01Facts
The Appellant (UPJVNL) operates the Rihand and Matatila Hydro Power Stations. Based on historical agreements (Sachdeva Committee, 1964), the State of Madhya Pradesh (Respondent No. 2, MPPMCL) is entitled to a specific share of power at cost price plus 5% due to submergence of its land.
¶ 6-7Following jurisdictional disputes, Respondent No. 2 filed Petition No. 128/MP/2016 before the CERC seeking a direction for UPJVNL to determine O&M expenses from April 1, 2008.
¶ 18On October 12, 2017, the CERC held it had jurisdiction but declined to reopen tariffs for 2008–2014 as they had already been determined by the State Commission (UPERC); it directed UPJVNL to file for tariff determination only from 2014–15 onwards.
¶ 19-20Respondent No. 2 filed a Review Petition (1/RP/2018). In the impugned review order dated July 11, 2018, the CERC rejected the primary grounds for review but suo motu modified the original order, directing Respondent No. 2 to pay only O&M charges for the 2008–2014 period based on UPERC orders.
¶ 22-2302Issues
i.1. Whether the CERC could exercise suo motu review powers to modify its previous order in the absence of a specific prayer or application by the parties.
¶ 25 / para. 37ii.2. Whether the CERC violated the principles of natural justice (Audi Alteram Partem) by modifying the Appellant's tariff entitlement without hearing the parties on that specific issue.
¶ 38iii.3. Whether the CERC exceeded its jurisdiction by effectively modifying tariff orders previously passed by the State Commission (UPERC).
¶ 25 / para. 3903Law Applied
The court primarily applied the principles governing review jurisdiction under Section 114 and Order XLVII of the Code of Civil Procedure, 1908, which stipulate that review power must be exercised upon an application and not suo motu.
¶ 37The fundamental principle of natural justice, Audi Alteram Partem, which mandates that no party be condemned or deprived of a right without being heard.
¶ 38The principle that a Central Commission does not possess supervisory or appellate jurisdiction over the final tariff orders of a State Commission unless specifically provided by statute.
¶ 39Provisions in the judgment · 4 · Linked ones open on LawLens
Electricity Act, 2003 Section 64Section 79
Code of Civil Procedure, 1908 Section 114Section 47
04Reasoning
The Tribunal found that the CERC had made a "conscious decision" in its original order not to reopen the 2008–2014 tariff because the UPERC had already adjudicated the matter.
¶ 31In the review proceedings, Respondent No. 2 did not seek the specific relief of paying only O&M charges for that period.
¶ 37The Tribunal reasoned that review jurisdiction is not a suo motu power; since no party applied for that specific rectification, the CERC's intervention was unwarranted.
¶ 37Furthermore, the Tribunal noted that the CERC failed to hear the Appellant before curtailing its tariff entitlement, thereby violating the principles of natural justice.
¶ 38The Tribunal observed a logical inconsistency: the CERC upheld the validity of the UPERC tariff orders for 2008–2014 while simultaneously issuing a direction that modified the payment terms of those very orders, which it had no jurisdiction to do.
¶ 3905Holding
The Tribunal set aside the impugned review order dated July 11, 2018, specifically to the extent of Paragraph 12, which had modified the original order regarding the 2008–2014 payment terms.
¶ 40The Tribunal held that the CERC’s modification was perverse, lacked jurisdiction, and violated natural justice.
¶ 36-38The appeal was allowed, and the original order dated October 12, 2017, was restored to its original form regarding the 2008–2014 period.
¶ 40Original Court PDF
Uttar Pradesh Jal Vidyut Nigam LimitedvsCentral Electricity Regulatory Commission & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
