Patna High Court

Paucity of funds or internal procedural irregularities cannot justify withholding payment for admittedly completed contractual works.

M/s Ghanshyam Lal vs The State of Bihar

Patna High CourtJUDGMENT: July 24, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner, a registered partnership firm, was awarded four road projects under the PMGSY Scheme involving construction and a five-year maintenance period.

Source reference: paras. 2-3

The petitioner completed the construction and maintenance works to the satisfaction of the authorities.

Source reference: para. 4

Despite the Executive Engineer recommending payment and requesting fund allotments via communications dated 09.06.2018 and 08.10.2020, the dues remained unpaid.

Source reference: paras. 5-6

The respondents contended that payment was withheld due to non-allotment of funds and subsequent discovery of procedural irregularities in the Measurement Book (consolidated entries instead of periodic ones), which triggered a preliminary enquiry.

Source reference: paras. 9, 15-16
02

Issues

1. Whether the respondents can withhold payment for admittedly completed maintenance work on the grounds of "paucity of funds" or "technical/procedural irregularities" in internal departmental records?

Source reference: para. 26

2. Whether the continued withholding of admitted dues for nearly eight years amounts to arbitrary action and unjust enrichment?

Source reference: para. 28
03

Law Applied

The Court applied the constitutional principle of Equality under Article 14 of the Constitution of India, which prohibits arbitrary and unreasonable State action.

Source reference: para. 11

It relied on the doctrine of "Admitted Liability," holding that once a contractual obligation is verified and acknowledged by the State through its officials, it must be honored within a reasonable timeframe.

Source reference: paras. 25-27

Furthermore, the Court recognized the principle of "Unjust Enrichment," asserting that the State cannot enjoy the benefits of a contractor's work without making the stipulated payment.

Source reference: para. 28
04

Reasoning

The Court observed that the respondents did not dispute the quality or execution of the work.

Source reference: para. 24

The pivotal evidence was Letter No. 781 (2018) and Letter No. 1270 (2020), where the Executive Engineer sought fund allotments, effectively acknowledging the debt.

Source reference: para. 25

The Court rejected the respondents' defense regarding irregularities in the Measurement Book, reasoning that since the book is a departmental record maintained by state officials, a contractor cannot be penalized for internal procedural lapses or administrative delays.

Source reference: para. 26

It found that the "verification process" and "departmental enquiry" cited by the State were afterthoughts raised years after the maintenance period had expired (2016-2017) to delay legitimate payment.

Source reference: paras. 21, 26
05

Holding

The Court allowed the writ petition, holding that the petitioner cannot be denied payment for work admittedly executed and accepted.

The Court characterized the eight-year delay as arbitrary and unjustified.

Source reference: para. 28

It directed the Executive Engineer to ensure the release of admitted dues for the four packages (BR-35R-021, BR-35R-028, BR-35R-033, and BR-35R-035) within two months.

Source reference: paras. 29-30

The Executive Engineer was further ordered to immediately pursue any necessary administrative approvals or fund allotments to comply with this timeline.

Source reference: para. 30
Patna High Court

Original Court PDF

M/s Ghanshyam LalvsThe State of Bihar

Patna High Court · July 24, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment