Facts
The petitioner was awarded a PWD contract for construction of the North Lakhimpur By-pass and entered into a Memorandum of Understanding (MoU) with respondent No. 6, Khushi Constructions, on 11 January 2021 to undertake the work.
Source reference: pp. 3–4, paras. 3–4The MoU provided that project payments would be made into a specified joint project account.
Source reference: pp. 3–4, para. 7After completion of the work, the petitioner and respondent No. 6 disputed entitlement to the proceeds.
Source reference: p. 4, paras. 5–6The Chief Engineer issued an order dated 31 December 2025 concerning payment to respondent No. 6, which the petitioner challenged in this writ petition; the Court noted that this was the second round of litigation.
Source reference: p. 4, paras. 5–6Issues
Whether the dispute between the petitioner and respondent No. 6 over entitlement to the contract proceeds could be adjudicated in proceedings under Article 226.
Source reference: p. 4, para. 6Whether the payable amount should be disbursed in accordance with the MoU into the parties’ joint project account.
Source reference: pp. 4–5, paras. 7–8Law Applied
A private dispute between contracting parties over their respective entitlement to payments is to be resolved before a competent civil court or, where an arbitration clause exists, through arbitration; the public-law remedy under Article 226 is not the forum for adjudicating that dispute.
Source reference: p. 4, para. 6The MoU, which stipulated that payments received in respect of the contract were to be deposited only into the specified joint project account.
Source reference: p. 4, para. 7Reasoning
The petitioner and respondent No. 6 disputed who was entitled to the completed-work proceeds, including whether payment to respondent No. 6 had been agreed.
Source reference: p. 4, para. 6The Court considered that question to be a dispute between the parties, not one for determination through the writ petition, and left its resolution to civil proceedings or arbitration if available.
Source reference: p. 4, para. 6However, because neither party disputed the MoU’s requirement that contract payments be deposited into the joint project account, the Court directed the Chief Engineer to pay the amount into that account.
Source reference: pp. 4–5, paras. 7–8Holding
The writ petition was disposed of.
The Chief Engineer, PWD (NH Works), was directed to disburse the entire amount payable into the joint project account within four months after service of a certified copy of the judgment.
Source reference: pp. 5–6, para. 8The petitioner and respondent No. 6 were left to resolve their dispute amicably or, failing that, before a competent civil court or through arbitration if an arbitration clause exists.
Source reference: pp. 5–6, para. 8The earlier interim order was vacated.
Source reference: pp. 5–6, para. 8Original Court PDF
M/S Dra Ktee (Jv)vsThe State Of Assam And Othrs
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
