Rajasthan High CourtAdministrative and Public LawConstitutional Law

Promissory estoppel bars retrospective withdrawal of duty exemptions for projects commissioned under specific policy assurances.

SAI TIRUPATI UNIVERSITYv.THE DISCOM THROUGH ITS CHAIRMAN

Promissory estoppel bars retrospective withdrawal of duty exemptions for projects commissioned under specific policy assurances.. SAI TIRUPATI UNIVERSITY vs THE DISCOM THROUGH ITS CHAIRMAN. Rajasthan High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the policy assurances made by the State in the Solar Policy, 2019 regarding electricity duty exemptions are enforceable under the doctrines of promissory estoppel and legitimate expectation?

The court held

The High Court disposed of the petitions, holding that the impugned amendment dated 10.05.2022 cannot operate retrospectively and is only prospective in nature

It also directed

The Court held that petitioners whose solar projects were commissioned prior to the amendment (10.05.2022) are entitled to the promised seven-year electricity duty exemption from their respective COD

The Court directed the competent authorities to verify the exact COD of each project and pass independent orders granting the exemption for the limited seven-year period

Relief was similarly extended to individual members of petitioner associations and rooftop solar owners, subject to verification of their commissioning dates

01Facts

The State of Rajasthan notified the Solar Policy, 2019, which explicitly assured an exemption from the payment of electricity duty for a period of seven years from the Commercial Operation Date (COD) for captive solar power plants

¶ 2, 5.14

Relying on this sovereign representation, Petitioner No. 1 (UltraTech) altered its position by investing approximately ₹89 crores to establish captive solar power generation facilities in Rajasthan

¶ 5.17, 9

On 10.05.2022, the State issued an amendment to Clause 16.4 of the Policy, effectively withdrawing the blanket seven-year exemption and making such benefits subject to separate government notifications issued under the Rajasthan Electricity (Duty) Act, 1962

¶ 5.18, 9.3

Consequently, the respondents began raising electricity duty bills on the petitioners' plants

¶ 5.19

The petitioners challenged the amendment, seeking the enforcement of the original exemption on the grounds of promissory estoppel and legitimate expectation

¶ 4

02Issues

i.1. Whether the policy assurances made by the State in the Solar Policy, 2019 regarding electricity duty exemptions are enforceable under the doctrines of promissory estoppel and legitimate expectation?

¶ 1

ii.2. Whether the State can retrospectively withdraw fiscal incentives to the detriment of investors who have already commissioned projects based on those incentives?

¶ 20

03Law Applied

The court primarily applied Section 3(3) of the Rajasthan Electricity (Duty) Act, 1962, which grants the State the power to exempt consumers from electricity duty in the public interest

¶ 9.1

It relied on the equitable doctrine of Promissory Estoppel derived from Motilal Padampat Sugar Mills v. State of U.P., which holds the State accountable to promises that induce a party to act to their detriment

¶ 14

The court further applied the principle of Legitimate Expectation and the test of Non-arbitrariness under Article 14 of the Constitution, as discussed in State of Jharkhand v. Brahmputra Metallics Ltd. and State of Punjab v. Nestle India Ltd., asserting that executive policy changes must be fair and supported by overriding public interest if they negate prior assurances

¶ 7, 14.1

Provisions in the judgment · 3 · Linked ones open on LawLens

Electricity Act, 2003 Section 3Section 7Section 9

04Reasoning

The State argued that the Solar Policy was a non-statutory executive guideline and that exemptions could only be granted via formal notification under the 1962 Act

¶ 8(A)-(B)

The Court rejected this, reasoning that the State cannot rely on its own failure to issue a statutory notification to defeat a concrete promise made in a formal policy intended to attract investment

¶ 15

The petitioners fulfilled all ingredients of promissory estoppel: a clear representation, intent to induce action, and substantial capital expenditure

¶ 13, 16

Regarding the State's claim of "public interest" based on financial constraints, the Court found this to be a "bald assertion" unsupported by evidence, especially given that the State's solar capacity targets had not yet been reached

¶ 17

The Court held that while the State has the flexibility to change economic policy, it cannot do so retrospectively to divest "accrued or vested rights"

¶ 19

Such an abrupt withdrawal without a transitional mechanism was deemed "manifestly arbitrary"

¶ 19

05Holding

The High Court disposed of the petitions, holding that the impugned amendment dated 10.05.2022 cannot operate retrospectively and is only prospective in nature

¶ 20

The Court held that petitioners whose solar projects were commissioned prior to the amendment (10.05.2022) are entitled to the promised seven-year electricity duty exemption from their respective COD

¶ 20, 21

The Court directed the competent authorities to verify the exact COD of each project and pass independent orders granting the exemption for the limited seven-year period

¶ 21, 29, 34

Relief was similarly extended to individual members of petitioner associations and rooftop solar owners, subject to verification of their commissioning dates

¶ 29, 34
Rajasthan High Court

Original Court PDF

SAI TIRUPATI UNIVERSITYvsTHE DISCOM THROUGH ITS CHAIRMAN

Rajasthan High Court · April 06, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment