Facts
The Petitioner (Engineering Projects India Limited) was awarded an Engineering, Procurement, and Construction (EPC) contract by Respondent No. 1 (Southern Railway) for the redevelopment of Katpadi Railway Station.
Source reference: p. 1-2Pursuant to the contract, the Petitioner furnished three bank guarantees (Performance, Mobilization Advance, and Additional Performance) totaling approximately Rs. 31.28 Crores.
Source reference: p. 2Disputes arose leading to two prior rounds of litigation under Section 9 of the Arbitration and Conciliation Act where interim protection was granted or the invocation was withdrawn.
Source reference: p. 2-3Following a third termination on 12.08.2025 and subsequent invocation letters dated 03.11.2025, the Petitioner approached the Court again.
Source reference: p. 3On 07.11.2025, the Court granted ad interim protection as the contractual completion period (30.11.2025) had not yet expired.
Source reference: p. 4However, by the time of the final hearing, the project remained incomplete, the contract was terminated, and the contractual deadline had passed.
Source reference: p. 9Issues
1. Whether the Petitioner made out a case for the continuation of an interim injunction restraining the invocation of unconditional and irrevocable bank guarantees after the expiry of the contractual period.
Source reference: p. 4, para 132. Whether the pendency of a mandatory pre-arbitral conciliation mechanism under the contract is a valid ground to restrain the invocation of a bank guarantee.
Source reference: p. 5, para 16-17; p. 9, para 34-35Law Applied
The court applied Section 9 of the Arbitration and Conciliation Act, 1996.
Source reference: p. 1It relied on the settled doctrine that a bank guarantee is an independent and autonomous contract between the bank and the beneficiary, distinct from the underlying commercial dispute.
Source reference: p. 7-8It cited United Commercial Bank v. Bank of India and U.P. Cooperative Federation Ltd. v. Singh Consultants & Engineers (P) Ltd., which established that judicial interference in unconditional bank guarantees is permitted only in cases of "egregious fraud" or "irretrievable injustice".
Source reference: p. 8Furthermore, per National Thermal Power Corporation Ltd v. Flowmore Pvt. Ltd., the mere pendency of arbitration (or conciliation) does not justify restraining the encashment of such guarantees.
Source reference: p. 10Reasoning
The Court reasoned that its jurisdiction under Section 9 is limited and does not extend to adjudicating the merits of the contract, such as the legality of termination or responsibility for delays.
Source reference: p. 7While the ad interim order of 07.11.2025 was justified because the contract period was still active, the subsequent expiry of the deadline on 30.11.2025 without project completion materially changed the factual foundation.
Source reference: p. 9The Petitioner failed to provide evidence of egregious fraud or prove that restitution would be impossible (irretrievable harm) if they eventually succeeded in arbitration.
Source reference: p. 10The Court specifically rejected the argument that the pending conciliation process should stay the invocation, noting that such a process cannot enlarge the scope of judicial interference with a bank’s obligation to pay on demand.
Source reference: p. 9-10Holding
The Court answered the issues in the negative, holding that the Petitioner failed to establish any recognized legal exception warranting the continuation of the injunction.
The Court vacated the interim order dated 07.11.2025 and dismissed the petition. It clarified that these observations are limited to the Section 9 proceedings and do not reflect an opinion on the merits of the underlying contractual disputes to be decided by an arbitral tribunal.
Source reference: p. 11Original Court PDF
Engineering Projects India LimitedvsSouthern Railway & Anr.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in