Facts
PRG Shipping held leases of spaces at the Nagapattinam Passenger Terminal.
Source reference: p. 3–5The lease term had been extended, with the Board’s approval dated 15 December 2025 indicating an end date of 23 December 2027. Before that date, the Board issued termination letters under clause 18 of the agreements and e-tender notices for the spaces.
Source reference: p. 3–5PRG Shipping sought interim injunctions under Section 9 of the Arbitration and Conciliation Act, 1996, pending arbitration.
Source reference: p. 3–5The Board argued that the leases had been granted through negotiations rather than the tender process and that open tendering could secure higher rent; it also submitted that the agreements allowed termination without cause.
Source reference: p. 3–5Issues
1. Whether interim injunctions should restrain the Board from acting on the termination letters and e-tender notices pending arbitration.
Source reference: p. 2–52. Whether the Board’s stated intention to obtain higher rent through open tender justified terminating the leases before their stated expiry.
Source reference: p. 5–6Law Applied
Section 9 of the Arbitration and Conciliation Act, 1996 empowers the court to grant interim measures in aid of arbitration.
Source reference: no citationThe court considered clause 18 of the lease agreements, which the Board relied on as permitting termination without cause.
Source reference: p. 5The judgment cited no precedents and stated no broader legal test for interim relief.
Source reference: no citationIt treated the potential burden on public-exchequer funds, arising from a possible damages award for premature termination, as relevant to whether the injunction should be granted.
Source reference: pp. 5–6Reasoning
The court noted that the grants of lease were not disputed and that the Board had consciously let the spaces to PRG Shipping for a defined period.
Source reference: pp. 5–6It considered the stated aim of obtaining better rent through open tender insufficient, on a prima facie basis, to justify shortening the agreed lease term—particularly as the tender policy was available when the leases were granted.
Source reference: pp. 5–6The court also considered that premature termination might expose the Board, a statutory authority, to a damages claim payable from public funds.
Source reference: pp. 5–6On that basis, it granted the injunction, while clarifying that its observations were only for the applications and would not bind the arbitral proceedings.
Source reference: pp. 5–6Holding
The court allowed both applications and made the injunctions against the termination letters and e-tender notices absolute, with no order as to costs.
The protection would automatically stand vacated if PRG Shipping failed to initiate arbitral proceedings within 12 weeks from 16 October 2026.
Source reference: p. 6Acts & Sections Cited
1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19961
Original Court PDF
The PRG Shipping Private Limited represented by itvsTamil Nadu Maritime board, represented by its Vice
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in