Delhi High Court

### Rejection of MSME Reference Does Not Extinguish Contractual Rights or Invalidate Predetermined Arbitral Procedures

Newton Engineering And Chemicals Limited vs Indian Oil Corporation Ltd.

Delhi High CourtJUDGMENT: April 16, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant (Company) and Respondent (Corporation) entered into a contract in 2011 for mechanical and piping works at the Mathura Refinery.

Source reference: p. 1-2

Upon completion, disputes arose, and the Appellant invoked arbitration under the General Conditions of Contract (GCC).

Source reference: p. 2

Under Clause 9.0.2.0 of the GCC, the General Manager (GM) of the Respondent must first determine whether a claim is a "notified claim" before the arbitrator can proceed.

Source reference: p. 2

While this determination process was underway in 2020, it stalled due to the COVID-19 pandemic and alleged communication failures by the Respondent.

Source reference: p. 3

Consequently, the Appellant sought a remedy under Section 18(1) of the MSME Act before the Facilitation Council (MSMFC).

Source reference: p. 4

On April 4, 2025, the MSMFC dismissed the reference, holding the Appellant was not a "supplier" under Section 2(n) of the Act.

Source reference: p. 4

When the Appellant subsequently attempted to resume the GCC arbitration process, the Respondent failed to respond, leading the Appellant to file a Writ Petition.

Source reference: p. 1, 4

The Single Judge dismissed the petition as non-maintainable on January 7, 2026.

Source reference: p. 1, 4
02

Issues

1. Whether electing to seek a remedy under the MSME Act precludes or extinguishes a party's right to pursue arbitration under the original contract.

Source reference: p. 4, para 13-14

2. Whether the failure of the Respondent to complete the mandatory determination under Clause 9.0.2.0 of the GCC renders the Appellant remediless.

Source reference: p. 5, para 17

3. Whether the time spent pursuing proceedings under the MSME Act should be excluded for the purposes of limitation.

Source reference: p. 5, para 18
03

Law Applied

General Conditions of Contract (GCC) (Clauses 9.0.1.0 to 9.0.3.0), which establish a two-tier process requiring a departmental determination of "notified claims" as a precursor to arbitration.

Source reference: p. 2-3

Micro, Small & Medium Enterprises Development Act, 2006 (MSME Act), specifically Sections 2(n) and 18, to determine if it contained any provision for the automatic exclusion of contractual remedies upon the rejection of an MSME reference.

Source reference: p. 4-5

General principles of equity and the law of limitation regarding the "theory of abandonment" and the exclusion of time spent in bona fide litigation in alternate forums.

Source reference: p. 5
04

Reasoning

The Court rejected the Respondent’s "theory of abandonment," which argued that by approaching the MSMFC, the Appellant had waived its right to arbitration.

Source reference: p. 4

The Court reasoned that seeking a remedy under the MSME Act—on the mistaken assumption of eligibility—does not non-suit a party from original contractual remedies unless specifically prohibited by statute, which the Respondent failed to demonstrate.

Source reference: p. 4-5

The Court held that the Respondent had a contractual duty to conclude the Clause 9.0.2.0 determination and could not benefit from its own omission or the pandemic-induced hiatus to render the Appellant remediless.

Source reference: p. 5

Regarding limitation, the Court found that since the Appellant legitimately exercised its right to approach the MSMFC, the time spent in those proceedings and the subsequent writ petition must be excluded to prevent the claims from being time-barred.

Source reference: p. 5-6
05

Holding

The Court set aside the Single Judge’s order and allowed the appeal.

The Court held that the original invocation of arbitration remains valid and that the Respondent's General Manager must complete the determination under Clause 9.0.2.0 within eight weeks.

Source reference: p. 6, para 19

The Court specifically ordered that the period from the initial invocation until the date of this judgment shall be excluded for the purposes of limitation.

Source reference: p. 6, para 19

The MSME order, having not touched upon merits, shall have no effect on future proceedings.

Source reference: p. 6
Delhi High Court

Original Court PDF

Newton Engineering And Chemicals LimitedvsIndian Oil Corporation Ltd.

Delhi High Court · April 16, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment