Facts
The Appellant, a partner of the Corporate Debtor (an LLP), challenged the Adjudicating Authority’s order dated 08.05.2025, which admitted the partnership firm into the Corporate Insolvency Resolution Process (CIRP).
Source reference: para. 2, 7During the pendency of the appeal, a settlement was reached between the parties on 21.08.2025.
Source reference: para. 3On 13.10.2025, the Tribunal passed an order setting aside the admission order and remanding the matter to the Adjudicating Authority to consider the settlement.
Source reference: para. 3the Financial Creditor (Respondent) moved the present application (I.A. No. 869 of 2026) seeking clarification, arguing that the phrase "the Appeal is allowed" in paragraph 7 of the previous order was legally inconsistent with the procedure required for post-admission settlements.
Source reference: para. 1, 4Issues
1. Whether the phrase "the Appeal is allowed" in the Tribunal’s earlier order was legally appropriate given that CIRP had already commenced.
Source reference: para. 4, 62. Whether the settlement and withdrawal of CIRP must strictly follow the statutory route prescribed under the Insolvency and Bankruptcy Code (IBC).
Source reference: para. 6Law Applied
Section 12A of the Insolvency and Bankruptcy Code, 2016, which governs the withdrawal of an application admitted under Sections 7, 9, or 10.
Source reference: para. 3, 6Glas Trust Company LLC v. Byju Raveendran & Others [(2025) 3 SCC 625], which establishes that once CIRP has commenced, any settlement or withdrawal must comply with the prescribed legal route to protect the interests of all claimants, rather than being summarily decided by the Appellate Tribunal.
Source reference: para. 3, 6Reasoning
The Tribunal noted that once a Corporate Debtor is admitted into CIRP, the IRP may have received multiple claims that cannot be ignored through a private settlement between the primary parties.
Source reference: para. 3Referring to the Glas Trust precedent, the Tribunal acknowledged it does not have the authority to simply "allow" an appeal and terminate CIRP based on a settlement concession; instead, the parties must move the Adjudicating Authority through the Section 12A route.
Source reference: para. 6The Tribunal admitted that the use of the phrase "the Appeal is allowed" in the order dated 13.10.2025 was an "inadvertent error" that did not align with the law or the facts of the case, as the matter was meant to be relegated to a pre-admission stage for settlement processing.
Source reference: para. 6Holding
The Tribunal allowed the application for clarification and corrected paragraph 7 of the order dated 13.10.2025.
It held that the appeal is "closed" (not "allowed") and the Adjudicating Authority’s order dated 08.05.2025 is set aside.
Source reference: para. 7The matter is remanded to the Adjudicating Authority to allow the parties to move a plea for settlement as per law.
Source reference: para. 7The Tribunal further ordered that if the settlement process fails, the Appellant is entitled to revive the appeal.
Source reference: para. 7No costs were awarded.
Source reference: para. 7Original Court PDF
Mehul Harish GosarvsAthena Constructions Limited & Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in