APTEL

Quasi-Judicial Authorities Must Disclose Evidence and Maintain Procedural Fairness During Prudence Checks

TATA POWER DELHI DISTRIBUTION LIMITED vs DELHI ELECTRICITY REGULATORY COMMISSION

APTELJUDGMENT: May 20, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant, a distribution licensee in Delhi, challenged the Tariff Order dated 28.03.2018 passed by the Delhi Electricity Regulatory Commission (DERC/Respondent). The impugned order trued up the Aggregate Revenue Requirement (ARR) for FY 2016-17 and approved the ARR/Tariff for FY 2018-19

Source reference: p. 2-3

While 26 issues were originally raised, several were disposed of by previous orders or withdrawn.

Source reference: p. 5-6

The Tribunal ultimately adjudicated two surviving issues: (i) the disallowance of ₹17.43 Crores as expenses towards "Other Business Income" based on an undisclosed audit report [para. 11], and (ii) the disallowance of ₹1.60 Crores in water charges paid to the Delhi Jal Board under an amnesty scheme

Source reference: para. 29
02

Issues

1. Whether the State Commission’s disallowance of expenses towards Other Business, predicated on an undisclosed internal auditor's report and without affording an opportunity for rebuttal, violated principles of natural justice and transparency under Section 86(3) of the Electricity Act, 2003.

Source reference: para. 15-22

2. Whether the Appellant is entitled to a one-time pass-through of water charges paid for the pre-privatization (DVB) period under a statutory amnesty scheme, notwithstanding the normative nature of O expenses under the MYT Regulations, 2011.

Source reference: para. 31-36
03

Law Applied

Section 86(3) of the Electricity Act, 2003, which mandates transparency in the Commission's functions.

Source reference: para. 11

The court relied on Kothari Filaments v. Commr. of Customs and T. Takano v. SEBI, establishing that quasi-judicial authorities cannot base decisions on material not disclosed to the affected party.

Source reference: para. 11, 21-22

DERC (MYT) Regulations, 2011, which classify O as a "controllable parameter" determined normatively.

Source reference: para. 37

Rule 8(3) of the Delhi Electricity Reform (Transfer Scheme) Rules, 2001, which permits liabilities from events prior to the transfer date to be included in the Discom’s revenue requirement (up to ₹1 Crore per annum) if approved by the Commission.

Source reference: para. 31, 41
04

Reasoning

Regarding Issue 1, the Tribunal found that DERC's reliance on an internal auditor's finding—which alleged that the "Other Business" expenses were already covered under normative O—was legally flawed because the audit report was never shared with the Appellant.

Source reference: para. 19-20

This prevented the Appellant from contesting the data or explaining why these were distinct, incremental costs.

Source reference: para. 22

Regarding Issue 2, the Tribunal acknowledged the Respondent’s argument that O is generally normative and not trued-up [para. 36]; however, it noted that these specific water charges pertained to the DVB period (prior to 2002) and thus could not have been factored into the "Base Year" audited accounts used for current normative calculations.

Source reference: para. 39

The Tribunal reasoned that since the Appellant mitigated consumer burden by settling only the principal amount under an amnesty scheme, and because the Transfer Scheme Rules specifically provide for handling historical liabilities, a rigid application of normative limits would be unjust.

Source reference: para. 40-41
05

Holding

The Tribunal set aside the Impugned Order on both issues and remanded the matter to the DERC.

On Issue 1: DERC is directed to provide the audit report/findings to the Appellant and afford them a reasonable opportunity to explain the "Other Business" expenses before passing a reasoned order [para. 28]. On Issue 2: DERC is directed to conduct a prudence check on the water charges paid under the amnesty scheme, considering Rule 8(3) of the Transfer Scheme Rules [para. 42]. DERC must also examine the claim for carrying cost and pass orders within three months.

Source reference: p. 26
APTEL

Original Court PDF

TATA POWER DELHI DISTRIBUTION LIMITEDvsDELHI ELECTRICITY REGULATORY COMMISSION

APTEL · May 20, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment