Facts
The Appellant (Seller) and Respondent (Buyer) entered into a Master LNG Sale and Purchase Agreement (MSPA) on 02.08.2006
Source reference: p. 9On 12.03.2007, they executed a "Confirmation Notice" for four cargoes scheduled for April, May, June, and August 2007
Source reference: p. 26The Confirmation Notice left certain details (LNG ship, receiving terminal, specific price) to be finalized via a "Delivery Notice"
Source reference: p. 27-28Between March and May 2007, the Buyer informed the Seller it could not secure regasification slots at the only two available Indian terminals (Hazira/Dahej) due to third-party unavailability
Source reference: p. 33, 38The Seller unilaterally issued Delivery Notices and subsequently "Take or Pay" (TOP) invoices for the first three cargoes, later terminating the contract and claiming damages for the fourth
Source reference: p. 40An LCIA Arbitral Tribunal in London issued an award on 25.06.2009 in favor of the Seller, holding the contract was concluded and the missing details were merely "operational"
Source reference: p. 43-47The Seller sought enforcement in India under Section 48 of the Arbitration and Conciliation Act, 1996. The Single Judge of the High Court refused enforcement on 05.07.2018, citing public policy violations
Source reference: p. 2, 7Issues
1. Whether the Arbitral Tribunal’s finding that a concluded contract existed—despite the lack of agreement on price and delivery terminal—was perverse and irrational so as to violate the "fundamental policy of Indian law"
Source reference: para. 3, 382. Whether the enforcement of a foreign award can be refused under Section 48(2)(b) if the findings "shock the conscience of the court"
Source reference: para. 83, 1103. Whether the 2015 Amendment to Section 48 (which limits the "fundamental policy" review) applies retrospectively to an enforcement petition filed in 2014
Source reference: para. 111, 118Law Applied
The Court primarily applied Section 48 of the Arbitration and Conciliation Act, 1996, specifically the "public policy" defense under Section 48(2)(b)
Source reference: p. 111It relied on Renusagar Power Co. Ltd. v. General Electric Co., which defined public policy as including the "fundamental policy of Indian law," "interests of India," and "justice or morality"
Source reference: p. 57, 115It further applied Associate Builders v. DDA, identifying that a "judicial approach" and non-perversity are part of the fundamental policy
Source reference: p. 65-68The Court applied Vedanta Limited v. Government of India, confirming that while merit review is prohibited, enforcement may be refused if the award violates basic notions of justice
Source reference: p. 56, 89Regarding temporal application, it followed Vedanta to hold that the pre-2015 unamended Section 48 applies to petitions filed before October 2015
Source reference: para. 111Reasoning
The Court examined whether the Tribunal’s decision to treat the price and receiving terminal as "operational issues" rather than "essential terms" was legally sustainable. Under the MSPA Clause 2.3 and 12.1, a contract is only formed when terms are "mutually agreed" via a Confirmation Notice
Source reference: p. 15, 18The Court noted that in LNG transactions, a terminal is not just a delivery point but a necessary regasification facility; without it, the buyer cannot physically receive the goods
Source reference: para. 149The Tribunal’s finding that a contract was "concluded" while the price remained a fluctuating formula and the terminal was non-existent shocked the Court’s conscience
Source reference: para. 178The Court reasoned that the Seller’s unilateral issuance of Delivery Notices and TOP invoices, despite knowing the Buyer lacked a terminal, was an attempt to foist a new contract upon an unwilling party
Source reference: para. 151, 173While acknowledging the narrow scope of Section 48, the Court concluded that the Tribunal ignored hallowed principles of contract law—specifically that an agreement is not a contract unless essential terms are settled—making the award perverse and irrational
Source reference: para. 177-178Holding
The Court held that the amended Section 48 (2015) did not apply because the enforcement proceedings commenced in 2014
Under the unamended standard, the Court held that the award was contrary to the fundamental policy of Indian law and basic notions of justice because it held the Buyer liable for a "Take or Pay" obligation under a non-concluded contract, which "defies all logic" and "shocks the conscience of the court"
Source reference: para. 178-180The Court dismissed the appeal and upheld the Single Judge's refusal to enforce the foreign award under Section 48(2)(b)
Source reference: para. 180Original Court PDF
ASEAN LNG TRADING CO. LTD., NOW KNOWN AS PETRONAS LNG LTDvsNISHU TOURS AND TRAVELS LTD.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in