Facts
The Appellant, a developer of a 2500 MW power plant, applied for Long-Term Access (LTA) and furnished two Application Bank Guarantees (BGs) totaling ₹2.5 Crore
Source reference: p. 3Due to environmental clearances being quashed by the High Court and subsequent prohibition of projects in the Western Ghats, the Appellant was unable to sign the LTA Agreement and decided to relocate the project
Source reference: p. 6The Appellant requested a refund of the BGs, arguing frustration of contract
Source reference: p. 7Respondent No. 4 (CTUIL) rejected the refund and moved to encash the BGs as per the Connectivity Regulations, 2009
Source reference: p. 7The Appellant filed a petition before the CERC (Respondent No. 1), which was dismissed on 24.08.2015
Source reference: p. 8The CERC held that the Regulations do not provide for force majeure exceptions regarding BG encashment if an applicant fails to sign the LTA Agreement
Source reference: p. 8-11Issues
1. Whether Regulation 12(5) of the Connectivity Regulations, 2009, mandatorily requires the Nodal Agency to encash a Bank Guarantee in the event of failure to sign the LTA Agreement.
Source reference: para. 15 / p. 122. Whether the Appellant’s failure to execute the LTA Agreement due to factors beyond its control (force majeure) justifies the withholding or refund of the Application Bank Guarantee.
Source reference: para. 15-16 / p. 12-13Law Applied
The court primarily interpreted Regulation 12 of the CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009
Source reference: p. 13-16It relied on the principle of statutory interpretation regarding the words "May" and "Shall," citing the Hon’ble Supreme Court’s decision in Bachahan Devi v. Nagar Nigam, Gorakhpur, which establishes that "may" is generally directory unless the context implies a mandatory duty
Source reference: para. 25 / p. 20-22It also applied the precedent from Chettinad Power Corporation Private Ltd. v. PGCIL, which clarified that Regulation 12(5) is discretionary and serves as a regulatory measure rather than a penal one
Source reference: para. 16 / p. 12Reasoning
The Tribunal analyzed the Statement of Reasons (SOR) for the 2009 Regulations, noting that the purpose of the BG is to "bring seriousness" to applications and ensure grid security, not to serve as liquidated damages or a penalty
Source reference: para. 28-31 / p. 23-24The Tribunal determined that the word "may" in Regulation 12(5) confers discretion upon the CTUIL rather than a mandatory obligation
Source reference: para. 35 / p. 28It reasoned that an automatic encashment policy, regardless of genuine hardships or force majeure events like the quashing of environmental clearances, would lead to a "serious miscarriage of justice"
Source reference: para. 35 / p. 29The Tribunal further noted that even the CERC had previously admitted before the Delhi High Court in NSL Nagapatnam Infrastructure Pvt. Ltd. v. CERC that Regulation 12(5) was never intended to be mandatory in all cases
Source reference: para. 32 / p. 25-26Thus, CTUIL must evaluate the specific facts and circumstances of each default before deciding to encash.
Source reference: no citationHolding
The Tribunal held that Regulation 12(5) of the Connectivity Regulations, 2009, is directory/discretionary and not mandatory
The impugned order of the CERC dated 24.08.2015 was set aside
Source reference: para. 36 / p. 29The matter was remanded to the CERC to conduct a fresh hearing to determine whether CTUIL was justified in encashing the BGs based on the specific facts of the Appellant's case, including the alleged impossibility of performance
Source reference: para. 19 / p. 30The Appeal was allowed and disposed of with directions to pass a fresh order within two months
Source reference: para. 19-20 / p. 30Original Court PDF
Talegaon Industrial Parks Pvt. Ltd.vsCentral Electricity Regulatory Commission & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in