Gujarat High Court

Pending review petition constitutes sufficient cause under Section 5 of the Limitation Act for condoning appeal delay.

PRINCIPAL AND SECRETARY, S.V.R. COLLEGE OF ENGINEERING AND TECHNOLOGY vs BALMUKUND D BHATT

Gujarat High CourtJUDGMENT: July 16, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The present applicant (original respondent No. 3) sought to recall a court order dated 11.06.2026, which had condoned a four-day delay in filing a Letters Patent Appeal (LPA).

Source reference: para. 1

The applicant contended that the actual delay was nearly 10 years.

Source reference: para. 2

The procedural history shows that the appellant’s Special Civil Application was rejected on 29.04.2016. The appellant filed a review petition in 2019 (after a 1166-day delay), which was condoned by a Single Judge on 17.06.2025. The review was ultimately dismissed on merits on 09.09.2025, leading to the filing of the LPA on 12.11.2025.

Source reference: para. 3

The applicant argued that the period spent pursuing the review petition should not be considered "sufficient cause" for condoning the delay in the appeal.

Source reference: para. 4
02

Issues

1. Whether the period spent bona fide prosecuting a review petition before a competent Single Judge constitutes "sufficient cause" under Section 5 of the Limitation Act for condoning delay in filing a subsequent appeal.

Source reference: para. 7-9

2. Whether the principles of Section 14 of the Limitation Act apply to a situation where the initial forum (the Single Judge in review) possessed the requisite jurisdiction.

Source reference: para. 10-12
03

Law Applied

Section 5 of the Limitation Act, 1963, regarding the extension of the prescribed period of limitation upon showing "sufficient cause".

Source reference: para. 5, 14

Section 14 of the Limitation Act, which allows for the exclusion of time taken in proceedings bona fide in a court without jurisdiction.

Source reference: para. 11

Deena (Dead) Through LRs. v. Bharat Singh (Dead) [(2002) 6 SCC 336] and Consolidated Engineering Enterprises v. Principal Secretary, Irrigation Department [(2008) 7 SCC 169], regarding the application of Section 14 principles to Section 5.

Source reference: para. 5
04

Reasoning

The court rejected the applicant's contention that the limitation should be computed strictly from the 2016 dismissal.

Source reference: para. 6

It reasoned that a litigant cannot simultaneously pursue an appeal and a review as they are parallel remedies, and filing a review is a valid legal option.

Source reference: para. 8-9

The court held that because the Single Judge chose to entertain the review and kept it pending for nearly nine years, this duration must "inure to the benefit of the appellant" regarding the delay in filing the appeal.

Source reference: para. 9

Regarding Section 14, the court clarified it was inapplicable because the Single Judge did have jurisdiction to hear the review.

Source reference: para. 12

Under Section 5, the court found "sufficient cause" existed because the appellant only became entitled to challenge the original order in the LPA once the review petition was finally dismissed.

Source reference: para. 15
05

Holding

The court answered that the pendency of the review petition constituted sufficient cause for the delay in filing the appeal.

The court held that there was no error in its previous order dated 11.06.2026 and refused to recall it. The application for recall was dismissed.

Source reference: para. 16
Gujarat High Court

Original Court PDF

PRINCIPAL AND SECRETARY, S.V.R. COLLEGE OF ENGINEERING AND TECHNOLOGYvsBALMUKUND D BHATT

Gujarat High Court · July 16, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment