01Facts
The Appellant (Company) and Respondent (Corporation) entered into a contract in 2011 for mechanical and piping works at the Mathura Refinery.
pp. 1-2Upon completion, disputes arose, and the Appellant invoked arbitration under the General Conditions of Contract (GCC).
p. 2Under Clause 9.0.2.0 of the GCC, the General Manager (GM) of the Respondent must first determine whether a claim is a "notified claim" before the arbitrator can proceed.
p. 2While this determination process was underway in 2020, it stalled due to the COVID-19 pandemic and alleged communication failures by the Respondent.
p. 3Consequently, the Appellant sought a remedy under Section 18(1) of the MSME Act before the Facilitation Council (MSMFC).
p. 4On April 4, 2025, the MSMFC dismissed the reference, holding the Appellant was not a "supplier" under Section 2(n) of the Act.
p. 4When the Appellant subsequently attempted to resume the GCC arbitration process, the Respondent failed to respond, leading the Appellant to file a Writ Petition.
p. 1, 4The Single Judge dismissed the petition as non-maintainable on January 7, 2026.
p. 1, 402Issues
i.1. Whether electing to seek a remedy under the MSME Act precludes or extinguishes a party's right to pursue arbitration under the original contract.
pp. 4, para 13-14ii.2. Whether the failure of the Respondent to complete the mandatory determination under Clause 9.0.2.0 of the GCC renders the Appellant remediless.
p. 5, para 17iii.3. Whether the time spent pursuing proceedings under the MSME Act should be excluded for the purposes of limitation.
p. 5, para 1803Law Applied
General Conditions of Contract (GCC) (Clauses 9.0.1.0 to 9.0.3.0), which establish a two-tier process requiring a departmental determination of "notified claims" as a precursor to arbitration.
pp. 2-3Micro, Small & Medium Enterprises Development Act, 2006 (MSME Act), specifically Sections 2(n) and 18, to determine if it contained any provision for the automatic exclusion of contractual remedies upon the rejection of an MSME reference.
pp. 4-5General principles of equity and the law of limitation regarding the "theory of abandonment" and the exclusion of time spent in bona fide litigation in alternate forums.
p. 5Provisions in the judgment · 2 · Linked ones open on LawLens
Micro, Small and Medium Enterprises Development Act, 2006 Section 2Section 18
04Reasoning
The Court rejected the Respondent’s "theory of abandonment," which argued that by approaching the MSMFC, the Appellant had waived its right to arbitration.
p. 4The Court reasoned that seeking a remedy under the MSME Act—on the mistaken assumption of eligibility—does not non-suit a party from original contractual remedies unless specifically prohibited by statute, which the Respondent failed to demonstrate.
pp. 4-5The Court held that the Respondent had a contractual duty to conclude the Clause 9.0.2.0 determination and could not benefit from its own omission or the pandemic-induced hiatus to render the Appellant remediless.
p. 5Regarding limitation, the Court found that since the Appellant legitimately exercised its right to approach the MSMFC, the time spent in those proceedings and the subsequent writ petition must be excluded to prevent the claims from being time-barred.
pp. 5-605Holding
The Court set aside the Single Judge’s order and allowed the appeal.
p. 6The Court held that the original invocation of arbitration remains valid and that the Respondent's General Manager must complete the determination under Clause 9.0.2.0 within eight weeks.
p. 6, para 19The Court specifically ordered that the period from the initial invocation until the date of this judgment shall be excluded for the purposes of limitation.
p. 6, para 19The MSME order, having not touched upon merits, shall have no effect on future proceedings.
p. 6Original Court PDF
Newton Engineering And Chemicals LimitedvsIndian Oil Corporation Ltd.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
