Facts
The petitioner, a registered partnership firm, was awarded four road projects under the PMGSY Scheme involving construction and a five-year maintenance period.
Source reference: paras. 2-3The petitioner completed the construction and maintenance works to the satisfaction of the authorities.
Source reference: para. 4Despite the Executive Engineer recommending payment and requesting fund allotments via communications dated 09.06.2018 and 08.10.2020, the dues remained unpaid.
Source reference: paras. 5-6The respondents contended that payment was withheld due to non-allotment of funds and subsequent discovery of procedural irregularities in the Measurement Book (consolidated entries instead of periodic ones), which triggered a preliminary enquiry.
Source reference: paras. 9, 15-16Issues
1. Whether the respondents can withhold payment for admittedly completed maintenance work on the grounds of "paucity of funds" or "technical/procedural irregularities" in internal departmental records?
Source reference: para. 262. Whether the continued withholding of admitted dues for nearly eight years amounts to arbitrary action and unjust enrichment?
Source reference: para. 28Law Applied
The Court applied the constitutional principle of Equality under Article 14 of the Constitution of India, which prohibits arbitrary and unreasonable State action.
Source reference: para. 11It relied on the doctrine of "Admitted Liability," holding that once a contractual obligation is verified and acknowledged by the State through its officials, it must be honored within a reasonable timeframe.
Source reference: paras. 25-27Furthermore, the Court recognized the principle of "Unjust Enrichment," asserting that the State cannot enjoy the benefits of a contractor's work without making the stipulated payment.
Source reference: para. 28Reasoning
The Court observed that the respondents did not dispute the quality or execution of the work.
Source reference: para. 24The pivotal evidence was Letter No. 781 (2018) and Letter No. 1270 (2020), where the Executive Engineer sought fund allotments, effectively acknowledging the debt.
Source reference: para. 25The Court rejected the respondents' defense regarding irregularities in the Measurement Book, reasoning that since the book is a departmental record maintained by state officials, a contractor cannot be penalized for internal procedural lapses or administrative delays.
Source reference: para. 26It found that the "verification process" and "departmental enquiry" cited by the State were afterthoughts raised years after the maintenance period had expired (2016-2017) to delay legitimate payment.
Source reference: paras. 21, 26Holding
The Court allowed the writ petition, holding that the petitioner cannot be denied payment for work admittedly executed and accepted.
The Court characterized the eight-year delay as arbitrary and unjustified.
Source reference: para. 28It directed the Executive Engineer to ensure the release of admitted dues for the four packages (BR-35R-021, BR-35R-028, BR-35R-033, and BR-35R-035) within two months.
Source reference: paras. 29-30The Executive Engineer was further ordered to immediately pursue any necessary administrative approvals or fund allotments to comply with this timeline.
Source reference: para. 30Original Court PDF
M/s Ghanshyam LalvsThe State of Bihar
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in