Facts
The appellant-contractor (Suvajit Paul) was appointed by the Food Corporation of India (FCI) for two years (01.05.2012 to 30.04.2014) to transport food grains from Dharmanagar to Agartala
Source reference: para 3.1The contractor filed a suit for ₹1,52,52,800/- plus interest, claiming detention charges for trucks stranded at FCI godowns for 4 to 20 days beyond the 3-day road movement permit period due to FCI's inadequate storage space
Source reference: para 3.2FCI contested the suit and filed a counterclaim for railway demurrage charges, alleging the contractor failed to supply sufficient trucks, causing delays in clearing railway wagons
Source reference: para 4.3, 5.1The Commercial Court partly decreed the contractor's suit for ₹4,42,800/- at 9% interest, applying a 6-day cut-off (3 permit days + 3 grace days) to define "extraordinary detention," and dismissed FCI’s counterclaim
Source reference: para 7.1, 9.7Both parties appealed the judgment
Source reference: para 1Issues
1. Whether the contractor was entitled to detention charges for vehicles stranded at the destination point due to FCI’s lack of storage space.
Source reference: para 9.72. Whether the detention of trucks beyond the stipulated 3-day permit period constituted an "extraordinary kind" of detention under Clause-XVIII(a)(vi) of the tender agreement.
Source reference: para 9.73. Whether the Trial Court was justified in fixing a 6-day cut-off period for the commencement of detention charges.
Source reference: para 9.84. Whether FCI was entitled to recover railway demurrage charges from the contractor in the absence of a specific contractual provision.
Source reference: para 6.1, 9.11Law Applied
The court interpreted Clause-XVIII(a)(vi) of the tender agreement, which states that no compensation is admissible for truck detention unless it is of an "extraordinary kind"
Source reference: para 4.1, 9.7It further applied the precedent set by the Hon'ble Supreme Court in Food Corporation of India & Ors. v. Abhijit Paul (2023) 15 SCC 40, which established that "charges" in a transport contract do not include railway demurrages unless the recovery is explicitly enabled by a clause in the agreement
Source reference: para 7.9, 9.11Reasoning
The court noted that FCI, via its own correspondence (Exhibit 21), admitted to a shortage of storage capacity and the consequent stranding of hundreds of trucks
Source reference: para 9.7The court reasoned that since the 3-day road movement permit was the standard period for delivery, any delay beyond this caused by FCI’s inability to unload trucks constitutes "extraordinary detention"
Source reference: para 9.8The court found the Trial Court’s imposition of an additional 3-day grace period (totaling a 6-day cut-off) to be arbitrary and without basis
Source reference: para 9.8, 9.13Regarding the counterclaim, the court observed that the agreement lacked any clause for railway demurrage, and following Abhijit Paul, FCI could not fasten such liability on the contractor
Source reference: para 9.11, 9.12Finally, the court found that the Trial Court had ignored several material exhibits (Exhibits 27, 41-57, 59-71, 78) which were essential for the accurate assessment of the contractor’s financial losses
Source reference: para 9.9, 9.13Holding
The High Court dismissed FCI’s appeals (RFA No. 8 & 9 of 2024) and partly allowed the contractor’s appeal (RFA No. 3 of 2024)
The court set aside the Trial Court's 6-day cut-off, holding that detention charges should be calculated for any delay beyond the initial 3-day permit period
Source reference: para 9.13The matter was remanded to the District Commercial Court for the limited purpose of re-determining the compensation amount by considering the previously ignored exhibits and applying the 3-day cut-off, with a directive to deliver a fresh judgment within four months
Source reference: para 9.13Original Court PDF
Food Corporation of India,vsSri Suvajit Paul,
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in