Facts
The Petitioner challenged the Technical Evaluation Result dated 20.02.2026 and the Financial Bid Result dated 12.03.2026 issued by the Ministry of Road Transport & Highways (MoRTH) regarding a tender for the construction of NH-913 in Arunachal Pradesh
Source reference: para. 1-2The Petitioner's bid was declared "Non-Responsive" for failing to meet eligibility requirements under Clause 2.2.2.2(i) (Threshold Technical Capacity) and Clause 2.2.2.2(ii) (Similar Work/Hill Road Criteria) of the Request for Proposal (RFP)
Source reference: para. 3Specifically, for a sub-contracted project (Project 'a'), the Petitioner claimed an executed value of ₹806.88 crore, whereas the approved value by the primary authority (MSRDC) was ₹303.14 crore
Source reference: para. 10, 20Additionally, the Petitioner failed to demonstrate 5 km of Hill Slope Protection (HSP) work in its original bid, attempting to substitute a "corrected" certificate post-bid that increased the recorded retaining wall length from 0.87 km to 8.70 km
Source reference: para. 17-19Issues
1. Whether the decision of the Respondent to declare the Petitioner’s bid as "Non-Responsive" based on failure to meet technical capacity and similar work criteria was arbitrary or legally flawed
Source reference: para. 36-372. Whether a bidder can rely on post-bid documents or "clarificatory" certificates that materially contradict the original bid documents to cure eligibility deficiencies
Source reference: para. 19, 51Law Applied
The court applied RFP Clauses 2.2.2.2(i) and (ii) governing technical capacity and similar work requirements, noting that sub-contract values are restricted to the "allowable sub-contracting limit" approved by the Government Authority
Source reference: para. 43-44It relied on the principle from Tata Cellular v. Union of India (1994) that judicial review of tenders is limited to the decision-making process rather than the merits of the decision itself
Source reference: para. 31, 55Precedents like Tata Motors Ltd. v. Brihan Mumbai Electric Supply & Transport Undertaking (2023) and N.G. Projects Ltd. v. Vinod Kumar Jain (2022) were applied to emphasize judicial restraint in tender matters to avoid public exchequer costs
Source reference: para. 31, 57The court also upheld the principle that the tender-issuing authority is the best judge of its requirements as per Haffkine Bio-Pharmaceutical Corporation Ltd v. Nirlac Chemicals (2018)
Source reference: para. 31, 57Reasoning
The Court found that the Petitioner failed the Threshold Technical Capacity under Clause 2.2.2.2(i) because its approved sub-contract value (₹303.14 crore) was significantly below the required ₹790.91 crore
Source reference: para. 44The Petitioner's reliance on subsequent, unapproved work orders to inflate the value was rejected because Clause 2.2.2.5(iv) mandates official authority approval for sub-contracts
Source reference: para. 44Regarding the "Similar Work" criteria under Clause 2.2.2.2(ii), the Court noted that the Petitioner’s original bid for Project 'a' only showed 0.87 km of HSP work, far below the mandatory 5 km
Source reference: para. 50The Court held that the "altered certificate" submitted during the representation stage—which showed an inexplicable tenfold increase in length—was inadmissible as post-bid documents cannot cure fundamental eligibility deficiencies
Source reference: para. 51-52The Court further determined that while Project 'c' met the HSP length, its financial value was below the minimum threshold, thus failing the conjunctive requirements of the RFP
Source reference: para. 53Holding
The Court dismissed the writ petition, holding that the Respondent's decision to declare the Petitioner non-responsive was justified and consistent with tender conditions
It ruled that the Petitioner failed to meet both the financial threshold for sub-contracted works and the specific technical requirement for 5 km of Hill Slope Protection
Source reference: para. 45, 50The Court reaffirmed that it would not substitute its judgment for that of the Technical Evaluation Committee (TEC) and all pending applications were dismissed
Source reference: para. 55, 58Original Court PDF
M/S Hazoor Multi Projects LimitedvsUnion Of India & Anr.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in