APTEL

Regulatory Commissions must determine O&M baselines using multi-factor analysis and reasoned prudence checks rather than mechanical extrapolation.

M/s Everest Power Private Limited vs Punjab State Electricity Regulatory Commission & Ors

APTELJUDGMENT: May 04, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant, Everest Power Private Limited (EPPL), operates the 100 MW Malana II Hydro Electric Project in Himachal Pradesh

Source reference: p.5

EPPL challenged two orders (dated 03.09.2019 and 09.03.2021) passed by the Punjab State Electricity Regulatory Commission (PSERC) regarding the determination of Annual Fixed Cost (AFC) for the Multi-Year Tariff (MYT) control periods from FY 2017-18 to FY 2022-23

Source reference: p.5-6

The Appellant alleged that the Commission erroneously disallowed legitimate Operation and Maintenance (OM) expenses and various capital expenditures (Add-Cap) incurred after the project's cut-off date

Source reference: p.8-9

EPPL also moved an application (IA No. 1855 of 2025) to introduce additional documents, including EPC contracts and correspondence, to justify cost escalations

Source reference: p.9
02

Issues

1. Whether the Commission erred in determining baseline OM values by failing to consider industry benchmarks and project-specific features as mandated by Regulation 8.1(b)

Source reference: p.9/14

2. Whether the disallowance of additional capital expenditure for the Project Colony and staff rest rooms was justified, given they were previously acknowledged in the Capital Investment Plan (CIP) Order

Source reference: p.9/40

3. Whether miscellaneous expenditures on office equipment and plant machinery were rightly excluded under the proviso to Regulation 18.2(e)

Source reference: p.9/52

4. Whether the disallowance of escalation costs and store construction costs lacked reasoned justification and violated Regulation 18.2(d)

Source reference: p.9/63, 72
03

Law Applied

The Tribunal applied Regulation 8.1(b) of the PSERC MYT Regulations, 2014, which mandates OM baseline determination based on audited accounts, industry benchmarks, and project-specific factors

Source reference: p.15

It relied on Section 61 of the Electricity Act, 2003, emphasizing the recovery of rightful costs for generating companies

Source reference: p.12

Regarding Add-Cap, it applied Regulation 18.2(d) for works necessary for efficient operation and Regulation 18.2(e) concerning natural calamities

Source reference: p.52, 59

The Tribunal followed BSES Rajdhani Power Ltd. v. DERC (2023) 4 SCC 788, which defines the scope of "truing up" as adjusting estimates to actuals without changing methodology

Source reference: p.48

It further followed A.N. Sehgal v. Raja Ram Sheoran regarding the interpretive limit of a "proviso"

Source reference: p.61

It further followed Omar Usman Chamadia v. Abdul regarding the necessity of reasoned, "speaking" orders

Source reference: p.65
04

Reasoning

The Tribunal found that the Commission mechanically escalated FY 2016-17 OM figures by WPI, ignoring the mandatory multi-factor analysis (audited costs and benchmarks) required by Regulation 8.1(b)

Source reference: p.30

It noted that the Commission’s comparison of the high-altitude, underground Malana II project with the surface-level Shanan project was fundamentally flawed due to geographic and technical dissimilarities

Source reference: p.33

Regarding capital expenditure, the Tribunal held that "truing up" cannot be used to introduce new caps or reverse prior approvals from the CIP stage

Source reference: p.48, 56

It ruled that the Commission incorrectly applied a proviso intended for "natural calamity" claims (18.2e) to "efficient operation" claims (18.2d), thereby wrongly excluding miscellaneous assets like computers and machinery

Source reference: p.60

Finally, the Tribunal observed that the disallowance of escalation and store construction costs was arbitrary as the Commission provided no reasons for rejecting audited evidence or contractual escalation clauses

Source reference: p.70-76
05

Holding

The Tribunal allowed both appeals and remanded the matters to the PSERC for re-determination within three months

(i) Baseline OM values must be re-determined considering actual audited accounts and industry benchmarks

Source reference: p.78

(ii) Actual audited expenditure for the Project Colony (Rs. 2.14 Cr) and Staff Rest Rooms (Rs. 1.01 Cr) must be allowed subject to prudence check

Source reference: p.79

(iii) Miscellaneous expenditure (Rs. 0.54 Cr) and Store construction (Rs. 0.61 Cr) are qualify under Regulation 18.2(d)

Source reference: p.79-80

(iv) Escalation costs (Rs. 1.12 Cr) must be re-evaluated via a speaking order. All allowed amounts are to be granted along with applicable carrying costs

Source reference: p.79, 81
APTEL

Original Court PDF

M/s Everest Power Private LimitedvsPunjab State Electricity Regulatory Commission & Ors

APTEL · May 04, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment