Facts
The appellant (contractor) was appointed by the Food Corporation of India (FCI) to transport food grains from Dharmanagar to Agartala for two years
Source reference: para 3.1The contractor filed a suit claiming detention charges at ₹800/day for trucks delayed at FCI depots due to inadequate storage space
Source reference: para 3.2FCI contested the claim and filed a counterclaim for railway demurrage charges, alleging the contractor failed to supply sufficient trucks to clear wagons
Source reference: para 5.1, 5.2The Trial Court partly decreed the contractor’s suit, awarding ₹600/day for delays exceeding a 6-day "cut-off" period, but dismissed FCI’s counterclaim for demurrage
Source reference: para 7.1, 9.7Both parties appealed the judgment
Source reference: para 2Issues
1. Whether the detention of trucks at the FCI depot beyond the road movement permit period constituted an "extraordinary kind" of delay entitling the contractor to compensation
Source reference: para 9.7, 9.82. Whether the Trial Court was justified in fixing a 6-day cut-off period for determining "extraordinary detention" when the road movement permits were valid for only 3 days
Source reference: para 7.6, 9.83. Whether FCI is legally entitled to recover railway demurrage charges from a road transport contractor in the absence of a specific contractual clause
Source reference: para 6.1, 9.11Law Applied
The court primarily applied the terms of the Tender Agreement, specifically Clause XVIII(a)(vi), which stipulates that no compensation is admissible for detention of trucks unless the detention is of an "extraordinary kind"
Source reference: para 4.1, 9.7It further relied on the precedent set by the Hon’ble Supreme Court in Food Corporation of India & Ors. v. Abhijit Paul (2023) 15 SCC 40, which established that in road transport contracts lacking specific recovery clauses, the Corporation cannot recover railway demurrage charges from contractors as "charges" or "expenses"
Source reference: para 7.9, 9.11Reasoning
The High Court found that FCI admitted to a shortage of storage capacity via Exhibit 22, yet continued to issue road movement permits with 3-day validity
Source reference: para 9.6, 9.8The Court reasoned that since FCI knew it lacked unloading space, detaining trucks beyond the 3-day permit period was entirely attributable to the Corporation and thus qualified as "extraordinary" under Clause XVIII(a)(vi)
Source reference: para 9.8The High Court critiqued the Trial Court’s arbitrary 6-day cut-off, holding that any delay beyond the initial 3 days should be compensable
Source reference: para 9.8Regarding FCI’s counterclaim, the Court noted that the witness (DW-1) admitted the agreement lacked a demurrage clause and that the High Court had previously held in WA No. 25 of 2016 that such charges cannot be claimed without contractual provision
Source reference: para 9.11, 9.12Finally, the Court observed that the Trial Court had ignored several material exhibits (Exhibits 29, 43, 47, etc.) which documented specific claims for detention, necessitated a remand for proper financial reassessment
Source reference: para 9.9, 9.13Holding
The High Court dismissed FCI’s appeals (RFA 7 and 10 of 2024) and partly allowed the contractor’s appeal (RFA 4 of 2024)
It held that FCI cannot claim railway demurrage in the absence of a contractual clause
Source reference: para 9.11The Court set aside the Trial Court’s 6-day cut-off and remanded the matter to re-determine detention charges using a 3-day cut-off and to consider the previously ignored exhibits
Source reference: para 9.13The Trial Court was directed to deliver a fresh judgment within four months
Source reference: para 9.13Original Court PDF
Food Corporation of India,vsSri Suvajit Paul,
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in