Facts
The dispute involves compensation for land degradation caused by open-cast coal mining by North Eastern Coalfields (the Company) in the Ledo area, Assam.
Source reference: p. 5While some compensation was paid between 1993 and 1995 as "full and final settlement," the Ledo Sonaligaon Pathar Parichalana Samity (the Samity) continued to seek damages for ongoing pollution
Source reference: p. 5Following a series of litigations, the Gauhati High Court in 2008 directed a fresh assessment.
Source reference: p. 6The Additional District Magistrate (ADM) subsequently assessed compensation at ₹2,98,31,308/- for the period 1989–2006
Source reference: p. 6This assessment was set aside by the High Court in 2014, with a direction for a joint field verification and fresh determination
Source reference: p. 6In 2015, a joint verification revealed that a fresh assessment for 1989–2006 was no longer feasible as mining had ceased in 2006
Source reference: p. 6-7Consequently, a meeting on 05.06.2015 resolved to revive the previously assessed amount of ₹2,98,31,308/-
Source reference: p. 7The Company challenged this resolution, while the Samity sought its enforcement
Source reference: p. 7-8Issues
1. Whether the Samity’s claim is barred by the principles of estoppel and waiver due to the 1993–1995 settlements?
Source reference: p. 7, 212. Whether the claim is barred by res judicata in light of previous PIL and human rights proceedings?
Source reference: p. 8, 213. Whether the Samity has the locus standi to maintain the writ petition as an unregistered body?
Source reference: p. 10, 204. Whether the resolution to pay ₹2,98,31,308/- is legally sustainable when the underlying assessment was previously set aside and a fresh assessment was found impossible?
Source reference: p. 10, 22Law Applied
The court emphasized that the damage caused by mining pollution is a "continuing damage," and prior payments do not absolve a company of liability for ongoing degradation
Source reference: p. 15It applied the principle that substantial justice must prevail over technical considerations, such as the registration status of a representative body
Source reference: p. 20-21Regarding res judicata, the court held the doctrine only applies when a matter is "directly and substantially in issue" and finally decided, which was not the case for the full compensation period
Source reference: p. 22The court also relied on Section 6 of the Societies Registration Act, 1860, noting that while societies must generally follow bylaws to sue, the court may overlook technicalities to prevent the deprivation of rights
Source reference: p. 18-20Reasoning
The court found that the Company's defense of "full and final settlement" from 1995 failed because pollution-induced land degradation is a continuous tort, making the number of affected ryots dynamic rather than static
Source reference: p. 15, 21On the issue of locus standi, the court ruled that since the Samity's members were undisputedly affected, technical hurdles regarding the Samity's legal status should not bar substantial justice
Source reference: p. 20-21Regarding the 2015 resolution, the court acknowledged a legal impasse: a fresh assessment was mandated by the Division Bench but was factually impossible due to the efflux of time (nearly 10 years since mining stopped)
Source reference: p. 16, 22While the 2015 resolution to revive a "set-aside" assessment was technically flawed, the underlying entitlement to compensation remained valid
Source reference: p. 22To resolve this, the court exercised its equitable jurisdiction to bypass the impossible task of precise quantification
Source reference: p. 22-23Holding
The court dismissed the Company’s challenge and partially allowed the Samity’s petition
It held that while the members were entitled to compensation, the original figure of ₹2.98 Crores could not be sustained due to the lack of fresh verification
Source reference: p. 22To balance the equities, the court awarded a lump sum compensation of ₹1,50,00,000/- (Rupees one crore fifty lakh)
Source reference: p. 23The Petitioner-Company (North Eastern Coalfields) was directed to pay this amount to the affected persons/Samity members within 60 days of the judgment
Source reference: p. 23Original Court PDF
Ledo Sonaligaon Pathar Parichalana SamityvsThe Union Of India And 5 Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in