning

The court reasoned that SAIL, as a public sector undertaking, is entitled to assess a bidder’s suitability based on past performance.

Source reference: p. 10

It rejected the argument that the BSL project was "unrelated," noting that even though the technologies (Top Charged vs. Stamp Charged) differ, the Petitioner’s failure as a lead EPC contractor at BSL was a valid technical concern.

Source reference: p. 9-10

The court found no violation of natural justice because the Petitioner was granted a representation and oral hearing following the previous court order.

Source reference: p. 11

On the charge of "blacklisting," the court observed that the advisory was an internal communication and did not prevent the Petitioner from securing other contracts (notably, the Petitioner had secured works worth ₹1,500 crores after the advisory was issued), thus it did not constitute an indefinite debarment.

Source reference: p. 11

Furthermore, the court highlighted that 25% of the vital project—essential for steel production—was already finished, and equity favored the Respondent as the successful bidder was not impleaded.

Source reference: p. 8-9
05

Holding

The Court dismissed the petition, holding that the Respondent’s decision to disqualify the Petitioner based on documented poor performance in a prior project was neither arbitrary nor mala fide.

The court held that judicial interference was unwarranted given the public interest in the timely completion of the steel plant and the fact that the Petitioner was provided a fair hearing.

Source reference: p. 11, 13

While dismissing the challenge, the court directed that the Respondent remains bound by its statement to reconsider the internal advisory if the Petitioner submits a representation demonstrating improved performance in the future.

Source reference: p. 14 / para. 36
Delhi High Court

Original Court PDF

Bhilai Engineering Corporation LimitedvsSteel Authority Of India Limited

Delhi High Court · May 14, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment