Gauhati High Court
Administrative and Public LawContract Law

Private payment-entitlement disputes must be resolved through civil proceedings or arbitration, not Article 226.

M/S Dra Ktee (Jv) vs The State Of Assam And Othrs

Gauhati High CourtJUDGMENT: September 28, 20262 MIN READSOURCE JUDGMENT
Private payment-entitlement disputes must be resolved through civil proceedings or arbitration, not Article 226.. M/S Dra Ktee (Jv) vs The State Of Assam And Othrs. Gauhati High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner was awarded a PWD contract for construction of the North Lakhimpur By-pass and entered into a Memorandum of Understanding (MoU) with respondent No. 6, Khushi Constructions, on 11 January 2021 to undertake the work.

Source reference: pp. 3–4, paras. 3–4

The MoU provided that project payments would be made into a specified joint project account.

Source reference: pp. 3–4, para. 7

After completion of the work, the petitioner and respondent No. 6 disputed entitlement to the proceeds.

Source reference: p. 4, paras. 5–6

The Chief Engineer issued an order dated 31 December 2025 concerning payment to respondent No. 6, which the petitioner challenged in this writ petition; the Court noted that this was the second round of litigation.

Source reference: p. 4, paras. 5–6
02

Issues

Whether the dispute between the petitioner and respondent No. 6 over entitlement to the contract proceeds could be adjudicated in proceedings under Article 226.

Source reference: p. 4, para. 6

Whether the payable amount should be disbursed in accordance with the MoU into the parties’ joint project account.

Source reference: pp. 4–5, paras. 7–8
03

Law Applied

A private dispute between contracting parties over their respective entitlement to payments is to be resolved before a competent civil court or, where an arbitration clause exists, through arbitration; the public-law remedy under Article 226 is not the forum for adjudicating that dispute.

Source reference: p. 4, para. 6

The MoU, which stipulated that payments received in respect of the contract were to be deposited only into the specified joint project account.

Source reference: p. 4, para. 7
04

Reasoning

The petitioner and respondent No. 6 disputed who was entitled to the completed-work proceeds, including whether payment to respondent No. 6 had been agreed.

Source reference: p. 4, para. 6

The Court considered that question to be a dispute between the parties, not one for determination through the writ petition, and left its resolution to civil proceedings or arbitration if available.

Source reference: p. 4, para. 6

However, because neither party disputed the MoU’s requirement that contract payments be deposited into the joint project account, the Court directed the Chief Engineer to pay the amount into that account.

Source reference: pp. 4–5, paras. 7–8
05

Holding

The writ petition was disposed of.

The Chief Engineer, PWD (NH Works), was directed to disburse the entire amount payable into the joint project account within four months after service of a certified copy of the judgment.

Source reference: pp. 5–6, para. 8

The petitioner and respondent No. 6 were left to resolve their dispute amicably or, failing that, before a competent civil court or through arbitration if an arbitration clause exists.

Source reference: pp. 5–6, para. 8

The earlier interim order was vacated.

Source reference: pp. 5–6, para. 8
Gauhati High Court

Original Court PDF

M/S Dra Ktee (Jv)vsThe State Of Assam And Othrs

Gauhati High Court · September 28, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment