Madras High Court
Administrative and Public LawContract Law

Pending appeal does not suspend the duty to align wheeling agreements with tariff orders.

M/S.MULLAI SOLAR GREEN ENERGY PVT. LTD., vs TAMIL NADU ELECTRICITY REGULATORY COMMISSION

Madras High CourtJUDGMENT: September 30, 20262 MIN READSOURCE JUDGMENT
Pending appeal does not suspend the duty to align wheeling agreements with tariff orders.. M/S.MULLAI SOLAR GREEN ENERGY PVT. LTD., vs TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Madras High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner sought revision of page 6 of its Energy Wheeling Agreement dated 30 March 2026, concerning SPG No. 029534170012, to align it with paragraph 5.5.8 of the Tamil Nadu Electricity Regulatory Commission’s Solar Tariff Order No. 9 of 2020.

Source reference: pp. 1–2

It also sought payment for unutilised surplus solar energy from 19 November 2025 at 75% of the competitively discovered tariff, stated to be ₹3.04 per unit.

Source reference: pp. 1–2

Both sides submitted that the issue was covered by earlier writ orders directing amendment of similar agreements in line with paragraph 5.5.8.

Source reference: pp. 3–6

The respondents stated that an appeal against the Commission’s order was pending before APTEL.

Source reference: p. 7
02

Issues

1. Whether respondents 2 to 4 should revise the petitioner’s Energy Wheeling Agreement to incorporate paragraph 5.5.8 of Solar Tariff Order No. 9 of 2020.

Source reference: pp. 2, 7

2. Whether payment due for the petitioner’s unutilised surplus solar energy should be made following that revision, notwithstanding the pending APTEL appeal.

Source reference: pp. 2, 7
03

Law Applied

Article 226 of the Constitution empowers the High Court to issue directions to public authorities.

Source reference: no citation

Paragraph 5.5.8 of TNERC Solar Tariff Order No. 9 of 2020, read with the Commission’s order in M.P. No. 47 of 2021 dated 11 May 2023, supports payment for eligible energy supplied over and above the sanctioned limit at 75% of the Commission-fixed tariff or, where no tariff is fixed, 75% of the tariff discovered through competitive bidding; the Commission had also held that the inconsistent agreement clause could not govern such payment.

Source reference: pp. 4–5

The Court followed its earlier decisions in W.P. Nos. 31457 of 2025 and 49777 of 2025, which applied that principle to require amendment of similar agreements.

Source reference: pp. 3, 6
04

Reasoning

The Court accepted the parties’ submission that the petitioner’s claim was covered by the earlier writ decisions, which had required the relevant agreements to be brought into conformity with paragraph 5.5.8.

Source reference: pp. 3, 6–7

Although the respondents pointed to a pending APTEL appeal, the Court held that compliance with its directions need not await that appeal.

Source reference: pp. 3, 6–7

It preserved the authorities’ ability to act in accordance with law after APTEL decides the matter.

Source reference: pp. 3, 6–7
05

Holding

The Court disposed of the writ petition and directed respondents 2 to 4 to revise the relevant agreement clause by incorporating paragraph 5.5.8 within six weeks from uploading of the web copy.

Any amount found payable to the petitioner is to be settled within eight weeks thereafter.

Source reference: pp. 7–8

Compliance need not await the APTEL decision, but the authorities may proceed in accordance with law once that decision is delivered.

Source reference: pp. 7–8

No costs were awarded.

Source reference: pp. 7–8
Madras High Court

Original Court PDF

M/S.MULLAI SOLAR GREEN ENERGY PVT. LTD.,vsTAMIL NADU ELECTRICITY REGULATORY COMMISSION

Madras High Court · September 30, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment